Assisted Living Expansion Feasibility: Kansas USDA Feasibility Study Case Study

    Last updated 2026-11-08

    How to read this case study. The engagement summary reflects the published record. Client names, actual costs, loan terms and proprietary data are confidential, so the project budget, market sizing and financial projections below are a modeled example built from public data for this project type and location. They show the analysis a lender-grade study performs, not the client's figures.

    In 2024 a community bank lending with a USDA guarantee needed a feasibility study for an assisted living expansion in Dodge City, Kansas, financed under the Community Facilities (CF) guaranteed loan program in the $5 million to $25 million loan tier. The study was prepared with a market and demand study. This page works through the questions such a study has to answer, using a modeled 40-unit expansion (24 assisted living apartments and 16 memory care suites added to an existing 40-unit nonprofit campus) and public data for Ford County and the six counties around it.

    The short version: Dodge City is too large for CF direct money but squarely inside the CF guaranteed rural area; the 90% occupancy ceiling in the CF rule leaves a thin margin above break-even; and the lease-up year, not the stabilized year, decides whether the sponsor's cash is enough. Data current as of November 2026.

    Engagement summary

    Published recordDetail
    ProgramUSDA Community Facilities guaranteed loan
    AssetAssisted living (expansion of an existing community)
    LocationDodge City, Kansas (Ford County, Great Plains region)
    Loan size tier$5 million to $25 million
    Year2024
    LenderCommunity bank with a USDA guarantee
    OutcomePrepared with market and demand study

    Source: this site's engagement index [16]. Everything else on this page (scope, budget, demand, rates, staffing and projections) is a model.

    The engagement card on the index also carried a longer summary. Several of its statements can be checked against the regulations and data this site holds; others cannot, and some need correcting. The table sets out what this page keeps and on what basis.

    Statement in the engagement cardStatus on this page
    CF guaranteed loans: up to $100 million per borrower, terms up to 40 yearsKept; matches 7 CFR part 5001 [1]
    Initial fee 1.25% of the guaranteed amount, 80% guaranteeKept for FY2026 (91 FR 11272) [5]; the card's "FY2025" label could not be checked against a FY2025 notice and is not used
    Kansas does not require a certificate of need for assisted livingKept; this site's Kansas page records it, citing NCSL [13]
    Study delivered at a "CF Financial Feasibility Study with Review Report standard", the "appropriate tier" for $5M to $25MCorrected. Part 5001 names a financial feasibility analysis (appendix B), a financial feasibility study with a CPA examination opinion, and an independent feasibility study for a new entity or activity; it has no "review report" tier, and loan size alone does not pick the type (5001.304) [1][2]
    Kansas assisted living averages $5,149 to $6,026 a month and memory care $5,587 (2024)Kept only as the card's figures; no source in this site's data. The model's rates are its own assumptions
    Kansas Frail Elderly waiver income threshold $2,829 a month and asset limit $2,000Kept only as the card's figures; to be confirmed against the state's current waiver rules
    National occupancy of 85.7% (Q4 2024) and 88.1% (Q2 2025), record occupied units, 1.3% inventory growth, 80+ population growth to 2030Not used; national trend figures with no source in this site's data
    West North Central assisted living occupancy below the national averageNot used; no source in this site's data
    A 40-bed community in Salem, Wisconsin filled within a yearNot used; an out-of-state anecdote with no source
    Form HUD-935.2A (Affirmative Fair Housing Marketing Plan) required for five or more residential unitsKept as the card's statement; the requirement is not in the rules this site has read and should be confirmed with the lender

    The question the lender and USDA needed answered

    A CF guaranteed loan is made by an approved lender; USDA guarantees part of it. Before the State Office issues a conditional commitment, the lender has to show the borrower is eligible, the project is in an eligible rural area, and the facility will generate enough cash to operate, fund reserves and repay the debt. Part 5001 makes the paperwork explicit for Community Facilities: a financial feasibility report is always required, and its form depends on the borrower and the loan [1][2].

    Borrower situation (CF guaranteed, 7 CFR 5001.304)Report the lender submits
    Existing facility, loan of $25 million or lessFinancial feasibility analysis under appendix B; the lender's credit evaluation can serve
    Debt backed by general obligation bonds or tax revenueFinancial feasibility analysis
    Three years of audited statements showing capacity to payFinancial feasibility analysis
    All other loansFinancial feasibility study with an examination opinion by a CPA under AICPA attestation standards
    Loan over $1,000,000 to a new entity or an entity starting a new activityIndependent feasibility study by a qualified consultant acceptable to the Agency, scope set by the Agency

    Source: 5001.304 and appendices A and B to subpart D [1][2].

    An expansion by an established operator usually starts in the first row. Two features of this kind of project can move it down the table. Memory care is the first: an operator that has never run a secure memory care unit is, for many reviewers, starting a new activity, and at this loan size that brings the independent study requirement. The second is the debt itself: if the existing campus cannot show three audited years of capacity to pay, the lender may not be able to rely on a simpler analysis. The published record states the study was prepared with a market and demand study; the work the State Office needed in either case was the same. It had to prove that the service area holds enough income-qualified seniors for 40 more units, that the campus fills them under a 90% occupancy ceiling, and that the combined campus covers the new debt service through lease-up.

    The occupancy rule is specific to senior care. Under 5001.304, CF projections for assisted living, skilled nursing and similar residential facilities may assume no more than 90% occupancy [1]. That ceiling governs every number in the projections below; it is not a target the model is free to exceed even if the market study finds a waiting list.

    Eligibility: why a guarantee and not CF direct

    TestRuleDodge City result
    CF direct loan population limitCity or town of 20,000 or less (7 CFR 1942.17) [3]Not eligible: 27,793 residents in the Census Bureau's April 2020 estimates base, 27,653 in July 2025 [8]
    CF grant population limit20,000 or less, plus a service-area income test (7 CFR 3570.53) [4]Not eligible on population
    CF guaranteed rural areaOutside any city or town of more than 50,000 and the urbanized area contiguous to it (7 CFR 5001.3) [1]Eligible on population; Ford County is a non-metro county in the OMB July 2023 delineation [9]; the parcel is confirmed on the USDA eligibility map
    CF guaranteed funding priorityFunds reserved first for places of 20,000 or less, released on 1 July for places up to 50,000 (5001.103(c), 5001.316(e)) [1]Outside the reserved pool; timing matters
    Borrower typePublic body, nonprofit with significant community ties, tribe, or a corporation operated on a not-for-profit basis for the life of the loan [1]Modeled as a local nonprofit with a board drawn from the service area
    Credit elsewhereBorrower certifies it cannot finance the project without the guarantee at reasonable terms [1]Lender documents it in the credit memo
    Local supportCertification of support from each affected local government [1]City and county letters

    Dodge City sits in a gap that shapes the whole financing plan. It is too large for CF direct loans and grants, which stop at 20,000, but it is far below the 50,000 line in the OneRD rural definition. A CF guarantee is therefore the main USDA route for a nonprofit borrower here. The same population count also costs the project the 15 priority points CF guaranteed scoring gives communities under 20,000, and it puts the application outside the pool reserved for small places until that reservation lapses each July [1]. A study that knows this sets its schedule around the State Office's funding calendar rather than the construction calendar.

