    How to read this case study. The engagement summary reflects the published record. Client names, actual costs, loan terms and proprietary data are confidential, so the project budget, market sizing and financial projections below are a modeled example built from public data for this project type and location. They show the analysis a lender-grade study performs, not the client's figures.

    Data current as of November 2026.

    Engagement summary

    In 2024 we prepared a feasibility study for a beet-sugar cooperative's processing equipment project in Crookston, Minnesota, financed through the USDA Business and Industry (B&I) guaranteed loan program with a regional agricultural bank as lender. The loan sat in the $5 million to $25 million tier, and the study was prepared to the five-component standard for lender submission.

    FieldPublished record
    ProgramUSDA Business and Industry (B&I) guaranteed loan
    AssetFood manufacturing: beet-sugar cooperative processing equipment
    LocationCrookston, Minnesota (Polk County)
    Loan size tier$5 million to $25 million
    Year2024
    Lender typeRegional agricultural bank
    OutcomePrepared to the five-component standard for lender submission

    Everything after this table that carries a dollar figure, a tonnage, a rate or a coverage ratio is a model. It uses a cooperative of the size a factory in the Red River Valley might serve and public Census, SBA and USAspending data, and every assumption is stated next to the number it drives. Program terms are the FY2026 terms in force when this page was written; the notice in force for a 2024 study set that year's percentages and fees.

    The question the lender and USDA needed answered

    A sugar cooperative is not a start-up, so the rule that forces an independent study on every new business borrowing more than $1,000,000 under B&I (7 CFR 5001.306(a)(3)(i)) does not apply on its face [1]. The study was still needed, for three reasons that recur in cooperative equipment loans.

    First, the Agency may require a feasibility study whenever the information in the application is not enough to judge the project, and the lender's own credit evaluation must address the feasibility study, market conditions and construction complexity under the "conditions" factor of the five Cs [1]. A processing upgrade installed between campaigns, with a fixed window and no second chance until the next harvest, is construction complexity of a particular kind.

    Second, the repayment source is unusual. A sugar cooperative pays its members for their beets out of what is left after processing costs and debt service. The lender is therefore underwriting a board decision as much as a factory: will members accept a smaller beet payment, or a per-ton capital retain, to carry the new debt? Part 5001 requires a global credit evaluation, historical and projected debt service coverage, and attention to reserves and working capital [1]. For a cooperative those tests run through the membership.

    Third, a sugar factory is a seasonal borrower. Part 5001 asks the lender for quarterly cash flow projections for seasonal borrowers and for projections that differ from history to be substantiated [1]. An equipment project that promises more sugar per ton and less fuel per ton departs from history by design, so the engineering claims behind those savings had to be tied to evidence the lender could cite.

    RuleWhat it requiresWhy it mattered here
    7 CFR 5001.306(a)(3)The Agency may require a feasibility study when information is insufficient; required for loans over $1,000,000 to a new businessExisting cooperative: study at Agency and lender discretion, requested because savings drive repayment
    7 CFR 5001.202 (conditions)Lender's written evaluation of the feasibility study, market study and construction complexityInstallation must fit an intercampaign window
    7 CFR 5001.202 (capacity)Global historical and projected coverage; reserves; quarterly cash flow for seasonal borrowersThe campaign concentrates cash in a few months
    7 CFR 5001.202 (content)Projections that deviate from history must be substantiatedExtraction and fuel gains are new, not historical
    7 CFR 5001.105(d)(1)Existing business equity tests at closingCooperative equity sources must be documented
    7 CFR 5001.406(c)B&I limit $25 million per borrower; up to $40 million for qualifying rural cooperatives processing value-added commodities, at the Secretary's discretionSets the ceiling for this and later phases

    Project description (modeled)

    The modeled project replaces and upgrades equipment at one existing factory in two intercampaign periods, the months between the end of one slicing campaign and the start of the next. Nothing in it adds acres or members. It is a productivity loan: the same beets, sliced faster, with less sugar lost to storage piles and pulp and less fuel burned per ton.

    PhaseWindowScopeWhat it changes
    Engineering and procurementMonths 1 to 8Heat and mass balance, equipment specification, long-lead orders, air permit reviewLocks vendor guarantees before money is committed
    Phase 1 installationFirst intercampaignFour slicers, two pulp presses, control system upgrade, electrical serviceSlice rate up 4%; first part of pulp sugar recovery; dryer fuel savings
    Campaign year 1First campaign after installationPhase 1 in servicePartial benefits; interest-only debt service
    Phase 2 installationSecond intercampaignDiffuser rebuild, added falling-film evaporator effect with condensate heat recoveryFull pulp recovery; steam economy gain
    Campaign years 2 to 5Following campaignsFull scope in serviceFull modeled benefits; level principal and interest

    The record states that capital investment at comparable cooperatives runs $24 million to $26 million per cycle for evaporators, slicers and diffusers. The modeled budget below lands at $25,628,000, inside that range, built from line items rather than taken from it.

    Project cost and sources and uses

    There is no construction-cost database behind this page, so every line is an assumption stated per unit or per component with a range. A real study replaces each with the document named in the last column: vendor quotes with performance guarantees for the slicers, presses, diffuser work and evaporator body; contractor bids for installation and electrical; an engineer's estimate for structural work; and a valuation of the equipment for the lender.

