Short answer
Every Section 9003 loan guarantee application must include a feasibility study. The program, formally the Biorefinery, Renewable Chemical, and Biobased Product Manufacturing Assistance Program, is governed by 7 CFR part 4279 subpart C for loanmaking and part 4287 subpart D for servicing [1][2]. Its Phase 1 application must contain a feasibility study "prepared by a qualified, independent third party," organised around a seven-part table of required components in 4279.261(e), with the author's resume or statement of qualifications attached [1]. Phase 2 adds a technical assessment by a qualified independent engineer, an appraisal, environmental documentation and, for projects with eligible costs of $25 million or more, a credit rating from a nationally recognized statistical rating organization [1].
The guarantee covers loans of up to $250 million to one borrower and up to 80% of eligible project costs, with the guarantee share falling from 80% (or 90% if three conditions are met) to 60% as the loan grows [1]. Rural Development decides whether a project is technically and economically feasible from the technical report and the feasibility study, and projects without feasibility are not selected [1].
Data current as of November 2026.
| Question | Answer from the rules |
|---|---|
| Is a feasibility study required? | Yes, in every Phase 1 application (4279.261(e)) [1] |
| Who may prepare it? | A qualified, independent third party; the author's qualifications must be submitted [1] |
| What else is technical? | A technical assessment by a qualified independent engineer in Phase 2 (4279.261(k)(8)) [1] |
| Largest loan | $250 million to one borrower; no minimum [1] |
| Loan as share of project | Up to 80% of eligible project costs; total federal participation also capped at 80% [1] |
| Guarantee share | 80% up to $125 million (90% if conditions met); 80% to under $150 million; 70% to under $200 million; 60% to $250 million [1] |
| Longest term | 20 years from closing or the project's useful life, whichever is less [1] |
| Application deadlines | October 1 and April 1, unless a Federal Register notice says otherwise [1] |
| Latest rule change | Final rule effective 9 July 2026, amending two servicing provisions in part 4287 [2] |
The site's explainer covers what the program finances, why it sits outside the OneRD rule and how its two-phase process differs from Business and Industry lending: Section 9003: The $250 Million USDA Loan Guarantee. This page is for the sponsor and lender who need to commission the study and want to know what it must contain, how it is scored and what it costs to get the structure wrong.
The independent feasibility study requirement
Part 4279 defines a feasibility study as "an analysis by an independent qualified consultant or consultants of the economic, market, technical, financial, and management feasibility of a proposed Project or business in terms of its expectation for success" [1]. The application rule adds that the study should be built from information gathered from other qualified parties and documents, such as independent engineer reports, marketing studies, feedstock studies, business plans and financial statements prepared by a certified public accountant, and that any information used must be submitted as attachments [1].
Independence is policed through the rule's definitions. A conflict of interest exists where a person has competing personal, professional or financial interests that prevent impartial action; an arm's-length transaction is one between disinterested parties with no affiliation and no security, monetary or stockholder interest in each other [1]. Contract costs above actual cost on agreements made at less than arm's length, or with an appearance of conflict, are ineligible project costs [1]. In practice that rules out the technology licensor, the engineering, procurement and construction (EPC) contractor, the developer, an equity investor and the loan packager as study authors.
