USDA Feasibility Study for Solar, Renewable Energy and Microgrids in Alaska

    NAICS 221114

    Renewable energy and microgrid projects in Alaska are bankable on validated load data, from $8 diesel in rural villages to a Railbelt gas shortfall from 2028. A USDA feasibility study validates diesel-displacement modeling against utility load data and plans bridge financing for the build-first REAP sequence.

    USAspending lists 55 Alaska REAP grant records for FY2024 to FY2026, so the program is heavily used here, and the rule that took effect on 16 October 2026 changes how each of those projects is financed. A REAP grant now arrives only after the system has run for a year, it is capped at a quarter of cost, and grant plus guaranteed loan may not exceed three quarters. In Alaska, where a short construction season and barge freight push cost to the front, the study's job is to show that the energy saved pays the construction loan without the grant.

    Program Fit

    REAP, B&I, and RUS High Energy Cost Grants all apply; under the revised REAP rule effective October 16, 2026, projects must be fully built and operating before applying. (Other pages on this site have reported a 2025 USDA policy barring solar and wind from B&I; that policy is not confirmed in this page's federal sources, so B&I eligibility for a solar project should be confirmed with the state office.)

    The REAP rule effective 16 October 2026

    The rule (91 FR 62600) appeared on 1 October 2026, six months after USDA withdrew its FY2025 to FY2027 REAP funding notice. Its main terms, read for Alaska:

    TopicRule effective 16 October 2026Alaska consequence
    TimingProject Period ends 12 to 24 months before the application (12 to 36 in the first window)Build with loan and bridge money; apply for the grant a year later
    Data12 months of actual production or savings and 12 months of pre-installation dataUtility or generator logs before and after
    Award size$1,500 minimum; $500,000 for renewable systems, $250,000 for efficiencyGrants cover less of large microgrids
    Cost shareGrant at most 25% of costOwner and lender carry at least 75%
    Combined fundingGrant plus guaranteed loan at most 75% of costOwner funds of at least 25%
    SizingGround-mount systems need commensurate historical use; storage at most 120% of prior annual useBattery sizing tied to load records
    ExclusionsStand-alone storage, storage retrofits, EV chargers, distribution-only projectsStorage only as part of a generating system
    Foreign componentsComponents from a foreign adversary under 15 CFR 791.4 ineligibleCountry of origin for every component
    EconomicsSimple payback must not exceed useful lifePayback tested as eligibility
    Applicant and siteOne application a year per highest-level owner; site control 12 months before the Project Period; one locationOwnership and lease evidence
    InstallersLicensed in the state with at least three similar installationsInstaller qualifications in the file

    USDA's own text points borrowers to the Part 5001 REAP guaranteed loan for up-front costs; no funding notice under the new rule had been published by 7 November 2026.

    RouteFit for an Alaska energy projectDeciding condition
    REAP guaranteed loanSolar, battery storage with generation, heat pumps, hydro and efficiency at rural businessesFY2026: 80% guarantee, 1.0% fee, 0.25% retention; grant plus loan at most 75% of cost
    REAP grantReimbursement after 12 months of operationAt most 25% of cost, $500,000 cap for renewable systems
    RUS High Energy Cost GrantsCommunity energy projects where home energy costs exceed 275% of the national average$100,000 to $3,000,000 awards; latest round up to $10 million (hub)
    Alaska Energy Authority Renewable Energy FundCommunity and utility renewable projectsRound 18 recommends 29 projects, $41,164,051 (hub); appropriation needed
    B&I guaranteeKept from the live page; confirm current USDA policy for solarOff-road tier 90% where it applies

    Because REAP loans sit in Part 5001, the 5001.127 screens apply too: a federal judgment, overdue federal tax or loan, or a debarment against the borrower or a 20 percent owner disqualifies it, as does gambling income above 15 percent.

    Required by rule or requested by the lender

    This page's federal sources do not include REAP's own technical-report requirement, so the study requirement is described from Part 5001: a new business borrowing above $1,000,000 under a guarantee must commission an independent study (5001.306(a)(3)(i)), and the hub adds that 5001.303(c)(4) lets the Agency require one whenever repayment is unclear. Under the build-first rule, the lender is financing the whole system before any grant, which is when it usually asks for a study.