    B&I is the other OneRD route, but it finances assisted living only where constant medical care is provided and available on site, and it carries a 3.0% fee against 1.25% for a CF guarantee [1][5]. For a nonprofit campus, CF is the natural fit.

    Project description (modeled)

    The model assumes an established nonprofit operating 40 assisted living apartments on an owned, debt-free campus, at 88% occupancy before the expansion. The expansion adds a 29,500 square foot wing and renovates the shared dining, kitchen and common areas so that one kitchen and one administrative team serve 80 units.

    Modeled scopeBeforeAfter
    Assisted living apartments4064
    Memory care suites (secure)016
    Total units4080
    Staff (full-time equivalents)24.041.3
    Building area added29,500 sq ft new wing; 4,500 sq ft renovated
    Modeled timelineMonths from engagementNotes
    Feasibility study and appraisal0 to 2This site's schedule lists 6 to 8 weeks for a Community Facilities study [15]
    Lender credit evaluation and State Office application2 to 5Conditional commitment depends on CF guaranteed funding in the fiscal year
    Design completion, bids, closing5 to 8Fixed-price contract before closing
    Construction8 to 2214 months; existing building stays open
    Pre-opening hiring and marketing19 to 22Funded by the sponsor
    Lease-up to 90%22 to 32About 10 months in the model

    Project cost and sources and uses

    There is no construction-cost database behind this page, so every line below is an assumption, stated with a range and with the document a real study would rely on. A real budget comes from the architect's estimate, contractor bids, equipment quotes and the lender's term sheet.

    Use of funds (modeled)AmountShareAssumption range and how a real study sources it
    Site work, paving and utility extensions$620,0004.1%$450,000 to $900,000; civil engineer's estimate
    New wing, 29,500 gross sq ft at $300/sq ft$8,850,00059.1%$265 to $360 per sq ft; contractor bids
    Renovation of existing dining, kitchen and commons, 4,500 sq ft at $180/sq ft$810,0005.4%$140 to $230 per sq ft; contractor bids
    Secure memory care entry, wander management and campus nurse call$295,0002.0%$220,000 to $380,000; vendor quotes
    Generator and life safety upgrades to the existing building$240,0001.6%$150,000 to $350,000; engineer's estimate
    Hard cost subtotal$10,815,00072.3%
    Construction contingency, 7% of hard cost$757,0005.1%5% to 10%; higher for renovation
    Furniture, fixtures and equipment (40 units at $9,500 plus $160,000 commons)$540,0003.6%Vendor quotes
    Architecture and engineering, 7.5% of hard cost$811,0005.4%6% to 9%; design contract
    Permits, survey, geotechnical, environmental and testing$135,0000.9%Local fee schedules and quotes
    Builder's risk and construction-period insurance$70,0000.5%Broker quote
    Feasibility study, appraisal and review, legal, lender closing costs$210,0001.4%Engagement letters and lender term sheet
    CF guarantee fee, 1.25% of the 80% guaranteed share$114,6000.8%91 FR 11272 (FY2026)
    Interest during construction, 14 months, average draw 55% at 7.50%$551,5133.7%Draw schedule
    Pre-opening staffing, training and marketing (sponsor funds)$260,0001.7%Operator budget
    Lease-up and working capital reserve (sponsor funds)$700,0004.7%Sized from the monthly lease-up model
    Total project cost$14,964,112100.0%

    At $14,964,112 the expansion costs $374,103 per new unit, because the budget also carries the renovation, campus-wide life safety and nurse call work, the reserves and the financing costs. Three items follow the CF guaranteed rules. The 1.25% guarantee fee and interest during construction may be paid from loan funds, and Part 5001 allows interest for up to three years until the facility is self-supporting [1]. Initial operating expenses and working capital may not be paid with CF guaranteed loan funds (5001.122(m)) [1], so the pre-opening budget and the lease-up reserve sit with the sponsor.

    Source of funds (modeled)AmountShareNote
    CF guaranteed loan from the community bank$11,460,00076.6%80% guaranteed ($9,168,000); $2,292,000 at the bank's own risk
    Sponsor cash reserves$1,904,11212.7%Unrestricted cash on the closing balance sheet
    Capital campaign and foundation gifts collected before closing$1,600,00010.7%Pledges count only when collected or firmly scheduled
    Total$14,964,112100.0%

    The modeled loan of $11,460,000 sits inside the published $5 million to $25 million tier. At 80%, USDA guarantees $9,168,000 and the bank keeps $2,292,000 at its own risk. Part 5001 sets no fixed equity percentage for CF guaranteed loans; instead, committed other funds earn priority points, and the lender sets its own expectation in the credit evaluation [1]. The model's $3,504,112 of sponsor cash and gifts is 23.4% of cost.

    CF guaranteed priority factor (7 CFR 5001.316)Points availableThis modeled projectWhy
    Community of under 20,000 people150Dodge City had 27,793 residents in the Census Bureau's April 2020 base
    Health clinic, public safety, early education or primary/secondary education facility100An assisted living community is not one of the listed facility types
    Other funds committed: 5% to 19% / 20% to 49% / 50% or more5 / 10 / 1510Sponsor cash and gifts are 23.4% of project cost
    Administrator points from a National Office reserveup to 15not modeledDiscretionary

    The fee would be higher if the lender asked USDA to issue the loan note guarantee before construction is finished: the FY2026 notice adds 0.50% of the guaranteed amount for that [5].

    Market analysis

    Kansas supply and the statewide picture

    The state data module for Kansas shows a state that is already well supplied with senior care buildings [6][7][9]:

    Kansas: assisted living and nursing facilities, supply and rural footprint

    MeasureKansasUnited States
    Establishments, 2019 → 2023575 → 593 (+3.1%)43,506 → 44,649
    Per 100,000 residents (2023)20.113.3
    Average employees per establishment51.053.5
    Average annual pay per employee$36,435$41,324
    Share of establishments in non-metro counties26.1% (114 in 22 counties)
    Share of state population in non-metro counties (2025)28.8%

    Non-metro counties with the most assisted living and nursing facilities (2023): Crawford County (13); Reno County (13); Montgomery County (9); Saline County (8); McPherson County (7); Brown County (6).