| Document | Phase | Rule | Prepared by |
|---|---|---|---|
| Feasibility study (Table 1 components) | Phase 1 | 4279.261(e) | Qualified, independent third party |
| Business plan (ten items) | Phase 1 | 4279.261(f) | Borrower; may be omitted where the study covers it |
| Financial model, monthly for three years after stabilized operation | Phase 1 | 4279.261(d) | Borrower and its advisors, in an active electronic format |
| Audited financial statements; balance sheet not over 90 days old; pro forma at startup | Phase 1 | 4279.261(c) | Borrower and its accountant |
| Scoring information | Phase 1 | 4279.261(g) | Borrower and lender |
| Appraisal, with Phase I environmental site assessment | Phase 2 | 4279.261(k)(2), 4279.244 | State certified general appraiser; specialized appraiser |
| Credit rating with recovery analysis (eligible costs of $25 million or more) | Phase 2 | 4279.261(k)(5) | Nationally recognized statistical rating organization |
| Lender's credit evaluation with sensitivity review | Phase 2 | 4279.261(k)(6), 4279.215 | Lender |
| Technical assessment | Phase 2 | 4279.261(k)(8) | Qualified independent engineer |
| Environmental documentation | Phase 2 | 4279.261(k)(4) | Under 7 CFR part 1970 |
The business plan line deserves attention. The rule lets the borrower omit any or all of the ten business plan items if they are in the feasibility study [1]. A study that covers ownership and affiliates, succession, management experience, products and strategy, vendors and models of major components, resource availability, site and distribution, market and competition, three years of stabilized projections and the use of funds removes a document and a source of inconsistency from the file.
Eligibility: borrower, project and lender
| Test | Rule | What the study or application must show |
|---|---|---|
| Borrower type | Individual, entity, tribe, state or local government unit, farm cooperative, farmer cooperative organization, association of agricultural producers, national laboratory, institution of higher education, rural electric cooperative, public power entity, or a consortium (4279.209(a)) | Organizational documents and ownership chart |
| Borrower exclusions | Borrower or certain owners with a federal judgment, delinquent federal taxes or debt, or debarment (4279.209(b)) | Certifications |
| Location | Project in a State (4279.210(a)); a rural location earns 5 points but is not required | Site description |
| Project type | Commercial-scale biorefinery using eligible technology, or technologically new commercial-scale biobased product manufacturing (4279.210(b)) | Technology description and commercial-scale evidence |
| Equity | Significant cash equity from the borrower and principals; loans to the project are not equity (4279.210(c)) | Sources and uses; equity commitments |
| Lender | Federal or state chartered bank, Farm Credit institution with direct lending authority, Bank for Cooperatives, examined credit union, or the National Rural Utilities Cooperative Finance Corporation; well capitalized; experienced in similar projects (4279.208) | Lender eligibility file |
Four definitions decide most eligibility questions, and a study that does not address them leaves the reviewer to do it.
| Definition | What it requires | Where the study proves it |
|---|---|---|
| Advanced biofuel | Fuel from renewable biomass other than corn kernel starch, including cellulosic, sugar and starch (other than corn-starch ethanol), waste-derived, renewable diesel-equivalent, biogas and butanol (4279.202) | Market and technical sections |
| Eligible technology | A technology adopted in a viable commercial-scale biorefinery, or one demonstrated to have technical and economic potential for commercial application (4279.202) | Technical section, scale-up history |
| Commercial-scale | Revenue recovers full project cost with an investor-grade return; profitable without public or private subsidies after construction (volumetric excise tax not counted); feedstock contracts adequate for proposed off-take; market entry, transport infrastructure and competitive products (4279.202) | Financial and market sections; subsidy-free case |
| Technologically new | Equipment, process or method whose first commercial-scale U.S. use was within the last five years and which is used in no more than three U.S. commercial-scale facilities (4279.202) | Technical section, for biobased product manufacturing |
The commercial-scale test is the one most often under-documented. It asks the study to show profitability without subsidies, which means the financial section needs a case that strips out tax credits, carbon credits and renewable identification number value and still recovers the project's cost.
| Eligible project costs (4279.210(d)) | Ineligible project costs (4279.210(e)) |
|---|---|
| Equipment purchase and installation, including an integrated demonstration unit later used in the project | Distributions to owners or relatives who keep an ownership share |
| New construction or retrofitting, land, site work, contingency reserves | Any line of credit |
| Permit and license fees; professional services, including loan packagers (not finders) | Equipment and processes for turning corn kernel starch into biofuel |
| Working capital; insurance and bonds | Payments above actual cost on less-than-arm's-length or conflicted contracts |
| Financing costs and capitalized construction interest (not the guarantee or renewal fees) | |
| Debt service reserve and other required cash reserves | |
| Limited refinancing of interim construction loans or up to 20% of the loan to secure a first lien |
Professional fees for planning and developing the project, including the feasibility study, are eligible uses of loan proceeds when reasonable and customary in the area [1].