    What the Study Covers

    Framed to the scope required by 7 CFR Part 5001 Appendix A for OneRD guaranteed loan submissions.

    • Market demand and competitive supply analysis
    • Technical and site feasibility, including environmental considerations
    • Five to ten year financial projections with DSCR, DCF, and sensitivity analysis
    • Management and operational capacity assessment
    • Economic feasibility and rural community impact

    For an Alaska system the "market" is the host's own load and its alternatives: diesel generation, the local utility tariff, Power Cost Equalization where relevant, and heating fuel. The technical chapter covers winter solar resource, snow and wind loading, battery performance in cold, integration with an existing diesel or utility grid, and the barge or air freight that sets installed cost.

    Alaska Market Evidence

    USDA High Energy Cost Grants in 2023–24 included $3,000,000 for run-of-river hydro in Tenakee Springs and $2,800,000 for solar and battery storage in Venetie, and Koniag, Inc. received $247,778 in REAP funds for solar and battery storage at the Kodiak Brown Bear Center.

    Solar and renewable generation in Alaska: market evidence

    Alaska: solar and other renewable power generation, supply and rural footprint

    MeasureAlaskaUnited States
    Establishments, 2019 → 20233 → 0 (-100.0%)405 → 942
    Per 100,000 residents (2023)0.00.3
    Share of state population in non-metro counties (2025)32.2%

    Sources: U.S. Census Bureau, County Business Patterns 2019 and 2023 (state and county files; establishments with paid employees; employment and payroll suppressed in some cells); Vintage 2025 county population estimates; OMB metropolitan statistical area delineation, July 2023. Non-metro county is a proxy for USDA rural eligibility, not the eligibility test itself.

    Interpretation. Census counted three renewable generating establishments with paid staff in Alaska in 2019 and none in 2023, while the national count more than doubled to 942. That series measures companies selling power, not the lodges, processors and tribal organisations that host REAP and High Energy Cost projects, so it shows that Alaska has no merchant renewable sector rather than no renewable activity. For underwriting, the consequence is that savings must come from the host's own use or from a utility or community buyer, and the study has to document that buyer.

    Alaska next to Washington and Hawaii (computed)

    Alaska has no land neighbour among the states; Washington and Hawaii are the nearest Pacific comparables. Rows are each state's own pack data.

    StateCensus count 2019 → 2023Per 100,000 residentsAvg. employeesAvg. payIn non-metro counties (of those placed)SBA 7(a) loans FY2020-26 (avg.)
    Alaska (this page)3 → 00.0suppressedsuppressednone placed0 (none)
    Washington0 → 40.15.8$210,478none placed2 ($1,852,500)
    Hawaii0 → 80.62.0$87,5000 of 72 ($1,400,000)
    United States→ 9420.312.3$138,631138 ($478,591)

    Hawaii, another isolated, fuel-import grid, grew from no generating establishments to eight and saw two recent SBA 7(a) loans averaging $1,400,000; Washington went from none to four. Neither is a close comparable for a village microgrid, but Hawaii shows how island grids attract solar once fuel costs are high.

    Railbelt gas, rural diesel and precedent

    The Alaska hub sets out the economics. Chugach Electric's firm Cook Inlet gas supply ends in 2028, and Enstar reported being 18 days of supply short for winter 2026 to 2027 at normal temperatures; rural heating fuel averaged a record $7.97 per gallon in summer 2026. USDA High Energy Cost Grants in 2023 and 2024 included $3,000,000 for hydro in Tenakee Springs, $2,907,000 for heat recovery in Nome and $2,800,000 for solar and battery storage in Venetie. Koniag's REAP project at the Kodiak Brown Bear Center was expected to save $54,636 a year, with a further $40,000 for heat pumps (October 2024). Other Alaska REAP awards on the hub include Lake Louise Lodging ($94,930, solar and battery), Frontier Assisted Living in Fairbanks ($134,600, 100 kW solar) and Northern Honey in Delta Junction ($32,000, solar). The hub's reviewer tests are diesel-displacement modelling validated against utility load data, interaction with Power Cost Equalization, begin-construction evidence for federal tax credits confirmed with tax counsel, and bridge financing for the build-first REAP sequence.