    Line itemBasisModeled costAssumption rangeHow a real study sources it
    Beet slicers with knife-change system4 x $650,000$2,600,000$500,000 to $800,000 per unitEquipment quote
    Diffuser rebuild (screens, drive, scroll sections)1 x $3,400,000$3,400,000$2,600,000 to $4,200,000 per unitVendor proposal and inspection report
    Falling-film evaporator body (added effect) with condensate heat recovery1 x $4,800,000$4,800,000$3,800,000 to $6,000,000 per unitEquipment quote and heat balance
    Pulp presses2 x $1,100,000$2,200,000$900,000 to $1,400,000 per unitEquipment quote
    Process controls and instrumentation (DCS upgrade)1 x $1,250,000$1,250,000$900,000 to $1,600,000 per unitIntegrator proposal
    Electrical: switchgear, motor control centres, drives1 x $1,150,000$1,150,000$850,000 to $1,450,000 per unitElectrical contractor bid
    Installation, mechanical and piping28% of equipment$4,312,00022% to 35% of equipmentContractor bids
    Structural steel, foundations, building changesallowance$900,000$600,000 to $1,300,000Structural engineer estimate
    Hard cost subtotal$20,612,000
    Contingency10% of hard cost$2,061,0007.5% to 15%Lender and engineer review
    Engineering and design7% of hard cost$1,443,0005% to 9%Engineering proposal
    Owner project management and commissioningallowance$350,000$250,000 to $500,000Owner budget
    Air permit modification and other permitsallowance$120,000$60,000 to $200,000Permit consultant
    Feasibility study, equipment appraisal, legal and closingallowance$185,000$120,000 to $260,000Engagement letters
    B&I guarantee fee (3.0% of guaranteed portion)$18,000,000 x 80% x 3.0%$432,000Fixed by FY2026 notice91 FR 11272
    Interest during installationaverage 45% drawn for 9 months at 7.00%$425,000Depends on draw scheduleLender draw schedule
    Total project cost$25,628,000

    Hard costs are $20,612,000, of which equipment is $15,400,000. Installation at 28% of equipment cost is the line most likely to move: work inside a running factory, around existing piping and in a fixed window, costs more than greenfield installation. The 10% contingency ($2,061,000) is a lender minimum for brownfield process work, not a comfortable margin, and the stress tests below show what happens if it is consumed. The guarantee fee ($432,000) and interest during installation ($425,000) are financed because the cooperative's equity is better kept for the campaign than spent on fees.

    SourcesAmountShareUsesAmount
    B&I guaranteed term loan (80% guaranteed)$18,000,00070.2%Equipment and installation$20,612,000
    Cooperative equity: retained patronage and capital retains$7,628,00029.8%Contingency$2,061,000
    Engineering, management, permits, study, legal$2,098,000
    Guarantee fee and interest during installation$857,000
    Total sources$25,628,000100.0%Total uses$25,628,000

    The cooperative's share, $7,628,000 or 29.8% of cost, comes from retained patronage and per-ton capital retains already on the balance sheet. That is well above the 10% minimum for an existing business, and it is deliberate: the lender's collateral position on specialised process equipment is thin (see below), and equity is the cheapest way to fix it. A REAP energy efficiency grant is not counted. Under the REAP rule effective 16 October 2026 a grant is applied for after the project has run for 12 to 24 months with metered data, is capped at $250,000 for efficiency projects and at 25% of cost, and is competitive, so a lender should underwrite without it [11].

    Market analysis

    Minnesota food manufacturing, the state supply base

    Census does not publish beet sugar refining as a separate line in the files used here, so the state picture uses food manufacturing excluding meat (NAICS 311 less 3116), the class that contains sugar.

    MeasureMinnesotaUnited States
    Establishments, 2019 → 2023559 → 571 (+2.1%)24,589 → 27,414
    Per 100,000 residents (2023)9.98.1
    Average employees per establishment56.742.0
    Average annual pay per employee$64,888$58,248
    Share of establishments in non-metro counties32.1% (193 in 33 counties)
    Share of state population in non-metro counties (2025)21.9%

    Non-metro counties with the most food manufacturing (excluding meat) (2023): Rice County (16); Douglas County (14); Morrison County (13); Otter Tail County (13); Goodhue County (10); Kandiyohi County (10).

    Sources: U.S. Census Bureau, County Business Patterns 2019 and 2023 (state and county files; establishments with paid employees; employment and payroll suppressed in some cells); Vintage 2025 county population estimates; OMB metropolitan statistical area delineation, July 2023. Non-metro county is a proxy for USDA rural eligibility, not the eligibility test itself.

    Minnesota has 571 food plants outside the meat sector, 9.9 per 100,000 residents against 8.1 nationally, and they are larger than average: 56.7 employees per plant against 42.0. Average pay of $64,888 is 11.4% above the national $58,248, a useful benchmark for the wage line in any Minnesota processing model. The count grew only 2.1% from 2019 to 2023 while the national count grew 11.5%, so Minnesota's food base is mature and concentrated in established, larger plants rather than new entrants. A third of the plants the county file places are in non-metro counties.

    What a reviewer takes from this table for a sugar cooperative is narrow. It confirms a deep processing labour market and a wage level; it says nothing about sugar demand. For a cooperative, the market question is not whether the factory can find customers but whether its members' acres, yields and sugar content will keep the slicers full, and at what net price the sugar sells.

    The regional processing belt

    StatePlants, 2023Change 2019 to 2023Per 100,000 residentsEmployees per plantAverage payNon-metro share
    Minnesota5712.1%9.956.7$64,88832.1%
    North Dakota9812.6%12.553.3$65,58036.4%
    South Dakota907.1%9.850.5$56,81856.5%
    Iowa3545.7%11.066.3$76,24754.6%
    Wisconsin9054.9%15.368.5$64,02334.2%
    Idaho23119.7%11.775.3$57,84134.2%
    United States27,41411.5%8.142.0$58,248

    Among the northern plains and upper Midwest states, Minnesota has the most food plants after Wisconsin and pays above the regional middle. North Dakota, the other half of the Red River Valley sugar district, has 98 plants at 12.5 per 100,000 residents and pays slightly more than Minnesota. The comparison matters for labour: factories on both banks of the Red River recruit from the same towns, and a study that sets wages from a Minnesota average without looking across the river understates competition for maintenance and controls staff.