    Sources: U.S. Census Bureau, County Business Patterns 2019 and 2023 (state and county files; establishments with paid employees; employment and payroll suppressed in some cells); Vintage 2025 county population estimates; OMB metropolitan statistical area delineation, July 2023. Non-metro county is a proxy for USDA rural eligibility, not the eligibility test itself.

    Kansas has 20.1 senior care establishments per 100,000 residents against 13.3 nationally, half again the national density. A reviewer reading that figure will ask why another 40 units are needed. The answer has to come from the local market, not the state average, and from the mix of buildings. Splitting the state total by industry shows where growth has been:

    Kansas industryNAICSEstablishments, 2019Establishments, 2023ChangeEmployees, 2023Average pay, 2023
    Nursing care facilities (skilled nursing)6231102762791.1%14,387$39,936
    Continuing care retirement communities623311124121-2.4%9,696$35,754
    Assisted living facilities for the elderly62331217519310.3%6,131$29,295

    Source: County Business Patterns, state files [6]. Assisted living for the elderly grew 10.3% in four years while skilled nursing was flat and continuing care communities shrank. Average pay in Kansas assisted living, $29,295 per employee, is the lowest of the three and includes part-time staff; it is the floor, not the budget, for the wage assumptions below.

    Regional comparison

    StateEstablishments, 2019Establishments, 2023ChangePer 100,000 residentsEmployees per establishmentAverage payShare of establishments in non-metro countiesShare of population in non-metro counties
    Kansas5755933.1%20.151.0$36,43526.1%28.8%
    Nebraska367335-8.7%16.861.3$35,46121.2%33.6%
    Oklahoma499466-6.6%11.554.2$35,51334.5%31.8%
    Colorado7077394.5%12.550.7$42,8897.0%12.0%
    Missouri1,0881,0880.0%17.549.9$38,29426.7%24.4%
    Iowa611559-8.5%17.464.4$37,07440.9%37.6%
    United States43,50644,6492.6%13.353.5$41,324

    Source: this site's state data modules, built from County Business Patterns and Vintage 2025 estimates [6][7][9]. Kansas has the highest density in the region and, with Colorado, one of only two states that added establishments between 2019 and 2023. Nebraska, Oklahoma and Iowa all lost buildings. A lender reads the pattern two ways: Kansas operators have been willing to build, and competing supply can enter freely, because Kansas has no certificate of need for assisted living [13]. That second point is why the study inventories approved but unbuilt projects as well as operating ones.

    The service area: Ford County and six neighbors

    The modeled primary service area is Ford County and the six counties that border it. A real study draws it from the sponsor's own admissions history (prior addresses of residents and of the adult children who chose the community) and a drive-time analysis.

    CountyPopulation, April 2020 basePopulation, July 2025ChangeBirths, 2025Deaths, 2025Net migration, 2025Nursing homes (623110)CCRC and assisted living (623311)Assisted living for the elderly (623312)
    Ford County34,28733,993-0.9%610257-639fewer than 34fewer than 3
    Gray County5,6525,6520.0%10374-653fewer than 3fewer than 3
    Hodgeman County1,7251,619-6.1%1634-27fewer than 3fewer than 3fewer than 3
    Edwards County2,9072,640-9.2%3455-60fewer than 3fewer than 3fewer than 3
    Kiowa County2,4632,432-1.3%293219fewer than 3fewer than 3fewer than 3
    Clark County1,9901,900-4.5%202212fewer than 3fewer than 3fewer than 3
    Meade County4,0603,852-5.1%5545-51fewer than 3fewer than 3fewer than 3
    Seven-county area53,08452,088-1.9%867519-811

    Sources: Vintage 2025 county estimates [7]; County Business Patterns 2023, county file [6]; OMB July 2023 delineation [9]. The county extract used for this page lists industry cells with at least three establishments; "fewer than 3" means two, one or none. All seven counties are non-metro.

    The table explains the shape of demand. Ford County holds 65.3% of the area's 52,088 residents and is young: 610 births against 257 deaths in 2025. The six surrounding counties hold 18,095 people, and their 257 births fell just short of 262 deaths; in four of them (Hodgeman, Edwards, Kiowa and Clark) deaths outnumbered births. Both parts of the area lost people to migration, 811 in total in 2025, and the seven counties together shrank 1.9% from the April 2020 base. The senior market for a Dodge City community is therefore older and thinner in the outlying counties than the Ford County totals suggest, and the outlying counties are where the adult children who move a parent closer are least likely to live. A study that treated the whole area as Ford County would overstate demand.

    Supply in the county file is thin and hard to read. Ford County shows four establishments classed as continuing care retirement communities and assisted living with 164 employees, and Gray County three nursing homes with 174 employees; every other cell has fewer than three establishments. County Business Patterns counts establishments with payroll, not licensed units, and a small residential home may not appear at all. That is why the census count is a starting point only. The study's real supply inventory comes from the state licensing roster: every licensed assisted living, residential health care, home plus and nursing facility within the drive time, with units, occupancy, rates by care level and any project with plans approved.

    Demand model (assumptions)

    The data modules carry no age detail, so the demand model below runs on stated assumptions with a range. A real study replaces each assumption with Census age-by-income estimates for the area, the share of seniors who own homes they could sell, and penetration rates measured at comparable rural communities.

    Scenario (assumptions)Share of area population aged 75+Residents aged 75+Income- and asset-qualifiedQualified residentsAssisted living penetrationAdded demand from outside the areaSupportable assisted living units
    Low6.0%3,12535%1,0948%10%96
    Base7.0%3,64640%1,45810%15%168
    High8.5%4,42745%1,99212%20%287

    The base case supports about 168 assisted living units in the area, inside a range of 96 to 287. The range is wide because three uncertain shares multiply together, which is exactly why a reviewer will not accept a single-point demand figure. Net demand then depends on what already operates:

    Competing assisted living units in the area, including the sponsor's 40 (placeholder)Unmet units, lowUnmet units, baseUnmet units, high
    110-1458177
    130-3438157
    150-5418137

    The competing-supply column is a placeholder, not a count; it shows how the conclusion moves with the inventory the study must build. In the base case the area has room for the 24 new assisted living apartments only if competing supply, including the sponsor's existing 40, is below about 145 units. In the low case there is no unmet demand at any of the supply levels shown, and the expansion would fill by taking residents from other communities. That is the finding the lender most needs to see tested, and it is why this kind of study is prepared with a market and demand study rather than a pro forma alone.

    Memory care is a separate market with a separate test. Residents living with dementia who cannot safely live in an open building need a secure setting, and in a rural area the alternative is often a nursing home bed or a move to a larger town.