What the feasibility study must contain: Table 1
Table 1 of 4279.261(e) lists the elements of an acceptable study. The list below follows its seven parts; the right-hand column is what a Rural Development reviewer and the lender will test in each [1].
| Part | Required elements | What the reviewer tests |
|---|---|---|
| (A) Executive summary | Project overview; separate determinations of economic, market, technical, financial and management feasibility; recommendations for implementation | Whether each determination is an actual finding, not a description |
| (B) Economic feasibility | Feedstock description and confirmation it is not already used for advanced biofuels or biobased products; feedstock source management, volumes and costs, collection, pre-treatment, transport, storage and risks; proof that federal or public woody biomass cannot be used for a higher-value product; impacts on similar biorefineries and on plants using similar feedstock in the supply area; resource conservation, public health and environmental effects; site; trained or trainable labor; utilities, rail, air and road; jobs and rural economic impact; work with producer associations or cooperatives | Feedstock draw area and competing demand; contract coverage; labor and infrastructure evidence |
| (C) Market feasibility | Sales organization; market and market area; marketing plan for principal products and byproducts; competition and similar facilities; off-take commitments, their duration and counterparty strength; industry status, market risks, competitive threats and advantages | Signed contracts versus letters of intent; counterparty ratings; price assumptions |
| (D) Technical feasibility | Site suitability; scale at which the process is proven (pilot, demonstration or semi-work scale) with results; integration of processes and integrated demonstration unit results; specific volume; operation and development costs with stated accuracy; project timeline through commissioning and ramp-up; commercial replicability; construction, production, regulatory, design and scale-up risks | Consistency with the independent engineer's assessment; scale-up gap |
| (E) Financial feasibility | Reliability of projections and assumptions, all sources and uses; projected statements over the project's useful life; dependence on investment and productivity incentives, loans and grants, renewable identification numbers, tax credits and other credits; constraints; ability to achieve income and cash flow; cost accounting; short-term credit; raw materials; sensitivity analysis on feedstock and energy costs and product and byproduct prices; project, financing, operational and tax risks | Subsidy dependence; coverage under stress; ramp-up cash |
| (F) Management feasibility | Experience in producing the product, acquiring feedstock, selling off-take and receiving federal assistance; plan for feedstock and labor procurement, marketing and succession; company-stage, conflict-of-interest and management risks | Operator depth for a first-of-a-kind plant |
| (G) Qualifications | Resume or statement of qualifications of the author and contributors, including prior experience | Independence and relevant experience |
Two parts of Table 1 have no close parallel in a Business and Industry study. The economic section must look outward at the effect of the project on other biorefineries and on existing plants using the same feedstock, and that finding earns 5 scoring points only when it is established "through an independent third-party Feasibility Study" [1]. And the financial section must quantify how far the project depends on credits and subsidies, which feeds both the 90% guarantee test and a 4-point scoring criterion.
The technical report and the 120-day demonstration
Rural Development's technical feasibility determination is based on the technical report [1]. Part 4279 requires that every project use an independent, third-party professional engineer and that the assessment show the design, procurement, installation, startup, operation and maintenance will let the project perform as specified over its useful life, reliably and cost-effectively, on verifiable data [1].