    The Red River Valley counties

    CountyOMB 2023Population, 2025Food plants (NAICS 311)Food employmentFood average payAll manufacturing plantsAll manufacturing employment
    Polk County, MNMetro30,54512930 (high noise)$68,415331,648
    Clay County, MNMetro67,7345431 (high noise)$71,671371,247
    Pennington County, MNNon-metro13,6864111 (low noise)$115,108161,143
    Marshall County, MNNon-metro8,798376 (high noise)$95,93415366
    Kittson County, MNNon-metro4,031353 (high noise)$92,32110144
    Renville County, MNNon-metro14,3564662 (low noise)$90,43718990
    Grand Forks County, NDMetro74,5019693 (high noise)$53,447552,692
    Cass County, NDMetro201,794301,722 (low noise)$66,13119311,458
    Richland County, NDNon-metro16,7317649 (high noise)$77,276381,696

    County Business Patterns counts all food plants (NAICS 311, meat included) by county, and employment carries a noise flag where Census adds noise to protect individual employers. Polk County shows 12 food plants with 930 employees (high noise), a large processing payroll for a county of 30,545 residents. Renville County in southern Minnesota and Richland County in North Dakota show the same pattern: a handful of plants with hundreds of employees and high average pay, the signature of a sugar factory in a small county. Because the noise flags are high in several cells, a study treats these as orders of magnitude and takes actual headcount and wages from the cooperative's payroll.

    Polk County is classed as metropolitan because it belongs to the Grand Forks metropolitan area. That is a county proxy, not the B&I test, and it is the first trap in a Crookston file.

    Rural area test

    PlaceCensus base 2020Estimate 20255001.3 screen
    Fargo, ND125,951136,275Over 50,000: excluded with its contiguous urbanized area
    Grand Forks, ND59,17360,365Over 50,000: excluded with its contiguous urbanized area
    Moorhead, MN44,50746,533Under 50,000: passes on population; contiguity decides
    East Grand Forks, MN9,1898,906Under 50,000: passes on population; contiguity decides
    Crookston, MN7,5067,375Under 50,000: passes on population; contiguity decides

    B&I's rural area test excludes any city or town of more than 50,000 people and the urbanized area contiguous and adjacent to it, using the latest decennial census, and USDA will not approve an application subject to meeting the rural test later [1]. Grand Forks, North Dakota (60,365 in the 2025 estimate) is over the line, so East Grand Forks, which adjoins it, needs a map check. Crookston, with 7,375 residents, passes on population and is a separate town. The study recorded the site's status from the USDA eligibility map with a date, which a reviewer expects to see in the first pages of the report.

    Sugar supply and price

    The engagement record states that Minnesota is the largest sugar beet producing state, with 334,000 intended acres, and that the 2024 campaign set a Red River Valley yield record of 32.2 tons per acre. It also cites a FY2026 Commodity Credit Corporation refined beet sugar loan rate for the Minnesota and eastern North Dakota region of 32.70 cents per pound, about 30% above the FY2025 rate of 25.18 cents, attributing the increase to 2025 farm legislation, and treats it as the revenue floor for pro forma modeling. None of these figures could be confirmed against a primary source for this page, so the model uses its own labelled price assumptions and shows the record's loan-rate figure as one scenario.

    The modeled net selling price is 36.0 cents per pound after freight and selling costs. A real study builds it from the cooperative's sales contracts and its marketing agent's reports, then tests it against the loan rate, because the loan rate (if confirmed) sets a level below which forfeiture becomes the cooperative's alternative to selling.

    Financing benchmarks

    Period7(a) loans7(a) dollars504 loans504 dollars
    FY2010 to FY2016101$42.8 million16$12.7 million
    FY2017 to FY201951$15.5 million6$10.4 million
    FY2020 to FY202354$33.4 million13$12.9 million
    FY2024 to FY202642$16.5 million4$3.1 million

    Average 7(a) loan, FY2020 to FY2026: $519,526. Average 504 loan: $944,059. Of the 101 7(a) loans approved in FY2010 to FY2016 for Minnesota food manufacturing (excluding meat), 4.0% were charged off (national: 7.4% of 3,150), on average 63 months after approval.

    Source: SBA 7(a) and 504 FOIA loan data, as of 30 Sep 2026 (project state; disbursed loans only; cancelled and undisbursed loans excluded).

    SBA lending is a weak guide to a cooperative of this size: the average Minnesota food-manufacturing 7(a) loan since FY2020 is $519,526, and a sugar cooperative's equipment cycle is thirty to fifty times that. What the SBA record does show is that Minnesota food manufacturers have repaid well: 4.0% of seasoned 7(a) loans were charged off against 7.4% nationally. USAspending lists 5 B&I loans in Minnesota for FY2024 to FY2026 (counts may be incomplete) and 544 REAP grants, so B&I volume in the state is thin and a lender new to the program should expect a careful state office review.