    Scenario (assumptions)Residents aged 75+Share living with dementiaResidents with dementiaShare needing a secure residential settingMemory care units supportable
    Low3,12511%34412%41
    Base3,64614%51015%77
    High4,42717%75318%135

    Even the low case supports about 41 memory care units across the area against 16 proposed, before counting existing secure units. The constraint on memory care is less likely to be demand than staffing and price: memory care suites in the model are priced at $6,700 a month and need around-the-clock aides on a secure unit.

    Rates and payer mix (assumptions)

    Revenue assumption (Year 1, modeled)ValueRange tested or how a real study sets it
    Assisted living monthly rate, private pay (rent and base care)$5,150Rate survey of every licensed competitor; 5% lower in stress
    Average level-of-care add-on, private assisted living$425Operator's care-level assessments
    Memory care monthly rate, private pay$6,700Rate survey; memory care competitors within the drive time
    Combined monthly receipts for a Frail Elderly waiver resident, assisted living$3,500State waiver rate schedule plus the resident's room-and-board payment
    Combined monthly receipts for a waiver resident, memory care$4,100Same
    Waiver share of occupied assisted living units20%Operator history; 35% in stress
    Waiver share of occupied memory care suites12%Operator history
    Ancillary and second-person fees per occupied unit per month$55Operator history
    Annual increase: private rates / waiver rates3.0% / 2.0%Rate history; waiver increases held below private
    Annual increase: wages / other expenses3.5% / 3.0%Local wage survey; vendor contracts
    Stabilized occupancy, all units90%Capped at 90% for CF projections (7 CFR 5001.304)

    The Frail Elderly waiver line matters because it sets the low end of the market. A waiver resident brings combined receipts well below the private rate, and the model holds waiver rates to 2.0% annual increases against 3.0% for private rates, so a campus that takes more waiver residents loses margin over time. The sensitivity table tests a 35% waiver share.

    Financial feasibility

    Staffing plan (modeled)

    Role (stabilized, 80 units)FTEYear 1 wage per FTEYear 1 wages
    Executive director1.0$98,000$98,000
    Director of nursing (RN)1.0$95,000$95,000
    Charge nurses (LPN), one per shift around the clock4.2$60,000$252,000
    Medication aides and resident assistants, assisted living12.6$36,000$453,600
    Resident assistants, memory care8.4$37,500$315,000
    Life enrichment1.5$34,000$51,000
    Dietary5.6$33,500$187,600
    Housekeeping and laundry3.5$31,000$108,500
    Maintenance1.5$46,000$69,000
    Business office, admissions and HR2.0$44,000$88,000
    Total41.3$1,717,700
    Benefits and payroll taxes at 24% of wages$412,248

    Labor is the largest cost: in the model, salaries, benefits and agency labor are 46.4% of Year 3 revenue. The plan covers one licensed practical nurse on every shift, a secure memory care unit staffed around the clock, and one kitchen for the whole campus. The expansion adds 17.3 full-time equivalents to an existing 24.0. A study tests the plan against the state's licensing minimums and the local wage market, and it shows what happens if the campus has to fill shifts with agency staff; the model carries agency labor at 3% of wages in Year 1 and 2% after that.

    Lease-up

    Month after openingOccupied new assisted living unitsOccupied memory care suitesCampus occupancy
    Month 14.0 of 242.0 of 1651.5%
    Month 26.0 of 243.5 of 1655.9%
    Month 38.0 of 245.0 of 1660.2%
    Month 410.0 of 246.5 of 1664.6%
    Month 512.0 of 248.0 of 1669.0%
    Month 614.0 of 249.5 of 1673.4%
    Month 716.0 of 2411.0 of 1677.8%
    Month 818.0 of 2412.5 of 1682.1%
    Month 920.0 of 2414.0 of 1686.5%
    Month 1021.6 of 2414.4 of 1689.0%
    Month 1121.6 of 2414.4 of 1689.0%
    Month 1221.6 of 2414.4 of 1689.0%

    The model assumes four assisted living apartments and two memory care suites are occupied at opening, from deposits taken during construction, and that the wing then gains two assisted living residents and one and a half memory care residents a month until it reaches the 90% ceiling in month 10. The existing building is assumed at 88% in Year 1, 89% in Year 2 and 90% thereafter. Absorption is the assumption reviewers question most; a real study sets it from the openings of comparable rural communities and from the sponsor's waiting list, and shows it month by month as here.

    Five-year pro forma

    Line (modeled)Year 1Year 2Year 3Year 4Year 5
    Average occupied assisted living units49.657.257.657.657.6
    Average occupied memory care suites9.614.414.414.414.4
    Campus occupancy (80 units)74.0%89.5%90.0%90.0%90.0%
    Assisted living, private pay (rent and care)$2,654,592$3,153,184$3,270,492$3,368,606$3,469,665
    Assisted living, Frail Elderly waiver residents$416,640$490,090$503,387$513,455$523,724
    Memory care, private pay$679,219$1,049,394$1,080,875$1,113,302$1,146,701
    Memory care, waiver residents$56,678$86,718$88,452$90,221$92,026
    Ancillary and second-person fees$39,072$48,674$50,414$51,926$53,484
    Total operating revenue$3,846,202$4,828,059$4,993,620$5,137,511$5,285,599
    Salaries, wages, benefits and agency labor$2,038,706$2,240,053$2,318,454$2,399,600$2,483,586
    Raw food$260,480$324,491$336,093$346,176$356,561
    Resident and medical supplies$56,240$70,061$72,566$74,743$76,985
    Utilities$180,000$185,400$190,962$196,691$202,592
    Property and liability insurance$140,000$144,200$148,526$152,982$157,571
    Repairs and maintenance$76,000$78,280$80,628$83,047$85,539
    Marketing and admissions$135,000$77,250$79,568$81,955$84,413
    Administration, IT and professional fees$185,000$190,550$196,266$202,154$208,219
    Licenses, dues and training$28,000$28,840$29,705$30,596$31,514
    Bad debt (1% of revenue)$38,462$48,281$49,936$51,375$52,856
    USDA retention fee passed through (0.50% of guaranteed balance)$45,191$44,492$43,738$42,926$42,050
    Total operating expenses$3,183,079$3,431,896$3,546,443$3,662,245$3,781,887
    Net operating income$663,123$1,396,163$1,447,178$1,475,266$1,503,713
    Replacement reserve deposit ($450 per unit, escalated)$36,000$37,080$38,192$39,338$40,518
    Cash flow available for debt service$627,123$1,359,083$1,408,985$1,435,928$1,463,194
    CF guaranteed loan debt service$1,016,261$1,016,261$1,016,261$1,016,261$1,016,261
    Debt service coverage0.62x1.34x1.39x1.41x1.44x

    All figures are modeled. Coverage is cash flow after the replacement reserve divided by annual debt service on the CF guaranteed loan. The existing campus is assumed to carry no other debt and to be exempt from property tax as a nonprofit; both assumptions are checked against the sponsor's audited statements in a real study.