    Rural footprint and B&I eligibility in Alaska

    The pack places no generator by county; 32.2% of Alaskans lived in non-metro areas in 2025. REAP guaranteed loans use Part 5001's rural definition (7 CFR 5001.3), and the hub reports USDA's Alaska guidance that only the Municipality of Anchorage is excluded. The hub adds one Alaska-specific caution: at least one REAP technical-assistance provider describes Juneau as excluded for REAP as well, although Juneau is below 50,000, so a Juneau project's eligibility is confirmed with the state office in Palmer. The Alaska hub also lists Eagle River, Chugiak and Girdwood as excluded.

    Financing benchmarks: REAP and B&I next to SBA

    SBA's files show no Alaska solar or renewable generation loan in FY2010 to FY2026, so only the national series is available.

    United States: SBA lending to solar and other renewable power generation (computed from the pack's national columns)

    PeriodU.S. 7(a) loansU.S. 7(a) dollarsAvg. 7(a) loanU.S. 504 loansU.S. 504 dollars
    FY2010 to FY201631$15,254,800$492,09010$9,457,000
    FY2017 to FY201929$12,362,600$426,2974$1,842,000
    FY2020 to FY202368$35,163,500$517,11014$9,184,000
    FY2024 to FY202670$30,882,100$441,1733$1,672,000

    Source: SBA 7(a) and 504 FOIA loan data, as of 30 Sep 2026 (project state; disbursed loans only; cancelled and undisbursed loans excluded). Computed from the national columns of the Alaska pack.

    The national loss record is poor: four of 31 renewable-generation 7(a) loans made in FY2010 to FY2016 were charged off, 12.9%, after about 51 months on average. Those were mostly businesses selling power. A host-owned system displacing $8 diesel is a different credit, but a lender will want the savings proven from metered data, which is now what REAP requires too.

    Program term (FY2026, 91 FR 11272)REAP guaranteed loanB&I under $5 millionB&I off-road Alaska tier
    Guarantee80%85%90%
    Upfront fee1.0%3.0%1.0%
    Annual retention fee0.25%0.55%0.50%
    Guarantee issued before construction is completeadditional 0.50%additional 0.50%additional 0.50%

    Worked example (illustrative)

    Inputs: an illustrative $400,000 solar array with battery storage at a rural business that today buys diesel-generated or high-tariff power, fixed 7.0%, 20-year amortization, a 20-year useful life for the payback test, and FY2026 REAP loan terms. In scenario A a REAP guaranteed loan covers three quarters of cost with no grant; in scenario B a quarter-of-cost grant arrives after a year of operation and the loan shrinks so that grant and loan together stay at three quarters.

    ItemA: loan only, no grantB: 25% grant plus loan
    Total project cost (illustrative)$400,000$400,000
    REAP grant (at most 25% of cost and $500,000; paid after 12 months of operating data)$0$100,000
    REAP guaranteed loan (grant plus loan at most 75% of cost)$300,000$200,000
    Owner funds (at least 25% of cost)$100,000$100,000
    Guaranteed amount at 80%$240,000$160,000
    Upfront guarantee fee (1.0% of guaranteed)$2,400$1,600
    First annual retention fee (0.25% of guaranteed balance after 12 payments)$585.73$390.48
    Rate and amortization (illustrative)7.0%, 20 years7.0%, 20 years
    Monthly payment$2,325.90$1,550.60
    Annual debt service$27,910.76$18,607.17
    Annual energy savings or revenue for 1.25x coverage$34,888.45$23,258.97
    Annual debt service if the rate is 2 points higher$32,390.13$21,593.42
    Simple payback ceiling: savings needed so that cost / savings does not exceed a 20-year useful life$20,000$20,000

    The owner funds $100,000 in both cases. Without a grant, the system must save $34,888.45 a year for 1.25x coverage, which for scale equals about 4,377 gallons of heating fuel at the summer 2026 rural average of $7.97 (computed). With the grant the requirement falls to $23,258.97, but the $100,000 arrives a year after completion, so the project needs bridge money in the meantime. Savings of $20,000 a year keep simple payback within a 20-year life. Because the guarantee fee is charged on 80 percent of the loan, the closing fee is only $2,400 in scenario A.