    Financial feasibility

    Operating assumptions

    Operating assumption (modeled)ValueRange tested or source a study uses
    Beets sliced per campaign1,450,000 tonsMember acres x 5-year average yield; grower contracts
    Slice rate before / after slicer replacement6,500 / 6,760 tons a day (+4%)Factory slice logs; vendor guarantee
    Campaign length before / after223 / 214 daysComputed: tons divided by slice rate
    Share of crop stored in piles70%Harvest and slicing schedule
    Storage sugar loss0.25 lb sugar per ton per day0.15 to 0.40; pile temperature records
    Sugar recovered from pulp after diffuser rebuild and presses2.0 lb per ton of beets1.0 to 3.0; vendor guarantee and lab data
    Net selling price of sugar (after freight and selling cost)36.0 cents per lbSales contracts and marketing agent reports
    Fuel use before project1.25 MMBtu per ton of beetsUtility bills for three campaigns
    Delivered natural gas$4.75 per MMBtuSupply contract; stressed +40%
    Fuel saved by added evaporator effect9% of factory fuelHeat and mass balance by engineer
    Dryer fuel saved by higher press solids$300,000 a yearPress vendor data
    Maintenance avoided on retired equipment$400,000 a yearMaintenance records
    Added electricity for new drives$80,000 a yearMotor list x tariff

    Three of these assumptions carry most of the value. Sugar recovered from pulp depends on the diffuser vendor's guarantee and on lab data before and after; the fuel saving depends on the engineer's heat and mass balance; the storage gain depends on a pile loss rate that varies with weather. The study asks for each in writing from the party that will be held to it.

    Debt terms

    Term (model)ValueRule or basis
    Loan amount$18,000,000Inside the $5 million to $25 million tier; B&I cap $25 million, up to $40 million for qualifying rural cooperatives (5001.406(c))
    Guarantee80%: $14,400,000 guaranteed, $3,600,000 held by the lender at riskFY2026 notice, $5 million to $25 million tier
    Guarantee fee3.0% of guaranteed portion: $432,000FY2026 notice; financed in the budget
    Annual retention fee0.55% of guaranteed principal outstanding: $75,744 after year 2FY2026 notice; 5001.455
    Rate7.00% fixed (illustrative assumption)Negotiated; not above the lender's rate on similar unguaranteed loans (5001.401)
    Interest-only period12 months (installation and first campaign)First full principal and interest within 3 years (5001.402)
    Amortization after interest-only14 years; monthly payment $168,372Within the useful life of the equipment (5001.402)
    CollateralFirst lien on the new equipment and a lien on factory real estateAppraisal and discounting under 5001.202 and 5001.203

    The guarantee does not change the cooperative's obligation. It changes the lender's exposure: at 80%, $18,000,000 leaves the bank with its unguaranteed share at full risk, which is why the bank reads the coverage and collateral sections hardest.

    Five-year pro forma: the project's own cash flow

    Campaign yearYear 1Year 2Year 3Year 4Year 5
    Sugar saved by shorter storage$391,886$391,886$391,886$391,886$391,886
    Sugar recovered from pulp$417,600$1,044,000$1,044,000$1,044,000$1,044,000
    Fuel saved, added evaporator effect$0$794,215$814,070$834,422$855,283
    Dryer fuel saved$300,000$307,500$315,188$323,067$331,144
    Maintenance avoided$200,000$410,000$420,250$430,756$441,525
    Added electricity-$80,000-$82,000-$84,050-$86,151-$88,305
    Cash benefit available for debt service$1,229,486$2,865,601$2,901,344$2,937,980$2,975,533
    New B&I debt service (interest and principal)$1,260,000$2,020,465$2,020,465$2,020,465$2,020,465
    Retention fee, 0.55% of guaranteed balance (charged to borrower in the model)$79,200$75,744$72,039$68,066$63,806
    Project DSCR before retention fee0.98x1.42x1.44x1.45x1.47x
    Project DSCR after retention fee0.92x1.37x1.39x1.41x1.43x

    The project pays for itself from year 2. In year 1, with only phase 1 in service and interest-only payments of $1,260,000, the modeled benefit of $1,229,486 covers interest only 0.98x. That shortfall is planned, not a failure: the study shows it so the cooperative budgets for it from general cash flow. From year 2, full benefits of $2,865,601 cover level debt service of $2,020,465 at 1.42x, rising to 1.47x by year 5 as fuel and maintenance savings inflate at 2.5% a year.

    Break-even and per-ton economics

    The project breaks even when it delivers 70.5% of the modeled year-2 benefit; benefits can fall 29.5% before the project stops covering its own debt. Expressed per ton of beets, the new debt costs members $1.39 a ton a year and the modeled benefits return $1.98 a ton, a net gain of $0.58 a ton ($845,136 across the crop) in year 2.

    Because a cooperative can set its own capital retain, the study also tested coverage on a retain basis. A retain of $1.75 a ton on the modeled crop covers the new debt service at 1.26x without counting any project benefit, which is the coverage a lender can rely on if the engineering claims disappoint.

    Sensitivity

    Scenario (one change at a time)Cash benefitDebt serviceProject DSCR
    Base case (campaign year 2)$2,865,601$2,020,4651.42x
    Rate 8.00% (+1 point)$2,865,601$2,141,2471.34x
    Rate 9.00% (+2 points)$2,865,601$2,265,7051.26x
    Benefits 25% below engineer estimate$2,149,201$2,020,4651.06x
    Benefits 40% below engineer estimate$1,719,361$2,020,4650.85x
    Crop 15% smaller (fewer tons sliced)$2,481,120$2,020,4651.23x
    Natural gas 40% cheaper (less fuel saved)$2,424,915$2,020,4651.20x
    Sugar price 20% lower$2,578,424$2,020,4651.28x
    Cost overrun 15% financed with more debt$2,865,601$2,367,5141.21x
    Rate \ benefits achieved100%85%70%55%
    6.00%1.51x1.28x1.05x0.83x
    7.00%1.42x1.21x0.99x0.78x
    8.00%1.34x1.14x0.94x0.74x
    9.00%1.26x1.08x0.89x0.70x

    No single change sinks the project. The weak point is the engineering estimate: if benefits come in 25% below plan, coverage falls to about 1.06x, and at 70% of plan with rates at 7.00% the project no longer covers itself. Combining a one-point rate rise, benefits 25% below plan and a crop 15% smaller gives 0.87x. A 15% cost overrun of $3,091,800 financed with more debt cuts coverage to 1.21x, which is why the lender asked for equity, not debt, to fund any overrun.

