USDA Water and Waste Disposal Feasibility Study and PER Support

    Last updated 2026-11-08

    Short answer

    A USDA Water and Waste Disposal (WWD) application is judged on two documents that answer different questions. The preliminary engineering report (PER) answers whether the proposed water, sewer, solid waste or storm water facility is the right one and what it will cost. The feasibility and financial work answers whether the people who will use it can pay for it: how many users will connect, what the system will cost to run, what rate each household will pay, and how much of the project a grant must carry so that the rate stays reasonable. Rural Development decides the loan, the grant and the interest rate from that second set of numbers [1].

    The direct loan and grant program is governed by 7 CFR part 1780. It serves public bodies, nonprofit associations and tribes in rural areas, defined as places not in a city or town of more than 10,000 people [1]. Guaranteed WWD loans made by commercial lenders sit in the OneRD rule at 7 CFR part 5001, carry a 90% guarantee and a 1.0% fee in fiscal year 2026, and are capped at $50 million per borrower [2][3].

    Data current as of November 2026.

    QuestionAnswer from the rules
    Which rule governs?7 CFR part 1780 for direct loans and grants; 7 CFR part 5001 for guaranteed loans [1][2]
    Who can apply?Public bodies, community-controlled nonprofits and federally recognized tribes [1]
    Rural test, direct and grantNot in a city or town over 10,000 people, from the latest decennial census [1]
    What the engineer must deliverA PER that conforms to customary professional standards, prepared by an engineer licensed in the state [1]
    What the financial work must proveRevenues cover operation and maintenance, reasonable reserves and debt payment [1]
    Longest loan termUseful life, state statute or 40 years, whichever is less [1]
    Largest grant75% or 45% of eligible project cost, depending on median household income [1]
    FY2026 guaranteed terms90% guarantee, 1.0% guarantee fee, no annual retention fee, 0.50% fee for a guarantee issued before construction is complete [3]

    The site's WWD article explains the program in general terms; read it first if the program is new to you: Water and Waste Disposal Program: Feasibility Requirements. This page is for a utility, district or nonprofit that is ready to assemble an application and needs to know exactly what the feasibility side must contain, how the grant is sized and who should prepare each piece.

    Who prepares what in a WWD application

    Part 1780 places the work on the owner. Applicants are responsible for "providing the services necessary to plan projects including design of facilities, environmental review and documentation requirements, preparation of cost and income estimates, development of proposals for organization and financing, and overall operation and maintenance of the facility" [1]. Those are three different professional jobs, and the rule treats them differently.

    Document or taskRuleWho prepares itWhat the Agency checks
    Preliminary engineering report (two copies with the initial application)1780.33(c), 1780.55The owner's engineer, licensed in the state where the facility is built (1780.54)Conformity with customary professional standards; State staff engineer review
    Environmental report1780.33(f), 1780.55Environmental professionals under 7 CFR part 1970State Environmental Coordinator review; no action limiting alternatives before review ends (1780.57(a))
    Operating budget (Form RD 442-7)1780.33(h)(1), 1780.41(a)(2)Applicant, usually with its accountant, fiscal advisor or feasibility consultantRevenue covers O&M, reserves and debt service (1780.7(f))
    User estimates and rate schedule1780.39(c), 1780.35(c)Applicant and its financial advisor or feasibility consultantRealistic users, signed user agreements, cash contributions
    Grant determination1780.35(b)Processing office, from the applicant's numbersDebt service share of median household income; similar system cost
    Business viability assessment1780.7(f); 5001.305(c) for guaranteed loansApplicant or lender, best documented by an independent business study, when a business is the main userWhether the business the system depends on can pay
    Credit elsewhere certification1780.7(d), 1780.33(d)ApplicantInability to finance at reasonable rates and terms
    Bond transcript and notes1780.39(b)(3), subpart DRecognized bond counsel, for public bodiesEvidence of indebtedness

    Two consequences follow. First, a general business consultant should not write the PER; the engineer of record does. The site's own WWD article says the same: engineering firms lead WWD project teams and feasibility consultants support the analytical components [5]. Second, the financial case is not a formality. The user count, operating budget, reserve schedule and rate design decide the loan amount, the grant amount and, through the median household income tests, the interest rate. If those numbers are weak, a sound engineering design can still produce a rate that the Agency will not accept.