    In Year 3 the combined campus earns $4,993,620 of revenue and $1,447,178 of net operating income, a 29.0% margin, and covers debt service 1.39x. Year 1 coverage is 0.62x: the campus is open, staffed and paying debt service on the whole loan while the wing fills. That is the normal shape of a lease-up and the reason the reserve below exists.

    Debt service on the CF guaranteed loan (illustrative rate)

    The rate is an assumption: 7.50% fixed, amortized over 25 years with monthly payments. CF guaranteed loan rates are negotiated between lender and borrower, may be fixed or variable, and may not exceed what the lender charges on similar loans without a guarantee; the term may run to the useful life of the facility, up to 40 years, with no balloon [1]. The annual retention fee of 0.50% is charged on the guaranteed share of the 31 December balance [5]; the model assumes the bank passes it to the borrower and counts it as an operating expense.

    Loan yearOpening balanceInterestPrincipalDebt serviceClosing balanceGuaranteed portion (80%)Retention fee on 31 Dec balance
    Year 1$11,460,000$853,997$162,263$1,016,261$11,297,737$9,038,189$45,191
    Year 2$11,297,737$841,401$174,860$1,016,261$11,122,877$8,898,301$44,492
    Year 3$11,122,877$827,826$188,435$1,016,261$10,934,442$8,747,553$43,738
    Year 4$10,934,442$813,197$203,064$1,016,261$10,731,378$8,585,103$42,926
    Year 5$10,731,378$797,433$218,828$1,016,261$10,512,550$8,410,040$42,050

    Annual debt service is $1,016,261. Net operating income of $1,270,326 after reserves would give 1.25 times coverage. Over 25 years the loan costs $25,406,517 in payments, of which $13,946,517 is interest at the assumed rate.

    Break-even occupancy

    Campus occupancy in Year 3 (all 80 units)RevenueNet operating incomeCash flow for debt serviceCoverage
    70%$3,883,927$439,394$401,2020.39x
    75%$4,161,350$691,340$653,1480.64x
    80%$4,438,774$943,286$905,0940.89x
    85%$4,716,197$1,195,232$1,157,0401.14x
    90%$4,993,620$1,447,178$1,408,9851.39x
    Break-even, 82.2%1.00x
    1.25x coverage, 87.2%1.25x

    The campus breaks even at 82.2% occupancy in Year 3 and reaches 1.25 times coverage at 87.2%. Against a 90% ceiling, that leaves less than eight points between the highest occupancy the projections may assume and the point at which the campus stops covering its debt. In practice the margin is the most important number in the study: it tells the lender how much room there is for a slow year, a competitor's opening or a staffing crisis that forces the campus to close admissions.

    Sensitivity and stress tests

    Scenario (modeled)Year 1 coverageYear 3 coverageYear 5 coverageNote
    Base case0.62x1.39x1.44x
    Occupancy capped at 85% instead of 90%0.52x1.14x1.18x
    Occupancy capped at 80%0.37x0.89x0.92x
    Private assisted living rate 5% lower0.50x1.24x1.28x
    Wages and benefits 10% higher0.42x1.16x1.20x
    Waiver share of assisted living residents 35% instead of 20%0.44x1.16x1.19x
    Interest rate 1 point higher (variable rate, re-amortized)0.57x1.27x1.32x
    Interest rate 2 points higher (variable rate, re-amortized)0.52x1.17x1.22x
    Construction overrun of 10% of hard cost, financed with more debt0.55x1.25x1.30xloan rises to $12,690,000
    Opening delayed 6 months (lease-up starts in month 7)0.09x1.39x1.44xdebt service starts on schedule while the new wing is empty

    Four results stand out. A permanent occupancy ceiling of 85% instead of 90% takes Year 3 coverage to 1.14 times, and 80% takes it below 1.00. A 10% rise in wages and benefits costs about as much coverage as a 15-point shift to waiver residents. A variable rate two points higher re-amortized from the start still leaves coverage above 1.15 times in Year 3, so rate risk is smaller here than occupancy and labor risk. A 10% construction overrun financed with more debt raises the loan to $12,690,000 and brings Year 3 coverage to 1.25 times exactly, which is why the budget carries a 7% contingency and a fixed-price contract matters.

    Reserves and the lease-up year

    Year 1 scenario (modeled)Cash flow for debt serviceDebt serviceYear 1 shortfallLease-up reserve left ($700,000 at opening)Result
    Base case$627,123$1,016,261-$389,138$310,862covered
    Opening delayed 6 months$91,494$1,016,261-$924,767-$224,767not covered
    Occupancy capped at 85%$525,605$1,016,261-$490,656$209,344covered
    Wages and benefits 10% higher$423,252$1,016,261-$593,008$106,992covered
    Waiver share of assisted living residents 35%$443,720$1,016,261-$572,541$127,459covered

    The sponsor's $700,000 lease-up reserve covers the base-case Year 1 shortfall of -$389,138 with about $311,000 to spare, and it covers each single stress shown except a six-month opening delay, which leaves a gap of about $225,000. A study that finds this does not reject the project; it recommends a larger reserve, a debt service reserve funded at closing, a construction schedule with float, or a sponsor liquidity covenant. Part 5001's credit evaluation rule asks the lender to address reserves for capital expenditure, debt service and maintenance, and to confirm working capital is adequate [1]; the model's replacement reserve of $450 per unit a year and the lease-up reserve are the two lines that answer it.

    Equity test under the CF guaranteed rule

    There is no fixed equity floor for CF guaranteed loans in Part 5001 [1]. B&I's 10% to 25% equity table (5001.105(d)) does not apply to a CF borrower. What the rule does reward is other money: sponsor funds of 23.4% of cost earn 10 priority points, and moving above 50% would earn 15 [1]. The lender will still look at the sponsor's balance sheet after closing, because a nonprofit that empties its reserves to build has nothing left for the lease-up year. The model leaves the existing campus debt-free and puts $3,504,112 of sponsor money into the project, including the full lease-up reserve.

    Financing benchmarks: SBA next to CF

    SBA lending to senior care in Kansas is thin, but it shows typical loan sizes for small for-profit operators, who cannot use CF [10]; SBA lenders may also require a feasibility study of their own borrowers [12]:

    Kansas: SBA lending to assisted living and nursing facilities

    Period7(a) loans7(a) dollars504 loans504 dollars
    FY2010 to FY20165$2.7 million3$8.8 million
    FY2017 to FY20196$4.2 million2$1.7 million
    FY2020 to FY20237$3.0 million3$2.2 million
    FY2024 to FY202612$7.2 million4$4.1 million

    Average 7(a) loan, FY2020 to FY2026: $541,368. Average 504 loan: $889,286. Kansas had fewer than 30 seasoned 7(a) loans for assisted living and nursing facilities; nationally, 3.3% of 1,086 FY2010 to FY2016 loans were charged off, on average 85 months after approval.