    What a lender-grade solar and microgrid feasibility study in Alaska must prove

    1. Load and the fuel it displaces. Twelve months of utility bills or generator logs, with the diesel, gas or tariff cost each kilowatt-hour replaces.
    2. Winter performance. Solar output by month at the site's latitude, snow loading and battery behaviour in cold.
    3. PCE and tariff interaction. How Power Cost Equalization and the utility's rates affect the savings the host actually keeps.
    4. A no-grant base case. Debt service covered from savings alone, with the grant as later upside.
    5. Railbelt price scenarios. For Railbelt sites, savings under current rates and under post-2028 gas or LNG pricing.
    6. Rule compliance. Storage within 120 percent of prior use, no stand-alone storage, component origin, one site, site control and installer qualifications.
    7. Freight and construction season. Barge or air schedules and a construction calendar with contingency.
    8. Tax-credit timing. Begin-construction evidence confirmed by tax counsel, as the hub advises.

    Risks and mitigants in Alaska

    RiskAlaska signalMitigant in the study
    Grant timingGrant after 12 months of operation (rule)Bridge financing, no-grant base case
    Winter outputLow winter sun at high latitudeMonthly production model, battery sizing
    Fuel price swingsHeating fuel at a record $7.97 (hub)Savings at several fuel prices
    Gas transitionFirm Railbelt gas ends 2028 (hub)Tariff scenarios for Railbelt hosts
    Freight and seasonBarge-dependent construction (hub)Fixed schedule and contingency
    EligibilityJuneau REAP status unclear (hub)Written confirmation from Palmer

    Process, documents and what gets a study sent back

    The host provides twelve months of bills or generator fuel logs, the utility tariff and any PCE details, installer proposals with component origin and cold-weather specifications, freight quotes, proof of site ownership or a lease of at least 12 months, three years of financial statements, and the personal statements and guarantees of 20 percent owners under 5001.204. Studies come back when output is modelled on annual averages, when savings use a fuel price the host does not pay, when storage exceeds 120 percent of prior use, or when the grant is treated as construction money.

    Program evidence, honestly labelled

    The Alaska hub lists the REAP and High Energy Cost awards above; none is a REAP guaranteed loan under the new rule, which is too recent for precedent. The Koniag project is kept from the live page.

    Recently Funded Projects

    Koniag, Inc. (Kodiak Brown Bear Center)

    $287,778

    Solar and battery storage; heat pumps (REAP)

    Kodiak Island

    Program evidence: USDA-financed projects as publicly reported.

    The $287,778 combines the $247,778 solar and battery award and the $40,000 heat-pump award reported on the hub (computed). The Pennsylvania rooftop solar case study further down is a library example outside Alaska with a $1.37M modelled loan, not a reported Alaska financing. For REAP and renewable evidence beyond Alaska, see the national renewable energy feasibility study page.

    Hiring a USDA solar and renewable energy feasibility study consultant in Alaska

    When it is required. By rule above $1,000,000 of guaranteed debt to a new business; otherwise at the lender's or Agency's request, which under the build-first rule is the normal case for any project financing its full cost up front.

    What the engagement includes. Energy-project scope, component by component: load and displaced-fuel analysis, system sizing and cold-climate technical review, the rule's eligibility screens, projections with and without the grant and with fuel-price, output and rate sensitivities, and a management assessment. Expect, from the cost page, the PDF and Word report, the Excel model, kickoff and midpoint calls and one revision round, backed by a written guarantee that the firm keeps revising without charge until the report is accepted.

    What you provide. Bills or fuel logs, tariff and PCE details, installer proposals, freight quotes, site documents and financial statements.