    Eligibility under 7 CFR part 1780

    Eligibility has six parts, and an application fails if any one is missing.

    TestWhat the rule saysEvidence the application needs
    Applicant typePublic body; nonprofit association, cooperative or corporation controlled by local public bodies or broadly owned by local people; federally recognized tribe (1780.7(a))Organizational documents, membership records
    Rural areaNot in a city or town over 10,000 inhabitants per the most recent decennial census (1780.3)Census population of the place served
    Rural share of the facilityFacilities may sit in non-rural areas, but funds pay only for the portion serving rural areas (1780.7(b))Cost allocation between rural and non-rural users
    Project need and designWill not decline below design population; adequate capacity for present and reasonably foreseeable growth; consistent with a current development plan (1780.7(c))Population trend, growth assumptions, plan consistency
    Credit elsewhereApplicant cannot finance from its own resources or commercial credit at reasonable rates and terms (1780.7(d))Written certification; lender responses where available
    Legal authorityAuthority to own, build, operate, borrow, pledge security and repay (1780.7(e))Statutes, charter, ordinances, attorney opinion
    Economic feasibilityTaxes, assessments, income or fees sufficient for operation and maintenance, reasonable reserves and debt payment (1780.7(f))Operating budget, user estimates, rate schedule
    CapabilityFinancial, technical and managerial capability to comply with federal and state requirements; alternatives of ownership, design and shared services considered (1780.1(j))Staffing, operator certification, audits, alternatives analysis

    The guaranteed program uses different eligibility language. A WWD guaranteed borrower must be a public body, tribe or nonprofit; it must certify that it cannot obtain credit elsewhere without the guarantee; and it must show significant community support through a certification from each affected local government [2]. The project must be in a rural area as defined in 5001.3, which for part 5001 means outside a city or town of more than 50,000 people and its contiguous urbanized area, and projects serving both rural and non-rural users are guaranteed only for the rural portion [2].

    Eligible purposes and limits

    Loan and grant funds may build, enlarge, extend or improve rural water, sanitary sewage, solid waste and storm wastewater facilities, plus the public and private relocations and connection charges needed for those facilities to work [1]. Some costs can be paid only with loan money, and some are barred altogether.

    CategoryLoan or grantLoan onlyNot eligible
    Construction and improvementFacilities, relocations, connection charges under service contracts (1780.9(a) to (d))Facilities not modest in size, design and cost (1780.10(a)(1))
    Professional feesLegal, engineering, administrative, fiscal advisory, recording, environmental analyses, planning (1780.9(e)(1)(i))Loan or grant finder's fees (1780.10(a)(2))
    Land and rightsLand, water rights, leases, permits, rights-of-way (1780.9(e)(1)(ii))
    Financing and start-upConstruction-period interest; initial operating expenses for ordinarily up to one year; purchase of existing facilities; limited refinancing (1780.9(e)(2))
    Business usersCosts normally borne by a business or industrial user, such as wastewater pretreatment (1780.10(a)(5))
    Sewer designNew combined storm and sanitary sewers (1780.10(a)(3))
    BroadbandUp to 10% of the amount provided, for related broadband infrastructure (1780.9(h))

    Costs incurred before approval can be paid only if the applicant asks in writing and the Agency finds compelling reasons, with no commitment to make the loan or grant (1780.9(f)) [1]. That matters for planning budgets: fiscal advisory and feasibility fees are eligible project costs, but a utility that pays them before approval carries the risk.

    Loan and grant terms you can confirm

    The rule fixes the structure of WWD pricing; the quarterly rates themselves are set by the Agency.