| Technical report section (4279.261(k)(8)) | Content |
|---|---|
| (i) Qualifications of project team | Delivery method (design-bid-build or design-build), component manufacturers' history and installed units at scale, team credentials and references, operator qualifications |
| (ii) Agreements and permits | Codes, zoning, licenses, land use agreements, emissions and effluent permits, warranties, environmental issues, with schedules |
| (iii) Resource assessment | Type, quantity and storage of feedstock; competing uses; shipping and receiving; invasive species controls |
| (iv) Design and engineering | Complete integrated facility design; monthly and annual performance; effect of feedstock interruption; site, foundations, backup equipment; site control for at least the financing term |
| (v) Project development schedule | Each task from resource assessment through startup and shakedown |
| (vi) Equipment procurement | Availability and delivery within the schedule |
| (vii) Equipment installation | Site development, installation plan, startup and shakedown conditions |
| (viii) Operations and maintenance | Warranties, spare parts, maintenance schedules, useful life and major replacements, operating costs and staffing, risk plan for major component failures |
| (ix) Decommissioning | Process, requirements and costs |
Where a technology has no history of successful use in a commercial-scale biorefinery, the borrower must provide, before a conditional commitment is issued, evidence of 120 days of continuous, steady-state production from an integrated demonstration unit, reported in 30-day intervals and proving yield and quality consistent with the commercial design basis [1]. The feasibility study's yield, uptime and ramp-up assumptions should be the ones that demonstration supports. A study that projects design output in year one while the demonstration ran below design is the inconsistency a reviewer looks for first.
Guarantee terms you can confirm
| Loan amount | Maximum guarantee | Source |
|---|---|---|
| Up to $125 million | 80%, or 90% if total federal participation is not over 60% of eligible project costs, feedstock and off-take agreements run at least one year, and tax credits, carbon credits and other subsidies are not over 10% of annual revenue in the base case | 4279.232(c)(1) |
| Over $125 million and under $150 million | 80% | 4279.232(c)(2) |
| $150 million to under $200 million | 70% | 4279.232(c)(3) |
| $200 million to $250 million | 60% | 4279.232(c)(4) |
| Fee | Rate | Basis |
|---|---|---|
| Guarantee fee, 90% guarantee | 3.0% | Loan x guarantee % x rate, paid once at loan note guarantee issuance (4279.231(a)(1)) |
| Guarantee fee, under 90%, loan over 75% of eligible costs | 2.0% | 4279.231(a)(2)(i) |
| Guarantee fee, under 90%, loan over 65% to 75% | 1.5% | 4279.231(a)(2)(ii) |
| Guarantee fee, under 90%, loan 65% or less | 1.0% | 4279.231(a)(2)(iii) |
| Annual renewal fee, loan originally over 75% of eligible costs | 1.00% | Outstanding principal at 31 December x rate x guarantee %, due 31 January, payable during construction (4279.231(b)) |
| Annual renewal fee, over 65% to 75% | 0.75% | 4279.231(b)(4)(ii) |
| Annual renewal fee, 65% or less | 0.50% | 4279.231(b)(4)(iii) |
These are the rule's default rates; the rule allows the Agency to set others by Federal Register notice [1].
| Term | Rule |
|---|---|
| Loan size | Up to 80% of eligible project costs; reduced dollar for dollar by other direct federal loans or grants; borrower supplies at least 20% from non-federal sources (4279.232(a), (b)) |
| Interest rate | Negotiated, fixed or variable, no higher than the lender charges similar non-guaranteed loans; variable rates tied to a published base and adjusted no more than quarterly; changes between conditional commitment and guarantee need Agency approval (4279.233) |
| Term | Lesser of 20 years from closing or useful life; first full installment within three years of the note; no balloon except release of the debt service reserve (4279.234) |
| Collateral | First lien on all project assets, the same for guaranteed and unguaranteed portions (4279.235) |
| Lender retention | At least 7.5% of the loan, from the unguaranteed portion (4279.224) |
| Guarantors | Unconditional guarantees from owners of 20% or more for the full term; others when warranted; may be required to be secured (4279.245) |
| Appraisal | Real estate collateral over $250,000; not over one year old; "as-completed" value for construction; Phase I environmental site assessment (4279.244) |
| Construction | Independent professional design and cost estimate; onsite inspector or independent engineer; firm fixed-price EPC contract with performance guarantees or equivalent contracts; contingencies agreed with the Agency; 100% performance and payment bonds or a secured parent guarantee; borrower bears changes and overruns (4279.256) |
| Reporting | Monthly construction reports; quarterly progress reports through steady-state design capacity; annual reports and inspections for the life of the loan (4279.256(i), 4279.290) |
The 9 July 2026 final rule changed the servicing side. Debt write-downs are now prohibited where the same owners or principals keep control of the business, except under the Bankruptcy Code, and borrowers, guarantors and related parties not at arm's length are prohibited from remaining involved in a project whenever the Agency takes a loss [2]. For a sponsor, the practical meaning is that there is no path to keep a failed plant after a loss claim, which makes the downside cases in the feasibility study more than a formality.