    Source: SBA 7(a) and 504 FOIA loan data, as of 30 Sep 2026 (project state; disbursed loans only; cancelled and undisbursed loans excluded).

    The modeled CF loan of $11,460,000 is more than twenty times the average Kansas 7(a) senior care loan; an expansion of this size is outside what SBA lending in the state usually finances. USDA Community Facilities activity in Kansas is also light. USAspending records 17 CF awards in Kansas from 1 October 2023 to 30 September 2026, 5 loans and 12 grants, against 25 in Nebraska, 32 in Missouri, 45 in Iowa and 47 in Oklahoma; Colorado had 12 [11]. Kansas ranks 37th of the 51 states with data. Counts are by program, not facility type, so they include fire halls and clinics as well as senior care. The Kansas precedent most often cited is a hospital: this site's Kansas page records $119,133,000 of Community Facilities financing for a 25-bed critical access replacement hospital in Colby [13]. For assisted living specifically, the closest published CF precedent on this site's state pages is outside Kansas: a $300,000 CF loan for 15 assisted living and memory care units in Bird Island, Minnesota [18].

    Technical and environmental feasibility

    The technical section of a CF study covers the building, the license and the construction risk. For this modeled project the issues are:

    • Licensure. The wing must be licensed in the right category for each unit type, and memory care needs the state's approval for a secure unit. The study confirms the license category, staffing minimums and any plan review with the state licensing agency before the pro forma is final. Kansas has no certificate of need for assisted living [13], so there is no approval gate, but also no protection from a competitor.
    • Life safety and design. Connecting a new wing to an older building often triggers upgrades to the existing building's fire protection, egress and emergency power. The budget carries $240,000 for generator and life safety work and $295,000 for secure entry and campus nurse call. A real study takes these from the architect's code review.
    • Construction while operating. Renovating the kitchen and dining room of an occupied building needs a phasing plan, temporary food service and a schedule the residents can live with.
    • Construction contract and draws. The lender will expect a fixed-price contract with an independent general contractor, retainage, a draw schedule and, if the guarantee is requested before completion, the 0.50% fee [5]. Construction obligations entered before the application can make a CF guarantee unavailable (5001.116(c)) [1].
    • Environmental review. USDA completes an environmental review before it commits; a campus expansion on previously developed land is usually straightforward, but flood zone, wetlands and historic properties are checked before design is fixed.
    • Collateral. Real estate over $250,000 needs a USPAP appraisal with as-is and prospective values; going concern value is deducted before collateral is discounted, and the appraisal may be no more than a year old at closing [1]. A senior care building is special-purpose collateral, so the appraisal's alternative-use analysis matters.

    Management and governance feasibility

    For a CF borrower, management feasibility has two parts. The first is the operator: the executive director's and director of nursing's experience, the existing campus's occupancy, inspection and complaint history, and, if memory care is new, who will run it. A sponsor adding memory care without a memory care director in place should expect the reviewer to ask for one, or for a management agreement with an operator that has run secure units. The second is the board: CF requires a nonprofit to show significant ties to the community, through association with or control by a public body or through broadly based local membership [1]. The study reads the bylaws, board minutes and the resolution authorizing the debt, and it confirms local government support letters are in the file.

    Economic and community impact (modeled)

    Impact measure (modeled)ValueBasis
    Construction spending in the county (hard cost plus contingency)$11,572,000Budget above
    Permanent jobs added (full-time equivalents)17.3Staffing plan: 41.3 FTE after expansion against 24.0 before
    Permanent jobs on campus after expansion41.3Staffing plan
    Year 3 payroll, benefits and agency labor$2,318,454Pro forma
    Residents served at stabilized occupancy72 (of 80 units)90% occupancy
    Memory care suites in a seven-county area16New service line for the sponsor
    Seven-county population, July 202552,088Census Vintage 2025

    The impact a State Office weighs is the service, not the jobs alone. A 16-suite memory care unit brings a secure setting to a seven-county area of about 52,000 people where the county data show no more than a handful of senior care establishments outside Ford County. Families who would otherwise drive a parent to a larger town keep that parent near home, and the campus adds about 17 permanent jobs in a county whose net migration was negative in 2025.

    Risks and mitigants

    RiskHow it shows upMitigant tested in the study
    Slow lease-upYear 1 coverage 0.62x; shortfall of -$389,138Lease-up reserve; pre-leasing deposits; monthly absorption from comparables
    Occupancy ceiling90% cap leaves under eight points above break-evenPayer mix and pricing that lower break-even; covenant at a realistic level
    Competing supplyNo certificate of need in Kansas [13]Inventory of licensed and approved projects; fair share test
    StaffingLabor is 46.4% of revenueLocal wage survey; recruitment plan; agency labor scenario
    Waiver dependenceWaiver residents pay well below private rates35% waiver stress; private-pay floor
    Construction overrun or delay10% overrun brings Year 3 coverage to 1.25x; 6-month delay leaves the reserve short7% contingency; fixed-price contract; schedule float; larger reserve
    Rate risk on a variable loan+2 points gives 1.17x in Year 3Fixed rate or a cap; rate change before closing needs Agency approval [1]
    Funding timingDodge City is outside the pool reserved for places of 20,000 or less [1]Schedule the application around the State Office's funding calendar
    Memory care as a new activityMay require an independent feasibility study [1]Settle the report type with the lender before fieldwork

    What the five Part 5001 components showed

    Part 5001's appendix A organizes a feasibility study into economic, market, technical, financial and management components, and appendix B adds the need-for-facility content specific to Community Facilities [2]. Applied to this modeled expansion:

    ComponentWhat the model showsWhat a reviewer would still ask
    Economic17.3 new jobs; about $11.6 million of construction spending including contingencyConstruction labor availability in southwest Kansas
    Market and needBase-case demand of 168 assisted living units and 77 memory care units in a 52,088-person areaA licensed-unit inventory and measured penetration rates
    TechnicalA buildable wing on an owned campus; license and life safety items budgetedArchitect's code review; state plan review for the secure unit
    FinancialYear 3 coverage 1.39x; break-even 82.2% under a 90% ceilingLease-up evidence; reserve size under a delay
    ManagementEstablished operator; memory care leadership to be namedResumes, board resolution, community ties

    Why studies like this are sent back

    • Occupancy above 90% in the projections, or stabilization in the first months after opening [1].
    • Demand counted from all seniors rather than income- and asset-qualified residents.
    • No licensed-unit inventory, or one that leaves out small residential homes and approved projects.
    • Staffing copied from a nursing home or from a metro operator.
    • A lender's financial feasibility analysis submitted where the borrower's situation called for an independent study or an examination opinion [1][2].
    • No lease-up reserve, or initial operating costs placed in the loan budget although CF guaranteed loan funds cannot pay them [1].
    • A market study written by the developer or operator rather than an independent consultant.