    TermRuleSection
    Rate settingSet each quarter, rounded to the nearest one-eighth of 1%; the lower of the rate at approval or closing unless the applicant chooses otherwise1780.13(a)
    Poverty rate60% of the market rate, not over 5%; requires a project to meet health or sanitary standards and service-area median household income below the higher of the poverty line or 80% of the statewide nonmetropolitan median household income1780.13(b)
    Intermediate rate80% of the market rate, not over 7%; service-area median household income not more than 100% of the statewide nonmetropolitan median1780.13(c)
    Market rateGuided by the average Bond Buyer Index for the four weeks before the first Friday of the last month before the quarter1780.13(d)
    TermUseful life, state statute or 40 years from the note or bond date, whichever is less; maximum term when grant funds are used1780.13(e)
    Principal deferralUp to 36 months after the first interest installment, longer only with Agency authorization1780.13(e)(1)
    Maximum grant75% of eligible project costs where income is below the higher of the poverty line or 80% of the statewide nonmetropolitan median and the project fixes a health or sanitary problem; 45% where income is above that level but not over 100%1780.10(c)
    Grant barsNo grant to reduce user cost below similar system cost, where income exceeds 100% of the statewide nonmetropolitan median, or where the other loan is not at reasonable rates and terms1780.10(b)
    ReservesDebt reserve of at least one average annual installment, built at one-tenth of an installment per year, unless state law prohibits; reserves for short-lived asset replacement1780.39(e), 1780.35(c)
    Interim financingFor loans over $500,000, commercial interim construction financing where available at reasonable rates1780.39(d)
    SecurityGeneral obligation, taxes or assessments, or facility revenues for public bodies; assignment of income and liens for other borrowers1780.14

    The guaranteed program has its own terms. For fiscal year 2026, USDA set the WWD guarantee at 90%, the guarantee fee at 1.0%, no periodic retention fee, and a 0.50% fee when the loan note guarantee is issued before construction is complete [3]. A $10,000,000 guaranteed WWD loan would therefore carry a $9,000,000 guaranteed portion and a one-time fee of $90,000. Part 5001 limits WWD guaranteed loans to $50 million per borrower, including existing WWD guaranteed debt, and requires the lender to certify that it would not make the loan without the guarantee [2].

    What the PER must contain

    Part 1780 does not print a PER outline. It says PERs "must conform to customary professional standards" and that PER guidelines for water, sanitary sewer, solid waste and storm sewer "are available from the Agency" [1]. Those guidelines are published on the Rural Development website, which this page does not cite; your engineer and the State staff engineer will work from the current version. What the regulation itself requires of the design is specific, and every item below needs a place in the PER.

    Design requirementSectionWhat the PER should show
    Environmental impact analysis built into planning and design1780.57(a), 1780.31(e)Alternatives considered before any action that narrows them; mitigation in the design
    Safe Drinking Water Act progress for water systems1780.57(g)How the project moves the system toward compliance
    Federal and state effluent standards for discharge or waste systems1780.57(h)Effluent conformity
    Water loss for existing systems1780.57(f)Evidence that distribution losses do not exceed reasonable levels
    Metering1780.57(m)A meter on each water connection, or a justified exception
    Fire protection and growth capacity1780.57(d), (e)Capacity sized for reasonable fire protection and growth
    Most economical service practicable1780.57(n), 1780.10(a)(1)Least-cost alternative; facilities modest in size, design and cost
    Combined sewers1780.57(i)No new combined systems; extensions only where separation is impractical
    Dam safety, seismic safety, pipe standards, leakage testing1780.57(j), (o), (k), (l)Compliance with the cited federal guidelines and ASTM or AWWA standards

    For a guaranteed WWD loan, part 5001 sets a floor: engineering documentation at the level of detail a lender would require for a standard commercial loan, including at minimum a project description, a cost estimate, the number of residential and non-residential connections and the population served [2]. The Agency states that it does not provide technical oversight or recommendations on technical feasibility for guaranteed projects; the lender must ensure that the design follows accepted practice, meets federal requirements including American Iron and Steel, and will be completed within available funds [2].