Scoring: where the study earns points
Rural Development scores each Phase 1 application that meets the minimum technical and economic feasibility requirements, out of 125 points; an application needs at least 55 points to be considered for a guarantee [1].
| Criterion (4279.266) | Maximum | What the feasibility study supplies |
|---|---|---|
| (a) Established market: off-take commitment (6), duration (6), counterparty credit rating (4), subsidy dependence (4) | 20 | Contract status, terms, counterparty ratings, base-case subsidy share |
| (b) No similar facilities in the feedstock supply area | 5 | Supply-area mapping of existing facilities |
| (c) Feedstock not previously used commercially for these products | 10 | Feedstock history |
| (d) Feedstock from producer associations or cooperatives (50% = 5 points; 30% = 3 points) | 5 | Supply plan by source |
| (e) Financial participation: loan plus other direct federal funding as a share of eligible costs (50% or less = 20 points, falling to 4 points at 70%) | 20 | Sources and uses |
| (f) Positive effect on resource conservation, public health and the environment (3, 6 or 10 points; 5 deducted for food or feed feedstock) | 10 | Impact analysis |
| (g) No economically significant negative impact on existing plants using similar feedstocks, established through an independent third-party feasibility study (none for wood pellets) | 5 | Competitive impact finding |
| (h) Rural economic development: rural location (5), wages above county median household wages (5), majority of feedstock harvested from the land (10) | 20 | Site, wage and feedstock data |
| (i) Local ownership over 20% (3) or over 50% (5) | 5 | Ownership analysis |
| (j) Commercial replicability, regional (5) or national (10) | 10 | Replication analysis |
| (k) Technology not yet operating at commercial scale as of 1 October of the funding year | 5 | Technology status |
| (l) Administrator bonus points for portfolio diversity and partnerships | 10 | Not controlled by the applicant |
Most of these points rest on facts the feasibility study establishes. Criterion (g) is the clearest case: the rule awards its points only when the finding comes from an independent third-party study [1].
How the 9003 study compares with a Business and Industry study
| Item | Section 9003 | Business and Industry (B&I) |
|---|---|---|
| When a study is required | Every Phase 1 application [1] | Guaranteed loans over $1 million to a new business; discretionary otherwise [3] |
| Content standard | Table 1 in 4279.261(e), with feedstock, competitive-impact and subsidy-dependence elements [1] | Appendix A to subpart D of part 5001 [3] |
| Technical review | Independent professional engineer required on every project [1] | Depends on project; technical feasibility is one of five components [3] |
| Loan ceiling | $250 million [1] | $25 million [3] |
| Guarantee share | 60% to 90% by loan size and conditions [1] | 85% under $5 million and 80% from $5 million to $25 million in FY2026 [4] |
| Application timing | Two deadlines a year with ranking [1] | Continuous [3] |
The same consultant can prepare both kinds of study, but a B&I study reformatted for a 9003 file will usually miss the competitive-impact finding, the subsidy-free case and the feedstock supply-area analysis that Table 1 requires.