    Program terms that applied

    TermCF guaranteed ruleSource
    Guarantee80% in FY2026; 90% is the regulatory ceiling91 FR 11272; 5001.407 [1][5]
    Up-front guarantee fee1.25% of the guaranteed amount ($114,600 on the modeled loan)91 FR 11272 [5]
    Annual retention fee0.50% of the guaranteed share of the outstanding balance ($45,191 in Year 1 of the model)91 FR 11272 [5]
    Fee if the guarantee is issued before construction completion0.50%91 FR 11272 [5]
    Maximum loan$100 million of CF guaranteed loans per borrowerPart 5001 [1]
    RateNegotiated; fixed or variable; no higher than the lender's similar loans without a guarantee5001.401 [1]
    TermUseful life, up to 40 years or state law, whichever is less; no balloon5001.402 [1]
    Rural areaOutside cities over 50,000 and their contiguous urbanized areas; funds reserved first for places of 20,000 or less5001.3, 5001.103(c), 5001.316(e) [1]
    Feasibility evidenceFinancial feasibility report always; independent study over $1 million to a new entity or activity5001.304 [1][2]
    Occupancy in projectionsNo more than 90% for assisted living5001.304 [1]
    Tax statusInterest on a guaranteed loan cannot be tax-exemptPart 5001 [1]

    The FY2026 fee notice governs loans obligated in fiscal year 2026 [5]; a 2024 obligation, like this engagement, was priced under that year's notice, which this site has not read. A Federal Register check on 11 November 2026 found no FY2027 notice yet [19].

    Lessons for sponsors of similar projects

    1. Check the population count before anything else. A town between 20,000 and 50,000 can use a CF guarantee but not CF direct money or grants, and it competes outside the pool reserved for small places until July.
    2. Treat 90% as a ceiling, not a target. Build the debt so that break-even sits well below it; in this model the margin is under eight points, and that is the figure the lender will focus on.
    3. Fund the lease-up from your own money. CF guaranteed loan funds cannot pay initial operating expenses, so the reserve has to come from the sponsor, and it has to survive a construction delay.
    4. Settle the report type early. Whether memory care is a new activity, and whether three audited years show capacity to pay, decides which report the lender submits; the fieldwork is the same, but the deliverable is not.
    5. Count supply from licenses, not from business counts. The Census count is a screen; the licensing roster, with units and approved projects, is the inventory.
    6. Put sponsor money in the stack. Other funds of 20% or more earn 10 priority points, and they make the lender's credit evaluation easier.

    If you are planning an assisted living or memory care expansion in a rural town and need a USDA feasibility study consultant, the engagement index describes the process: a fifteen-minute scoping call, a written proposal inside one business day and a firm fixed fee before you sign [16]. Request a proposal for your study [17].

    Data current as of November 2026.

    David Miller, CPA

    USDA Feasibility, Inc.

    Frequently Asked Questions

    Why did this Dodge City project use a CF guaranteed loan rather than a CF direct loan?

    CF direct loans and CF grants are limited to cities and towns of 20,000 people or less (7 CFR 1942.17 and 3570.53), and Dodge City had 27,793 residents in the Census Bureau's April 2020 estimates base. CF guaranteed loans use the wider OneRD rural definition in 5001.3, which excludes only cities over 50,000 and their contiguous urbanized areas. Dodge City therefore qualifies for a guarantee but not for direct money, and it misses the 15 priority points and the funding reserved for places of 20,000 or less.

    Does USDA require a feasibility study for a CF guaranteed assisted living expansion?

    A financial feasibility report is always required for a CF guaranteed loan. For an existing facility borrowing $25 million or less, a financial feasibility analysis under appendix B can serve, and the lender's credit evaluation may be enough. A loan over $1,000,000 to a new entity or an entity starting a new activity needs an independent feasibility study, and other loans need a study with a CPA examination opinion (5001.304). Adding memory care for the first time can count as a new activity.

    What occupancy can an assisted living study assume for a CF loan?

    No more than 90%. Section 5001.304 limits CF projections for assisted living, skilled nursing and similar residential facilities to 90% occupancy, whatever the market study finds. In this page's model the combined campus breaks even at 82.2% occupancy and reaches 1.25 times coverage at 87.2%, so the cap leaves a margin of under eight points. A study should show the monthly ramp to the cap and the coverage at lower ceilings, such as 85% and 80%.

    How much equity does a nonprofit need for a CF guaranteed loan?

    Part 5001 sets no fixed equity percentage for CF guaranteed loans; the B&I table in 5001.105(d) does not apply. Instead, committed other funds earn priority points: 5 for 5% to 19% of cost, 10 for 20% to 49% and 15 for 50% or more (5001.316). The lender also judges the sponsor's balance sheet after closing. In the model, sponsor cash and gifts of $3,504,112 are 23.4% of a $14,964,112 project, which earns 10 points.

    Can the CF guaranteed loan pay for lease-up losses and working capital?

    No. Part 5001 bars CF guaranteed loan funds from paying initial operating expenses, working capital or recurring costs (5001.122(m)). The loan may pay the guarantee fee, professional fees and interest for up to three years until the facility is self-supporting. A lease-up reserve must therefore come from the sponsor. In the model, a $700,000 reserve covers the base-case Year 1 shortfall but not a six-month opening delay, which leaves a gap of about $225,000.

    What does a CF guarantee cost on a loan like this?

    For FY2026 USDA guarantees 80% of a CF loan and charges 1.25% of the guaranteed amount up front and 0.50% a year on the guaranteed share of the balance (91 FR 11272). On the modeled $11,460,000 loan, the fee is $114,600 and the first-year retention fee about $45,191. Issuing the guarantee before construction is complete adds 0.50% of the guaranteed amount. B&I, by comparison, charges 3.0% up front.

    Who can prepare an assisted living feasibility study for a USDA loan?

    An independent qualified consultant acceptable to the Agency, with no stake in the operator, developer, property or loan (Part 5001). Where a CF guarantee calls for a financial feasibility study with an examination opinion, a CPA must prepare it under AICPA attestation standards. A developer's market study or an operator's pro forma can be inputs, but they do not meet the independence test. Settle with the lender which report type the State Office expects before fieldwork starts.

    How long does an assisted living feasibility study take, and what does it cost?

    This site's cost page lists Community Facilities studies at $6,900 to $12,000 and 6 to 8 weeks from the engagement letter, with a rush option, and every proposal states a firm fixed fee. An expansion that adds memory care, uses a seven-county service area or needs a CPA examination opinion usually sits toward the upper end. The appraisal, architect's estimate and environmental review run alongside the study and are separate engagements.