    The point where engineering and feasibility meet is the user count. The PER's design population and connection count must be the same numbers the operating budget uses. A PER sized for 600 connections paired with a rate study built on 450 paying users is the kind of mismatch a reviewer stops on.

    What the feasibility and financial work must contain

    Part 1780 does not use the phrase "feasibility study" for direct loans the way part 5001 does for business loans. It uses tests: economic feasibility, realistic users, reasonable user charges, reserves and capability [1]. A lender-grade WWD feasibility package is the document that passes those tests with evidence.

    ComponentRuleWhat it must prove
    Realistic users1780.39(c)(1)Rates set on a realistic number of users, not the maximum the system could serve
    Signed users1780.39(c)(3)Enforceable user agreements with a penalty clause for new users, unless use is mandatory or users already receive service
    User cash contributions1780.39(c)(2)Contributions near one year's minimum user fee, paid before closing or construction, unless waived
    Vacant lots1780.39(c)(4)Vacant property counted only with development plans, a written payment agreement and a bond or escrow
    Connection program1780.39(c)(5)A plan to get every signed user connected as soon as service is available
    Operating budget1780.33(h)(1)Operation, maintenance, debt service and reserves on Form RD 442-7
    Reserves1780.39(e), 1780.35(c)Debt reserve schedule and short-lived asset replacement without building a substantial surplus
    Rate design1780.35(c)User charges that are reasonable and cover all costs after completion
    Grant need1780.35(b)Debt service share of median household income; similar system cost comparison
    Business dependence1780.7(f)Viability of any business that is the primary user and on which the system depends
    Population durability1780.7(c)(1)The served area is not likely to fall below the design population
    Service-area equity1780.11(b)Unjustified differences in service within the area are remedied
    Management capability1780.1(j), 1780.47Staff, operator capacity, accrual-basis statements and audits

    For guaranteed loans, part 5001 adds a parallel test: projected taxes, assessments, revenues or fees must cover operation and maintenance, any reserves the lender requires and debt payment, and the lender's credit analysis must account for any interest rate adjustment under the guarantee [2]. Where the majority user is a business and the system depends on it, the business's economic viability must be assessed [2]. That is the situation in which an independent business feasibility study is most clearly needed on a WWD file: a sewer extension built for a food processor, a water line serving a single industrial park tenant, or a solid waste facility whose tonnage comes from one hauler.

    Priority points: how WWD applications are ranked

    When funds are limited, the Agency ranks eligible direct loan and grant applications by points [1]. The feasibility package is where most of these points are documented.

    Priority (direct loans and grants)PointsSection
    Serves a rural area of 1,000 people or fewer251780.17(a)(1)
    Serves 1,001 to 2,500151780.17(a)(2)
    Serves 2,501 to 5,50051780.17(a)(3)
    Emergency, water supply deterioration or Safe Drinking Water Act requirement251780.17(b)(1)
    Corrects wastewater inadequacies or health standards251780.17(b)(2)
    Solid waste administrative orders151780.17(b)(3)
    Median household income below the poverty line, where that line is below 80% of the statewide nonmetropolitan median301780.17(c)(1)
    Median household income below 80% of the statewide nonmetropolitan median201780.17(c)(2)
    At or above the poverty line and between 80% and 100%151780.17(c)(3)
    Merges smaller facilities151780.17(d)(1)
    Extends service to additional rural areas101780.17(d)(2)
    Public body or tribe51780.17(d)(3)
    Other than RUS funds: 50% or more / 20% to 49% / 5% to 19%15 / 10 / 51780.17(d)(4)
    Agency identified target areas101780.17(d)(5)
    Primarily recycles solid waste51780.17(d)(6)
    Unreliable drinking water quality or supply101780.17(d)(7)
    State program official points, with written justificationup to 151780.17(e)
    National Office pointsup to 151780.17(g)

    Guaranteed WWD applications are scored on a separate 150-point scale [2].