Worked example: structure, fees and coverage (illustrative)
This example uses an assumed project with eligible project costs of $150 million, an illustrative fixed rate of 7.0% and a 20-year level annual amortization. It shows how the loan size and guarantee choice change fees, coverage and scoring. It is not a quote, and actual rates are negotiated between the lender and borrower [1].
| Structure | A: $90M loan, 90% guarantee | B: $90M loan, 80% guarantee | C: $120M loan (maximum) | D: $75M loan |
|---|---|---|---|---|
| Loan as share of eligible costs | 60% | 60% | 80% | 50% |
| Guarantee | 90% (if all three conditions met) | 80% | 80% (federal share over 60%, so no 90%) | 80% |
| Guaranteed amount | $81,000,000 | $72,000,000 | $96,000,000 | $60,000,000 |
| Guarantee fee rate | 3.0% | 1.0% | 2.0% | 1.0% |
| One-time guarantee fee | $2,430,000 | $720,000 | $1,920,000 | $600,000 |
| Annual renewal fee rate | 0.50% | 0.50% | 1.00% | 0.50% |
| First-year renewal fee on the full balance | about $405,000 | about $360,000 | about $960,000 | about $300,000 |
| Non-federal funds required | $60,000,000 | $60,000,000 | $30,000,000 | $75,000,000 |
| Annual debt service (7.0%, 20 years) | $8,495,363 | $8,495,363 | $11,327,151 | $7,079,469 |
| Cash flow needed for 1.25x coverage | $10,619,204 | $10,619,204 | $14,158,939 | $8,849,337 |
| Financial participation points (criterion e) | 12 | 12 | 0 | 20 |
The 90% guarantee in column A is a maximum the rule allows when the conditions are met; it comes with the 3.0% fee rate, so on these numbers the extra 10 points of guarantee cost $1,710,000 more at closing than column B and about $45,000 more in the first renewal year. Column C shows the opposite trade: borrowing the maximum halves the equity requirement but doubles the renewal rate, adds $2.8 million to annual debt service and scores no financial participation points. Column D buys 8 more scoring points than A or B with $15 million more equity.
Operating sensitivity for the $90 million loan (illustrative)
| Case | Product revenue | Credit and subsidy revenue | Feedstock cost | Other operating cost | Cash flow before debt service | Coverage |
|---|---|---|---|---|---|---|
| Base | $54,000,000 | $6,000,000 (10.0% of revenue) | $27,000,000 | $15,000,000 | $18,000,000 | 2.12x |
| Feedstock cost +20% | $54,000,000 | $6,000,000 | $32,400,000 | $15,000,000 | $12,600,000 | 1.48x |
| Product price -15% | $45,900,000 | $6,000,000 | $27,000,000 | $15,000,000 | $9,900,000 | 1.17x |
| Credits and subsidies to zero | $54,000,000 | $0 | $27,000,000 | $15,000,000 | $12,000,000 | 1.41x |
| Feedstock +20% and price -10% | $48,600,000 | $6,000,000 | $32,400,000 | $15,000,000 | $7,200,000 | 0.85x |
| Output at 80% of design | $43,200,000 | $4,800,000 | $21,600,000 | $15,000,000 | $11,400,000 | 1.34x |
"Cash flow before debt service" here is revenue less feedstock and other operating costs, before taxes, capital spending and reserves; a real study would also model those. Three points follow from the table. The base case meets the 10% subsidy limit exactly; if credit revenue were $9 million on $54 million of product sales, the subsidy share would be 14.3%, the project would lose eligibility for the 90% guarantee and drop from 4 to 2 points under criterion (a)(4) [1]. The single-variable cases look survivable, but the combined feedstock and price case does not cover debt service, which is exactly the correlation a biorefinery faces when commodity markets move together. And the 80% output case is the first-of-a-kind ramp-up risk in numbers; Table 1 asks the study to address scale-up risk and the technical report to support the yield the model uses [1].