    Delay stress

    Campaign yearBenefit on scheduleBenefit if phase 2 slips one campaignDebt serviceDSCR if delayed
    Year 1$1,229,486$1,229,486$1,260,0000.98x
    Year 2$2,865,601$1,239,986$2,020,4650.61x
    Year 3$2,901,344$2,901,344$2,020,4651.44x

    A one-campaign slip in phase 2, for example a late evaporator delivery, is the most damaging single event. In year 2 coverage falls to 0.61x and the cooperative must find $780,479 from general cash flow or a reserve. The study recommended either an interest-only period that runs through the second campaign (Part 5001 allows the first full payment up to three years from the note [1]) or a debt service reserve funded at closing.

    The membership test

    The project can pass every lender test and still fail if members stop delivering beets. The study therefore ran the whole cooperative, not only the project.

    Cooperative-level assumption (modeled)ValueSource in a real study
    Recoverable sugar290 lb per ton before project; +2.75 lb with projectFactory lab and polarisation records
    Labour (year-round and campaign)$14.00 per tonThree years of cooperative statements
    Energy$5.94 per tonThree years of cooperative statements
    Lime, chemicals, packaging$5.00 per tonThree years of cooperative statements
    Maintenance and repairs$5.00 per tonThree years of cooperative statements
    Administration and insurance$3.00 per tonThree years of cooperative statements
    Co-products (pulp, molasses)$16.00 per tonCo-product sales contracts
    Existing cooperative debt service$8,000,000 a yearLoan agreements; global debt schedule
    Grower cost of production$58.00 per tonExtension budgets and member surveys
    Net sugar price scenarioBeet payment per ton, no projectBeet payment per ton, with project and new debtChange per tonMargin over assumed grower cost ($58 a ton)
    Base (36.0 cents)$81.95$82.50$0.56$24.50
    Record's FY2026 loan-rate figure (32.70 cents, unverified)$72.38$72.84$0.47$14.84
    Price down 20% (28.8 cents)$61.07$61.43$0.36$3.43
    Price down 30% (25.2 cents)$50.63$50.89$0.26-$7.11

    At the base price the modeled beet payment is $82.50 a ton with the project and its debt, about 56 cents more than without it, and well above the assumed grower cost of $58.00. At a price 20% lower the margin over grower cost shrinks to $3.43 a ton, and at 30% lower growers lose money with or without the project. That is the real risk in a sugar cooperative loan: price, not the equipment. The project slightly improves the payment in every scenario, so it does not add to the price risk, but the study had to show the board and the bank what a low-price year does to member loyalty and delivery contracts.

    Equity and collateral

    Existing-business test, 5001.105(d)(1) (any one)RequiredModeledResult
    10% of total eligible project cost invested$2,562,800$7,628,000Pass
    10% balance-sheet equity (or debt to equity at most 9 to 1), modeled cooperative balance sheet after closing10% of assets43.3% ($142,000,000 of $328,000,000)Pass
    Collateral (modeled)ValueDiscount factor (assumption)Discounted value
    New process equipment (installed cost less contingency and soft costs)$20,612,00050%$10,306,000
    Lien on factory real estate (modeled appraised value, as is)$9,000,00070%$6,300,000
    Discounted collateral value$16,606,000
    Loan amount$18,000,000
    Discounted coverage0.92x

    The cooperative passes the existing-business equity tests easily. Collateral is the tighter test. Specialised process equipment has a thin resale market, so a 50% discount on installed cost is a conservative but realistic starting point, and with a lien on factory real estate the discounted coverage is 0.92x. Part 5001 lets the lender discount collateral and requires it to justify the discounts, and an appraisal of real estate over $250,000 must meet USPAP [1]. The study flagged the shortfall early so the bank could choose between a larger real estate lien, a smaller loan or more equity, rather than discovering it in credit committee.

    Technical and environmental feasibility

    The technical section tied every benefit in the pro forma to a document. For the slicers, the vendor's rated throughput and the factory's own slice logs; for the diffuser rebuild, a pre-project inspection report and the vendor's guarantee on sugar lost to pulp; for the evaporator, a heat and mass balance showing the steam economy gain and the condensate heat recovered; for the presses, guaranteed pressed-pulp solids, which drive dryer fuel. The study also checked electrical capacity for the new drives, structural loads for the evaporator body, and whether the work fits the intercampaign window with a realistic float.

    Environmental review under Part 5001 is a separate Agency process from the five feasibility components. The study identified the items that review would ask about: whether the evaporator and pulp dryer changes require an air permit modification, wastewater and condensate handling, and whether any work disturbs ground outside the existing factory footprint. Equipment replaced inside an existing plant usually raises fewer environmental questions than new construction, but the permit schedule still belongs in the installation timeline.

    Management and governance feasibility

    A cooperative's management section has two layers. The first is the factory team: the plant manager, maintenance and controls staff, and the engineering firm and installers that will work inside a live plant. The study looked at their record on past intercampaign projects and at who signs off commissioning.