    Priority (guaranteed loans)PointsSection
    Primarily serves a rural area under 10,000 people205001.317(a)
    Health priorities (same three categories as direct)25 / 25 / 155001.317(b)
    Long-term population decline over the last three censuses55001.317(c)(1)
    Rural county with 20% or more in poverty for 30 years55001.317(c)(2)
    Unemployment at 125% or more of the state rate55001.317(c)(3)
    Merges facilities / extends to additional rural areas10 / 105001.317(d)(1), (2)
    Public body or tribe55001.317(d)(3)
    Non-Rural Development funds: 50% or more / 20% to 49% / 5% to 19%15 / 10 / 55001.317(d)(4)
    Target areas / solid waste recycling / unreliable drinking water5 / 5 / 105001.317(d)(5) to (7)
    Approval official and Administrator pointsup to 15 each5001.317(e), (f)

    Two of these lines reward financial structure rather than need. The share of non-USDA money in the project moves an application by up to 15 points under either scale, which is why the funding plan, including any state revolving fund, community development block grant or local contribution, belongs in the feasibility package with commitment letters rather than as a hope.

    Grant determination and affordability: the tests in order

    Rural Development does not set the grant by negotiation. Part 1780 sets a sequence [1]:

    1. Compare the service area's median household income with the statewide nonmetropolitan median household income. Both come from five-year American Community Survey data unless the applicant documents that the data misrepresent the area and supplies a reliable survey (1780.1(b)).
    2. That ratio sets the maximum grant share (75% or 45%), the interest rate tier and the income priority points.
    3. The applicant is considered for a grant when the debt service portion of the average annual cost per equivalent dwelling unit (EDU) exceeds 0.5% of median household income (income at or below 80% of the statewide nonmetropolitan median) or 1.0% (income above that, up to 100%) (1780.35(b)(2)).
    4. If that grant would bring the annual EDU cost below the cost of similar systems in comparable communities, the grant is reduced so that it does not (1780.35(b)(3)).
    5. The loan carries the rest, at the maximum term (1780.13(e)).
    Service-area income vs statewide nonmetropolitan medianInterest rate tierMaximum grantDebt service threshold for grant considerationIncome priority points
    Below the poverty line (where the line is below 80% of the median), health or sanitary projectPoverty (60% of market, max 5%)75%0.5% of income30
    Below 80%, health or sanitary projectPoverty (60% of market, max 5%)75%0.5% of income20
    Below 80%, other projectIntermediate (80% of market, max 7%)45%0.5% of income20
    80% to 100%Intermediate (80% of market, max 7%)45%1.0% of income15
    Above 100%MarketNo grantNot applicable0

    Read the poverty-rate and 75% grant rows together with the project purpose: both depend on the project meeting health or sanitary standards [1]. An extension for growth in a low-income area gets the intermediate rate and a 45% ceiling.

    Worked example: user-rate affordability (illustrative)

    The numbers below are illustrative. They follow the 1780 tests in order with stated assumptions; they are not a quote of current rates, which Rural Development publishes each quarter.

    Inputs

    InputValueBasis
    ProjectWastewater treatment upgrade required to meet health standardsQualifies for the poverty rate and 75% grant ceiling if income test is met
    Eligible project cost$7,500,000Assumed
    Realistic paying users450 EDUs (420 residential, 30 commercial EDUs)1780.39(c)(1): realistic, not maximum
    Service-area median household income$46,000Assumed ACS five-year figure
    Statewide nonmetropolitan median household income$60,000Assumed; 80% is $48,000
    Income ratio76.7%Below 80%, so 0.5% debt service threshold
    Illustrative market rate4.125%Assumed for the example
    Poverty rate2.5% (60% of 4.125% = 2.475%, rounded to the nearest one-eighth)1780.13(a), (b)
    Term40 years, annual payments1780.13(e)
    Operation and maintenance per EDU$420 per yearAssumed operating budget
    Short-lived asset reserve per EDU$45 per yearAssumed