Process and timeline
| Step | Timing or rule |
|---|---|
| Letter of intent identifying borrower, lender, sponsors, project, feedstock, technology, products, cost and loan request | At least 30 calendar days before the application deadline (4279.260(a)(1)) |
| Phase 1 application, including the feasibility study, financial model and business plan | Deadlines 1 October and 1 April unless a Federal Register notice says otherwise; incomplete applications rejected (4279.260(b), (c)) |
| Eligibility and technical and economic feasibility determination | On a complete Phase 1 application (4279.265) |
| Ranking | By about 31 October and 30 April; up to 50% of budget authority (excluding biobased product manufacturing) for the first window (4279.267(a), (b)) |
| Invitation to Phase 2 | Highest scores first, minimum 55 points, subject to budget authority and other funding (4279.267(c)) |
| Unselected ranked applications | Carried forward one more application cycle (4279.267(d)) |
| Phase 2 | Appraisal, loan agreement terms, environmental documentation, credit rating, lender credit evaluation, technical assessment (4279.261(k)) |
| 120-day integrated demonstration evidence | Before the conditional commitment, for technology without commercial-scale history (4279.265(b)(2)) |
| Conditional commitment | Void unless accepted by lender and borrower within 60 days (4279.278(b)) |
| Closing and loan note guarantee | Lender certifies 16 conditions, including no material adverse change (4279.281) |
| After construction | Annual borrower reports and annual inspections for the life of the loan (4279.290) |
Deadlines can move. In December 2024 USDA reopened the 1 October 2024 deadline and extended it to 31 December 2024 by Federal Register notice [5]. USDA's 2024 information collection estimate for the program counted 26 respondents and 7,803 total burden hours [6]. For the study itself, the practical schedule works backward from the letter of intent: feedstock and off-take evidence, the demonstration data and the engineer's scope must exist before the study can reach conclusions.
Why 9003 feasibility studies get sent back
- No subsidy-free case, so the commercial-scale test is unanswered.
- Off-take described as "strong interest" without stating whether agreements are signed, letters of intent or letters of interest, the three levels the scoring rule distinguishes.
- Feedstock volumes quoted without a draw area, competing users or contract terms.
- No finding on effects on other biorefineries or plants using similar feedstock.
- Yields and uptime that exceed what the pilot, demonstration or semi-work scale results support.
- A single-variable sensitivity analysis where feedstock and product prices plausibly move together.
- The study, the financial model and the independent engineer's report use different capacity, cost or schedule figures.
- The author has a role in the project, or the qualifications statement is missing.
Hiring a Section 9003 feasibility study consultant
The rule leaves the choice of consultant to the borrower and lender but sets the bar: qualified, independent, third party, with prior experience documented in the qualifications section [1]. Ask any candidate to show where each Table 1 element will appear, how the study will reconcile with the independent engineer, and whether it will deliver the five separate determinations and a recommendation. Professional fees for planning and developing the project, including the study, are eligible uses of loan proceeds when reasonable and customary [1], and an agent may not act as both loan packager and loan service provider on the same loan [1].
What this site provides on a 9003 engagement is the independent feasibility study: economic, market, financial and management analysis, the subsidy-free and combined-stress cases, the competitive-impact finding, the executive determinations and recommendation, and the authors' qualifications. The technical assessment is the independent engineer's; engineering, environmental site assessments, appraisals and legal work are outside the site's scope [7]. The study is written to be consistent with the engineer's report, and the financial projections are built to the monthly-then-annual format of 4279.261(d) so the lender's model and the study can be reconciled.
The site's cost page does not list Section 9003. Its published tiers top out at complex OneRD engagements of $9,500 to $18,000 over 7 to 10 weeks [7]; a 9003 study is scoped and quoted individually, at a firm fixed fee in a written proposal, after a fifteen-minute scoping call [7][8]. What you provide: technology and demonstration data, the engineer's scope or draft report, feedstock and off-take agreements or term sheets, the sources and uses, the financial model, ownership documents and management resumes.
Request a scoped proposal for your Section 9003 feasibility study at the contact page. A senior analyst responds within one business day [8].
Related pages
- Section 9003: The $250 Million USDA Loan Guarantee, the program explainer.
- Renewable energy feasibility study, for REAP and B&I energy projects.
- USDA B&I feasibility study, for projects under $25 million on proven technology.
- Food processing feasibility study, for biobased and value-added processing on the B&I side.
- Conventional vs USDA feasibility study, on what a USDA-grade study adds.
- The USDA Feasibility Study Framework.
USDA Feasibility, Inc.