    The second is governance. The board authorises the debt, sets the capital retain and decides how project benefits flow back to members. The study reviewed the bylaws and the growers' delivery agreements, because those documents, not the factory, guarantee the tonnage the model depends on. It noted the record's point that grower contracts sit at the centre of management feasibility. Members who are also borrowers on their own farm equipment feel price pressure first; the record notes that a single six-row harvester costs $500,000 to $700,000 new, which is part of why member payments and retains need careful setting.

    B&I eligibility also depends on the borrower and its controlling owners. Under 5001.127, a borrower is ineligible if it or an owner of more than 20% (passive investors aside) has an outstanding federal judgment, delinquent federal tax or debt, or a debarment; the lender verifies this [1]. In a cooperative with hundreds of members no member usually holds 20%, so the check centres on the cooperative itself and any controlling entity.

    Economic and community impact (modeled)

    Effect (modeled)AmountBasis
    Year-round jobs retained at the factory310Assumption for a factory of this size; a study uses payroll records
    Campaign (seasonal) jobs retained240Assumption; campaign staffing records
    New skilled jobs (controls, maintenance)6Assumption from the equipment scope
    Average annual pay used for the factory$64,888Minnesota food manufacturing average, CBP 2023 (pack)
    Added value to members per ton, year 2$0.58Benefit less new debt service, divided by tons
    Added value to members, year 2$845,136Same, total
    Member-growers served (assumption)480Membership roll; delivery contracts

    The project's case for a rural guarantee is retention more than growth. A sugar factory in a town of 7,375 is one of the largest private payrolls in the county, and its members' farms depend on its slicing capacity. The modeled impact is the factory's jobs held at a Minnesota food-manufacturing average wage of $64,888, a handful of new skilled positions, and a net gain to members after debt service. A real study replaces each assumption with payroll records, membership rolls and the cooperative's own delivery data.

    Risks and mitigants

    RiskEffect in the modelMitigant the study proposed
    Engineering benefits below guaranteeCoverage 1.06x at 75% of benefitsVendor performance guarantees with remedies; capital retain set to cover debt without benefits
    Phase 2 slips a campaignYear-2 coverage 0.61xExtended interest-only period or debt service reserve
    Installation overrun1.21x if 15% overrun is debt-financedFund overruns with equity; fixed-price installation contracts
    Sugar price fallsMember margin over cost shrinks to $3.43 a ton at -20%Board policy on retains; loan-rate floor confirmed from the CCC notice
    Short crop (weather, disease)Coverage 1.23x at -15% tonsMulti-year yield history; retains per ton set on a conservative crop
    Lower gas pricesCoverage 1.20x at -40% gasFuel savings valued at contract prices, not spot peaks
    Collateral shortfallDiscounted coverage 0.92xLarger real estate lien or more equity
    Member attritionFewer tons, higher fixed cost per tonDelivery agreements; membership trend analysis
    Seasonal cash concentrationDebt due outside campaign monthsQuarterly cash flow; payment dates matched to sugar sales

    What the five Part 5001 components showed

    Part 5001 organises an acceptable feasibility study into economic, market, technical, financial and management feasibility [4]. The engagement record lists environmental work alongside them; environmental review is a separate USDA requirement, so this page treats it under technical feasibility.

    ComponentWhat the modeled study foundWhat a reviewer would check
    EconomicFactory jobs and member farms depend on slicing capacity; the project protects bothLocal employment share; member count
    MarketVolume is bounded by member acres; price is the variable; the record's loan-rate figure gives a floor once confirmedPrice scenarios; sales contracts; loan-rate notice
    TechnicalEach benefit tied to a vendor guarantee or engineering balance; installation fits two intercampaign windowsGuarantees, heat balance, schedule float
    Financial1.42x coverage from year 2; year 1 planned below 1.00x; break-even at 70.5% of benefits; delay is the main stressPro forma, quarterly cash flow, reserves
    ManagementBoard authority, retains and delivery agreements underpin tonnage; factory team has to work inside a live plantBylaws, delivery contracts, project team record

    Studies like this one come back from lenders and state offices for predictable reasons:

    1. Savings stated as a single number with no vendor guarantee or engineering balance behind them.
    2. An annual model for a seasonal borrower, with no quarterly cash flow.
    3. Coverage computed on the project alone, ignoring the cooperative's existing debt and the membership's ability to absorb a lower payment.
    4. No delay scenario for work that must fit an intercampaign window.
    5. Collateral valued at installed cost rather than discounted resale value.
    6. The rural area test asserted from the county's non-metro status rather than the eligibility map.
    7. A sugar price assumption with no link to contracts or the loan rate.

    Program terms that applied

    FY2026 B&I termValueSource
    Guarantee, loans of $5 million to $25 million80%91 FR 11272 [2]
    Guarantee, loans under $5 million85%91 FR 11272 [2]
    Guarantee fee3.0% of the guaranteed portion (1.0% under the reduced-fee criteria)91 FR 11272 [2]; 5001.454 [1]
    Extra fee if the guarantee is issued before construction is complete0.50%91 FR 11272 [2]
    Annual retention fee0.55% of guaranteed principal outstanding at 31 December91 FR 11272 [2]; 5001.455 [1]
    Maximum loan$25 million; up to $40 million for qualifying rural cooperatives5001.406(c) [1]
    TermUseful life, up to 40 years; no balloon5001.402 [1]
    Interest rateNegotiated; fixed, variable or both; not above the lender's rate on similar loans5001.401 [1]
    Rural areaOutside cities over 50,000 and their contiguous urbanized areas5001.3 [1]
    Feasibility studyRequired over $1,000,000 for a new business; otherwise at Agency discretion5001.306(a)(3) [1]
    Agricultural productionOnly inside an integrated processing business that owns it; at most 50% of the loan or $5 million5001.105(b)(7) [1][3]

    Two of these deserve a note for cooperatives. The $40 million ceiling is not automatic; it applies to qualifying rural cooperatives that process value-added commodities and needs the Secretary's approval, so a cooperative planning a third phase should ask the state office early. And B&I does not finance members' beet growing: the agricultural production rule lets B&I fund production only when the borrower itself owns and operates it inside an integrated processing business, and caps that part of the loan [1][3].