    Results

    StepCalculationResult
    Debt service threshold per EDU0.5% x $46,000$230 per year
    Debt service the users can carry at the threshold450 x $230$103,500 per year
    Annual payment factor, 2.5% for 40 years0.039836
    Supportable loan$103,500 / 0.039836about $2,598,000
    Grant$7,500,000 - $2,598,000$4,902,000 (65.4%, under the 75% ceiling)
    Debt reserve buildOne-tenth of the annual installmentabout $10,350 per year, $23 per EDU
    Annual cost per EDU$230 debt service + $420 O&M + $23 debt reserve + $45 short-lived asset reserve$718 per year
    Monthly bill per EDU$718 / 12$59.83
    Bill as share of median household income$718 / $46,0001.56%

    Sensitivity: what moves the grant and the bill

    ScenarioEffectAnnual cost per EDUMonthly
    Base case aboveLoan about $2.60 million, grant $4.90 million$718$59.83
    Only 400 users connect; loan unchangedDebt service rises to about $259 per EDU (0.56% of income)$750$62.47
    Similar systems cost $760 per yearGrant reduced so the EDU cost is not below $760; loan rises to about $3.03 million, grant falls to about $4.47 million (59.6%)$760$63.33
    No grant, poverty rate, full $7.5 million loanDebt service about $664 per EDU$1,195$99.61
    No grant, at the 4.125% illustrative market rateDebt service about $858 per EDU$1,409$117.38
    Income at 90% of the state median ($54,000), intermediate rate 3.25%Threshold 1.0% = $540 per EDU; loan about $5.40 million; grant about $2.10 million (28.0%, under the 45% ceiling)$1,059$88.25

    Three lessons come out of the arithmetic. The user count drives everything: every user that does not connect raises the bill for everyone else, which is why the rule requires signed user agreements, cash contributions and a connection program [1]. The similar system cost test can take grant away from a community that has kept rates low for years, so the comparison set of systems must be chosen and documented with care. And income data decides the tier: a service area at 79% of the state median and one at 81% face different thresholds, rates and grant ceilings, so where five-year ACS figures look wrong for a small area, the rule allows a reliable income survey (1780.1(b)) [1].

    The market: how many places the 10,000 test reaches

    The direct program's population line is low, but most American municipalities fall under it. In the Census Bureau's Vintage 2025 incorporated place estimates, 16,331 of 19,483 incorporated places (83.8%) had an April 2020 estimates base of 10,000 or fewer people, together home to about 28.2 million residents [4].

    Incorporated places by April 2020 population basePlacesShare of placesPopulationShare of incorporated-place population
    1,000 or fewer (25 priority points)9,28247.6%3,614,0621.7%
    1,001 to 2,500 (15 points)3,36217.3%5,485,3152.6%
    2,501 to 5,500 (5 points)2,28911.7%8,628,9064.1%
    5,501 to 10,000 (eligible, no population points)1,3987.2%10,447,3215.0%
    10,001 to 50,000 (outside the direct rural test)2,35412.1%51,592,73524.6%
    Over 50,0007984.1%129,986,12062.0%
    Total19,483100%209,754,459100%

    Source: U.S. Census Bureau, Vintage 2025 subcounty population estimates, incorporated places (summary level 162), ESTIMATESBASE2020 [4]. Townships and unincorporated areas are not places in this file and are also rural under the 10,000 test. The rule uses the decennial census count, which the estimates base approximates.

    The same file shows why the "will not decline below design population" test in 1780.7(c)(1) deserves real analysis. Between the April 2020 base and July 2025, 8,407 of those 16,331 small places (51.5%) lost population in the Census estimates [4].