    Fees and timing. The cost page prices REAP studies at $4,900 to $8,500 over four to five weeks where the guaranteed loan is under $600,000, and $7,500 to $11,500 over five to seven weeks above it. Rush delivery, subject to analyst availability, takes three to four weeks at a 20 to 35 percent mark-up.

    How to start. Send the community, the current energy source and twelve months of bills or fuel logs through the Get Your Free Consultation form at the bottom of this page; within a day the firm replies, and a written proposal with the fee fixed comes after the consultation. An independent USDA feasibility study consultant has no link to the installer or the battery supplier, and a solar feasibility study consultant can check the storage-sizing and component-origin rules on the first call.

    Last updated 2026-11-08

    David Miller, CPA

    USDA Feasibility, Inc.

    Frequently Asked Questions

    Does USDA require a feasibility study for a solar or renewable energy project in Alaska?

    Part 5001 requires an independent study for guaranteed loans above $1,000,000 to a new business (5001.306(a)(3)(i)), and lets the Agency require one where repayment is unclear. Most Alaska REAP projects are smaller, but since the rule of 16 October 2026 the grant comes a year after the system operates, so lenders financing the full cost usually ask for a study of the savings.

    What does 7 CFR Part 5001 require the study to contain?

    Independent conclusions on economic, market, technical, financial and management feasibility. For an Alaska system, market means the host's load and the fuel or tariff it displaces; technical covers winter output, battery behaviour, grid integration and the rule's screens; financial means savings, debt service and payback with and without the grant; management covers ownership, operation and maintenance in a remote setting.

    How is a solar or renewable energy project evaluated in a USDA feasibility study?

    Twelve months of bills or generator logs set the baseline; modelled output is matched to load month by month, with winter and summer shown separately, and each kilowatt-hour is valued at the fuel or tariff it replaces, after PCE effects. Savings are then set against debt service: in this page's $400,000 example, a no-grant REAP loan needs $34,888.45 a year for 1.25x coverage, and payback must stay within the system's life.

    How long does a USDA feasibility study take in Alaska?

    REAP-scale studies on the cost page take four to five weeks under $600,000 of guaranteed loan and five to seven weeks above it; rush delivery takes three to four. Gathering a year of generator logs or utility data is often the slow part in rural Alaska. The grant application itself waits until the system has run for 12 months, so the study's first use is the construction loan.

    How does the FY2026 85 percent guarantee affect solar or renewable energy projects under $5 million?

    Eighty-five percent is the FY2026 B&I guarantee below $5 million (91 FR 11272), and 90 percent the Alaska off-road B&I rate. Most Alaska solar projects use the REAP guaranteed loan instead: 80 percent guaranteed, a 1.0 percent fee and 0.25 percent retention. On the $300,000 loan in this page's no-grant example, that is $240,000 guaranteed and a $2,400 fee. Confirm B&I eligibility for solar with the state office before relying on it.

    Who prepares a solar or renewable energy feasibility study in Alaska?

    An analyst with energy and USDA experience who is independent of the host, the installer, the equipment suppliers and the lender, and acceptable to the Agency. The Alaska state office in Palmer decides acceptability for each application; no approved list is published. Under the new rule, modelled production must be reconciled with metered data, a task best done by someone with no stake in the installation.

    What does a solar feasibility study consultant cost in Alaska?

    The cost page lists $4,900 to $8,500 for REAP studies with a guaranteed loan under $600,000 and $7,500 to $11,500 above that, where full debt service and rate modelling are needed. A lodge or business array with good bills usually fits the first band; a microgrid with diesel integration may fit the second. The written proposal states the fee before any work starts.

    How long does an Alaska solar study stay current?

    Part 5001 sets no expiry, but fuel prices, utility rates and tax-credit rules all moved in 2025 and 2026. The cost page treats USDA data under about 18 months old as current. Because a REAP grant application now comes at least a year after the system starts, plan to update the study with twelve months of actual output at that point.

    Can the same solar study serve an SBA lender and USDA?

    Yes, if prepared to Part 5001; 13 CFR 120.160(b) lets an SBA lender insist on a study and sets no template for it. SBA's files show no Alaska solar-generation loan, and nationally 12.9 percent of seasoned SBA solar loans were charged off, so any lender will want savings modelled from the host's own records rather than from generic production estimates.