    Lessons for sponsors of similar projects

    1. Underwrite the board, not only the factory. The lender is relying on the cooperative's power to set retains and payments. Put the bylaw provisions and the board resolution in the study.
    2. Get savings in writing from the people who will be held to them. Vendor guarantees and an engineer's heat balance turn an estimate into a number a credit officer can cite.
    3. Plan the year-1 gap. Projects installed in phases rarely cover debt in the first campaign. Show the gap and how it is funded.
    4. Model the slip. The intercampaign window is fixed; a late delivery costs a whole year of benefits. Price an extended interest-only period or a reserve before closing.
    5. Test collateral at resale value. Specialised process equipment rarely secures its own loan; decide early what else the lender can take.
    6. Check the map, not the county. Polk County is metropolitan; Crookston is not excluded on that account. A dated map determination ends the argument.
    7. Use the record's price figures only after confirming them. A loan rate or price index in the pro forma should come with its notice or contract.

    If your cooperative or processing plant is planning an equipment cycle with a guaranteed loan, a USDA feasibility study consultant can scope the study around your lender's credit memo before installation planning is final. Standard B&I studies take six to seven weeks and complex ones seven to nine, with fees listed on the cost page [12]. Request a proposal for a fifteen-minute scoping call and a written, fixed-fee proposal [13].

    David Miller, CPA

    USDA Feasibility, Inc.

    Frequently Asked Questions

    Does a cooperative need a feasibility study for a B&I equipment loan?

    Not automatically. Part 5001 requires an independent study for B&I loans over $1,000,000 to a new business, and an established cooperative is not a new business. The Agency may still require one when the application does not give enough information, and the lender must evaluate feasibility, market conditions and construction complexity in its credit analysis [1]. When repayment depends on promised savings, such as more sugar per ton or less fuel, lenders usually ask for a study because those gains are not in the cooperative's history.

    Which guarantee percentage applies to a sugar cooperative loan between $5 million and $25 million?

    Under the FY2026 notice, B&I loans of $5 million to $25 million carry an 80% guarantee, a 3.0% guarantee fee on the guaranteed portion and a 0.55% annual retention fee; loans under $5 million carry 85% [2]. A reduced-fee option at 1.0% and 0.50% exists for loans that meet the Agency's criteria. Percentages are set each fiscal year by Federal Register notice, so a 2024 study used that year's terms and a new application uses the notice in force when the loan is obligated.

    Can a sugar cooperative borrow more than $25 million under B&I?

    Part 5001 caps B&I at $25 million per borrower but allows up to $40 million for qualifying rural cooperative organizations that process value-added agricultural commodities, at the Secretary's discretion [1]. A cooperative planning a multi-year equipment program should raise the higher limit with the Rural Development state office before splitting the work into phases, because the answer changes how the phases, collateral and equity are arranged. The modeled project on this page stays inside the $5 million to $25 million tier.

    How do you calculate debt service coverage for a cooperative that pays out its net proceeds?

    Two ways, and the study shows both. The project basis divides the cash benefit of the equipment (sugar recovered, fuel and maintenance saved) by the new debt service; in the model that is 1.42x from year 2. The retain basis divides a per-ton capital retain by the debt service; a retain of $1.75 a ton covers it at 1.26x. The lender also needs the cooperative's global coverage across existing debt, and a test that the beet payment after debt still exceeds growers' costs.

    What does the sugar loan rate have to do with a feasibility study?

    It works as a floor under the price assumption. The engagement record cites a FY2026 refined beet sugar loan rate of 32.70 cents per pound for the Minnesota and eastern North Dakota region, against 25.18 cents in FY2025, and used it as the floor for pro forma scenarios. Those figures were not confirmed for this page, so the model shows the record's figure as one scenario and uses its own labelled price. A real study cites the Commodity Credit Corporation notice directly.

    Is Crookston eligible as a B&I rural area if Polk County is metropolitan?

    The county's metropolitan status does not decide it. Polk County belongs to the Grand Forks metropolitan area, but the B&I test in 7 CFR 5001.3 excludes only cities and towns over 50,000 and the urbanized area contiguous to them [1]. Crookston had about 7,375 residents in the 2025 estimate and is a separate town. The study recorded a dated determination from the USDA eligibility map, which is the evidence a reviewer accepts.

    Why does an equipment loan need a delay scenario?

    Because sugar factories can only install major equipment between campaigns. If a vendor delivers late, the work waits a year, and so do the savings that pay the debt. In the model a one-campaign slip in phase 2 drops year-2 coverage to 0.61x and leaves a shortfall of $780,479. The study proposed an interest-only period through the second campaign or a reserve at closing, both of which the lender can build into the loan terms.

    How much equity does an existing cooperative need for a B&I loan?