    Population band (April 2020 base)PlacesPlaces that lost population by 2025Share losingBand population change 2020 to 2025
    1,000 or fewer9,2825,06454.6%+1.1%
    1,001 to 2,5003,3621,73151.5%+2.2%
    2,501 to 5,5002,2891,01944.5%+3.6%
    5,501 to 10,0001,39859342.4%+4.1%

    The smallest places are where priority points are highest and where population loss is most common. A WWD feasibility package for a town of 800 should therefore show the town's own trend, the user count it implies over the loan term, and a rate case at a lower user count.

    StateIncorporated places of 10,000 or fewerShare of the state's incorporated places
    Illinois1,07282.8%
    Texas98880.7%
    Pennsylvania94393.0%
    Iowa89795.5%
    Missouri85691.5%
    Minnesota75488.1%
    Ohio74780.8%
    Kansas59094.4%
    Oklahoma54792.6%
    Nebraska51297.0%

    Source: as above [4]. Counts are places, not water or sewer systems; many small places are served by rural water districts that cross place lines.

    Process and timeline

    The rule sets several clocks. The rest of the timeline depends on engineering, environmental review, funding cycles and bids.

    StageWhat happensRule or timeframe
    Early contactProcessing office explains eligibility; can point to technical assistance on income surveys and rate schedules1780.31(a), (b)
    Eligibility determination (optional)Written request instead of a full SF 424.2; does not give funding priority1780.31(c)
    PER preliminary review (optional)PER may be submitted before the rest of the application1780.33(c)(1)
    Initial applicationSF 424.2, intergovernmental review, two PER copies, credit elsewhere certification, eligibility documents, environmental report1780.33
    Completeness checkApplicant told within 15 federal working days what is missing1780.32(a)
    Eligibility and funding adviceWithin 45 days of a completed application1780.32(b)
    Public notice of intentNewspaper notice within 60 days of filing1780.19(a)
    Public information meetingBefore approval, with notice at least 10 days ahead, unless a vote or referendum authorizes the debt1780.19(b)
    Selection for further processingHighest priority scores first, subject to funds1780.36
    Processing conference and full applicationOperating budget, user agreements, professional service contracts, insurance1780.39
    Letter of conditions and obligationIssued only when funds are available; obligation on Form RD 1940-1 sets the approval-date rate1780.39(i), 1780.41
    Before closing or constructionInsurance, verification of users and contributions, applicant funds deposited, other funds committed, title and rights-of-way1780.44
    ConstructionInterim financing for loans over $500,000 where available; multiple advances only for loans over $100,0001780.39(d), 1780.45(b)

    The feasibility and financial work belongs early, ideally alongside the PER and before the initial application, because the user count, budget and income evidence decide the score, the rate tier and the grant. The site's general engagement schedule runs 4 to 8 weeks from signed engagement letter to final report, with a 3 to 4 week rush option [6].

    Common reasons WWD files stall

    • The rate study uses the maximum possible users rather than a realistic count (1780.39(c)(1)).
    • New users have not signed enforceable user agreements or paid contributions (1780.39(c)(2), (3)).
    • Vacant lots are counted as paying users without bonds or escrow (1780.39(c)(4)).
    • The PER and the operating budget use different connection counts or design populations.
    • The operating budget omits the debt reserve or short-lived asset replacement (1780.39(e)).
    • Service area boundaries leave out users in a way that raises a nondiscrimination or inequity question (1780.35(a), 1780.11(b)).
    • The project depends on one business, and nobody has assessed that business (1780.7(f)).
    • Project costs include items a business user should pay, such as pretreatment (1780.10(a)(5)).
    • Work started or land was committed before environmental review ended, limiting alternatives (1780.57(a)).
    • Engineering was not procured on qualifications, or professional service contracts were not sent for Agency concurrence (1780.39(b)).
    • Median household income data are disputed late, after the grant has been calculated (1780.1(b)).