    How does a study measure assisted living demand in a rural Kansas market?

    It counts residents aged 75 and over in the service area, keeps those whose income and assets can pay the rates, applies a penetration rate measured at comparable rural communities, and deducts every licensed unit already serving that market. This page's model, built on stated assumptions, finds base-case demand of 168 assisted living units in a 52,088-person seven-county area, with a range of 96 to 287. The licensing roster, not the Census business count, supplies the competing units.

    Does Kansas require a certificate of need for an assisted living expansion?

    No. This site's Kansas page records that Kansas has no certificate-of-need law for assisted living, citing NCSL. That removes an approval step and its delay, but it also means a competitor can open nearby without a state review of need. A Kansas study should therefore inventory projects with plans approved or under construction, not only operating buildings, and test coverage if a competing community opens during the lease-up year.

    Sources

    [1] 7 CFR part 5001, OneRD Guaranteed Loans (CFR 2026 edition, title 7 vol. 15, revised 1 Jan 2026), including 5001.3, 5001.103, 5001.105, 5001.116, 5001.122, 5001.202, 5001.203, 5001.304, 5001.316, 5001.401, 5001.402, 5001.407, govinfo. https://www.govinfo.gov/content/pkg/CFR-2026-title7-vol15/xml/CFR-2026-title7-vol15-part5001.xml (accessed 11 Nov 2026)

    [2] 7 CFR part 5001, subpart D, appendix A (Elements of an Acceptable Feasibility Study) and appendix B (Financial Feasibility Reports) (CFR 2026 edition). https://www.govinfo.gov/content/pkg/CFR-2026-title7-vol15/pdf/CFR-2026-title7-vol15-part5001-subpartD-appA.pdf ; https://www.govinfo.gov/content/pkg/CFR-2026-title7-vol15/pdf/CFR-2026-title7-vol15-part5001-subpartD-appB.pdf (accessed 11 Nov 2026)

    [3] 7 CFR part 1942, subpart A, Community Facility Loans, section 1942.17 (CFR 2025 edition, title 7 vol. 13, the latest on govinfo). https://www.govinfo.gov/content/pkg/CFR-2025-title7-vol13/xml/CFR-2025-title7-vol13-part1942.xml (accessed 11 Nov 2026)

    [4] 7 CFR part 3570, subpart B, Community Facilities Grant Program, section 3570.53 (CFR 2026 edition). https://www.govinfo.gov/content/pkg/CFR-2026-title7-vol15/xml/CFR-2026-title7-vol15-part3570.xml (accessed 11 Nov 2026)

    [5] USDA, OneRD Annual Notice of Guarantee Fee Rates, Periodic Retention Fee Rates, Loan Guarantee Percentage and Fee for Issuance of the Loan Note Guarantee Prior to Construction Completion for Fiscal Year 2026, 91 FR 11272 (9 Mar 2026). https://www.govinfo.gov/content/pkg/FR-2026-03-09/html/2026-04581.htm (accessed 6 Nov 2026)

    [6] U.S. Census Bureau, County Business Patterns 2019 and 2023, state and county files. https://www2.census.gov/programs-surveys/cbp/datasets/2023/cbp23co.zip ; https://www2.census.gov/programs-surveys/cbp/datasets/2023/cbp23st.zip ; https://www2.census.gov/programs-surveys/cbp/datasets/2019/cbp19st.zip (accessed 7 Nov 2026)

    [7] U.S. Census Bureau, Vintage 2025 county population estimates. https://www2.census.gov/programs-surveys/popest/datasets/2020-2025/counties/totals/co-est2025-alldata.csv (accessed 7 Nov 2026)

    [8] U.S. Census Bureau, Vintage 2025 subcounty population estimates (incorporated places). https://www2.census.gov/programs-surveys/popest/datasets/2020-2025/cities/totals/sub-est2025.csv (accessed 8 Nov 2026)

    [9] OMB metropolitan and micropolitan statistical area delineation file, July 2023. https://www2.census.gov/programs-surveys/metro-micro/geographies/reference-files/2023/delineation-files/list1_2023.xlsx (accessed 7 Nov 2026)

    [10] U.S. Small Business Administration, 7(a) and 504 FOIA loan data, as of 30 Sep 2026. https://data.sba.gov/sites/default/files/uploaded_resources/FOIA_7a_FY2020_Present_asof_260930.csv (and companion files) (accessed 7 Nov 2026)

    [11] USAspending.gov, award counts by place of performance for Assistance Listings 10.766 (Community Facilities) and 10.768 (B&I), 1 Oct 2023 to 30 Sep 2026, API v2 spending_by_award_count. https://api.usaspending.gov/api/v2/search/spending_by_award_count/ (accessed 7 Nov 2026)

    [12] 13 CFR part 120, Business Loans (CFR 2026 edition), section 120.160. https://www.govinfo.gov/content/pkg/CFR-2026-title13-vol1/xml/CFR-2026-title13-vol1-sec120-160.xml (accessed 7 Nov 2026)

    [13] usda-feasibility-study.com, USDA Feasibility Study Consultant in Kansas (state page: certificate of need, Colby precedent, State Office). https://usda-feasibility-study.com/kansas (read 11 Nov 2026)

    [14] usda-feasibility-study.com, Assisted Living Feasibility Study for USDA B&I and Community Facilities Loans. https://usda-feasibility-study.com/assisted-living-feasibility-study-usda (read 11 Nov 2026)

    [15] usda-feasibility-study.com, USDA Feasibility Study Cost & Timeline. https://usda-feasibility-study.com/usda-feasibility-study-cost (read 11 Nov 2026)

    [16] usda-feasibility-study.com, Selected USDA Feasibility Study Engagements. https://usda-feasibility-study.com/engagements (read 11 Nov 2026)

    [17] usda-feasibility-study.com, Contact & Request a Proposal. https://usda-feasibility-study.com/contact (read 11 Nov 2026)

    [18] usda-feasibility-study.com, USDA Feasibility Studies in Minnesota (state page, precedent table). https://usda-feasibility-study.com/minnesota (read 11 Nov 2026)

    [19] Federal Register API, OneRD guarantee fee notices and documents citing 7 CFR part 5001, newest first. https://www.federalregister.gov/api/v1/documents.json?conditions[cfr][title]=7&conditions[cfr][part]=5001&order=newest (accessed 11 Nov 2026)

    Data current as of November 2026.

    Ready to Start Your USDA Project?

    Get your free consultation today and take the first step toward securing USDA funding for your rural development project.

    Our USDA feasibility study consultants scope every engagement against the five Part 5001 components in a free consultation.