    An existing business meets the rule with any one of three tests at closing: at least 10% balance-sheet equity (or debt to equity of 9 to 1 or better), at least 10% of total eligible project costs invested, or owner capital of at least 10% of net fixed assets plus depreciation [1]. Equity must be cash or earning assets, not appraisal surplus. In the model the cooperative puts in $7,628,000, far above the $2,562,800 minimum, mainly to offset thin collateral on specialised equipment.

    Can the same study support a REAP grant for the evaporator upgrade?

    Partly. Since 16 October 2026 a REAP grant is applied for after the project has operated for 12 to 24 months, needs 12 months of actual savings data and 12 months of pre-installation data, and is capped at $250,000 for efficiency projects and 25% of cost [11]. The feasibility study's heat balance and baseline fuel data become the starting point for that later application, but the loan should be underwritten without the grant because it is competitive and paid after the fact.

    What would a study like this cost and how long does it take?

    The site's cost page lists $6,900 to $12,500 for standard B&I studies and $10,500 to $14,500 for complex engagements such as loans over $10 million or phased projects; a multi-phase cooperative equipment study usually falls in the complex band [12]. Standard studies take six to seven weeks and complex ones seven to nine. Every engagement starts with a scoping call and a written fixed-fee proposal, and includes all five Part 5001 components and an Excel workbook [12][13].

    Sources

    [1] 7 CFR part 5001, OneRD Guaranteed Loans (CFR 2026 edition, title 7 vol. 15, revised 1 Jan 2026), govinfo; sections 5001.3, 5001.105, 5001.127, 5001.202, 5001.203, 5001.306, 5001.401, 5001.402, 5001.406, 5001.454, 5001.455. https://www.govinfo.gov/content/pkg/CFR-2026-title7-vol15/xml/CFR-2026-title7-vol15-part5001.xml (accessed 11 Nov 2026)

    [2] USDA, OneRD Annual Notice of Guarantee Fee Rates, Periodic Retention Fee Rates, Loan Guarantee Percentage and Fee for Issuance of the Loan Note Guarantee Prior to Construction Completion for Fiscal Year 2026, 91 FR 11272 (9 Mar 2026). https://www.govinfo.gov/content/pkg/FR-2026-03-09/html/2026-04581.htm (accessed 6 Nov 2026)

    [3] USDA Rural Development, OneRD Guaranteed Loan Regulation, technical amendments, 90 FR 57351-57352 (11 Dec 2025), revising 5001.105(b)(7). https://www.govinfo.gov/content/pkg/FR-2025-12-11/html/2025-22567.htm (accessed 11 Nov 2026)

    [4] OneRD Guaranteed Loan Regulation, 85 FR 42494 (14 Jul 2020), appendix A to subpart D of part 5001, Elements of an Acceptable Feasibility Study, pp. 42556-42557. https://www.govinfo.gov/content/pkg/FR-2020-07-14/pdf/2020-13991.pdf (accessed 7 Nov 2026)

    [5] U.S. Census Bureau, County Business Patterns 2019 and 2023, state and county files. https://www2.census.gov/programs-surveys/cbp/datasets/2023/cbp23st.zip ; https://www2.census.gov/programs-surveys/cbp/datasets/2023/cbp23co.zip ; https://www2.census.gov/programs-surveys/cbp/datasets/2019/cbp19st.zip (accessed 7 Nov 2026)

    [6] U.S. Census Bureau, Vintage 2025 county population estimates (co-est2025-alldata). https://www2.census.gov/programs-surveys/popest/datasets/2020-2025/counties/totals/co-est2025-alldata.csv (accessed 7 Nov 2026)

    [7] U.S. Census Bureau, Vintage 2025 city and town population estimates (sub-est2025). https://www2.census.gov/programs-surveys/popest/datasets/2020-2025/cities/totals/sub-est2025.csv (accessed 8 Nov 2026)

    [8] OMB metropolitan and micropolitan statistical area delineation file, July 2023 (list1_2023). https://www2.census.gov/programs-surveys/metro-micro/geographies/reference-files/2023/delineation-files/list1_2023.xlsx (accessed 7 Nov 2026)

    [9] U.S. Small Business Administration, 7(a) and 504 FOIA loan data, as of 30 Sep 2026. https://data.sba.gov/dataset/7-a-504-foia (accessed 7 Nov 2026)

    [10] USAspending.gov, award counts by place of performance for Assistance Listings 10.768 (B&I), 10.766 (Community Facilities) and 10.868 (REAP), FY2024 to FY2026. https://api.usaspending.gov/api/v2/search/spending_by_award_count/ (accessed 7 Nov 2026)

    [11] USDA RBCS, Rural Energy for America Program (REAP), final rule with comment period, 91 FR 62600 (1 Oct 2026), effective 16 Oct 2026. https://www.govinfo.gov/content/pkg/FR-2026-10-01/html/2026-20178.htm (accessed 7 Nov 2026)

    [12] usda-feasibility-study.com, USDA Feasibility Study Cost & Timeline (site page). https://usda-feasibility-study.com/usda-feasibility-study-cost (read 7 Nov 2026)

    [13] usda-feasibility-study.com, Contact & Request a Proposal (site page). https://usda-feasibility-study.com/contact (read 7 Nov 2026)

    [14] usda-feasibility-study.com, Selected Engagements (site page). https://usda-feasibility-study.com/engagements (read 7 Nov 2026)

    Ready to Start Your USDA Project?

    Get your free consultation today and take the first step toward securing USDA funding for your rural development project.

    Our USDA feasibility study consultants scope every engagement against the five Part 5001 components in a free consultation.

    Get Your Free Consultation

    Fill out the form below and we'll contact you within 24 hours to discuss your project.

    We'll respond within 24 hours