    Can an Alaska solar project include battery storage under REAP?

    Yes, as part of a generating system, within limits. The rule effective 16 October 2026 excludes stand-alone storage and storage retrofits and limits storage to 120 percent of prior annual use, and ground-mount systems must show historical energy use that matches their size. A study sizes the battery from twelve months of load data and shows how it shifts solar output into evening and winter use.

    Is a Juneau renewable energy project eligible for REAP?

    Probably, but confirm it. The Alaska hub notes that at least one REAP technical-assistance provider describes REAP rural areas as excluding Juneau as well as Anchorage, even though Juneau is below the 50,000 population line in 7 CFR 5001.3. Because applications cannot be approved subject to meeting the rural test, a Juneau sponsor should get the state office's written view in Palmer before building.

    Other project types in Alaska

    Hotels and Resorts · RV Parks and Campgrounds · Restaurants and Food Service · Event Venues and Tourism Attractions · Manufacturing and Resource-Sector Support · Food and Seafood Processing · Back to all Alaska project types

    Sources

    1. U.S. Census Bureau, County Business Patterns 2019 and 2023, state and county files: https://www.census.gov/programs-surveys/cbp.html
    2. U.S. Census Bureau, Vintage 2025 county population estimates: https://www.census.gov/programs-surveys/popest.html
    3. Office of Management and Budget, metropolitan statistical area delineation, July 2023 (Census delineation files): https://www.census.gov/geographies/reference-files/time-series/demo/metro-micro/delineation-files.html
    4. U.S. Small Business Administration, 7(a) and 504 FOIA loan data, as of 30 Sep 2026: https://data.sba.gov/dataset/7-a-504-foia
    5. 7 CFR Part 5001, OneRD Guaranteed Loanmaking and Servicing, CFR 2026 edition (govinfo): https://www.govinfo.gov/content/pkg/CFR-2026-title7-vol15/xml/CFR-2026-title7-vol15-part5001.xml
    6. 91 FR 11272, OneRD annual notice of guarantee fee rates, retention fee rates and guarantee percentages for FY2026 (govinfo): https://www.govinfo.gov/content/pkg/FR-2026-03-09/html/2026-04581.htm
    7. 90 FR 57351, OneRD guaranteed loan regulation technical amendments, December 11, 2025 (govinfo): https://www.govinfo.gov/content/pkg/FR-2025-12-11/html/2025-22567.htm
    8. 13 CFR Part 120, SBA business loan programs: https://www.ecfr.gov/current/title-13/chapter-I/part-120
    9. USAspending.gov award counts, Assistance Listings 10.768 (B&I), 10.766 (Community Facilities) and 10.868 (REAP), Alaska place of performance, FY2024 to FY2026: https://www.usaspending.gov/search
    10. REAP final rule with comment period, 91 FR 62600 (1 Oct 2026), effective 16 Oct 2026 (govinfo): https://www.govinfo.gov/content/pkg/FR-2026-10-01/html/2026-20178.htm
    11. Notice of Rescission of Funding Opportunity for REAP, 91 FR 20090 (15 Apr 2026) (govinfo): https://www.govinfo.gov/content/pkg/FR-2026-04-15/html/2026-07332.htm
    12. Neighbouring-state data packs (Washington, Hawaii), built from sources 1 to 4
    13. Alaska hub sources reused here (RUS High Energy Cost Grant charts and NOFO, REAP charts, Alaska Energy Authority Renewable Energy Fund, Chugach and Enstar gas supply, DCCED fuel price report, Juneau REAP question, Anchorage exclusion, off-road tier, lender standing): /alaska
    14. USDA Feasibility Study Consultants, cost and timeline page: /usda-feasibility-study-cost

    Data current as of November 2026.

    Ready to Start Your USDA Project?

    Get your free consultation today and take the first step toward securing USDA funding for your rural development project.

    Our USDA feasibility study consultants scope every engagement against the five Part 5001 components in a free consultation.