    Hiring a WWD feasibility study and PER consultant

    Start with the engineer. Part 1780 requires the owner to announce engineering and architectural service needs publicly and to negotiate those contracts on demonstrated competence and qualifications at a fair and reasonable price; state procurement law can be used if the State Director finds it meets the same intent (1780.39(b)(1)) [1]. The engineer must be licensed in the state where the facility will be built (1780.54) [1].

    Then decide who prepares the financial case. Part 1780 lists accountants, auditors, appraisers, environmental professionals and financial advisors among the professional services a project may need, and requires that every contract between the applicant and its professional and technical representatives be in writing and be subject to Rural Development concurrence (1780.39(b)) [1]. Fees count as reasonable when they do not exceed what the profession charges for similar work without USDA financing [1]. That concurrence requirement is a useful screen: a feasibility consultant whose scope and fee you cannot show to the processing office is the wrong one.

    This site does not prepare PERs and does not lead WWD engineering; it works with the applicant's engineering firm on the feasibility and financial components, as its WWD article states [5]. For a WWD application that means:

    • User and demand analysis: realistic user counts, signed-user status, vacant property, growth and decline scenarios.
    • Operating budget review and projection consistent with Form RD 442-7, including debt and short-lived asset reserves.
    • Rate design and affordability analysis: debt service per EDU against the median household income thresholds, similar system cost comparison, sensitivity cases.
    • Grant determination modelling so the governing body sees the likely loan and grant split before it adopts rates.
    • Business viability assessment where a business is the primary user (1780.7(f), 5001.305(c)).
    • Management and capability review for the five feasibility components where a lender or the Agency asks for a full study.

    On this site's standard terms, an engagement is quoted at a firm fixed fee in a written proposal, includes a projection with sensitivity analysis, a PDF and Word report with an Excel workbook, a kickoff and a midpoint call and one round of revisions; engineering, environmental assessments, legal work and appraisals are separate [6]. The site's WWD article estimates, for substantial WWD applications, $8,500 to $18,500 or more for a separate feasibility study and $5,000 to $15,000 or more for rate analysis when it is not bundled with the PER, alongside engineering and environmental costs that the engineer and environmental consultants quote [5].

    What you provide: the PER or its draft and the engineer's cost estimate; the current rate ordinance and three years of audits or financial statements; the customer list by class and the signed user agreements; existing debt instruments; any income survey; and letters for other funding sources. A senior analyst responds to each inquiry within one business day with a scoped proposal or follow-up questions [7].

    Request a scoped proposal for the feasibility and rate work on your WWD application at the contact page.

    David Miller, CPA

    USDA Feasibility, Inc.

    Frequently Asked Questions

    Does a USDA Water and Waste Disposal loan require a feasibility study?

    Part 1780 does not use the term the way the business programs do, but it requires the same substance. Every project must show that taxes, assessments, fees or other revenues will cover operation and maintenance, reasonable reserves and debt payment (1780.7(f)), with rates set on a realistic user count (1780.39(c)) and an operating budget on Form RD 442-7. Where a business is the main user and the system depends on it, the business's viability must be assessed. A guaranteed WWD loan under part 5001 adds the same revenue test to the lender's credit analysis.

    Who prepares the preliminary engineering report?

    The owner's engineer. Part 1780 makes owners responsible for engineering services, requires engineers to be licensed in the state where the facility is built, and requires engineering services to be procured on qualifications at a fair and reasonable price. The PER must conform to customary professional standards; the Agency publishes PER guidelines for water, sewer, solid waste and storm sewer projects. A feasibility consultant should use the PER's cost estimate and connection count, not write the PER.

    What is the population limit for WWD direct loans and grants?

    A rural area for part 1780 is any area not in a city or town with more than 10,000 inhabitants, using the most recent decennial census, with certain statutory exclusions. Facilities may be located in non-rural areas, but funds can pay only for the portion that serves rural areas. Guaranteed WWD loans under part 5001 use that rule's rural definition, which is built around cities and towns of more than 50,000 and their contiguous urbanized areas.

    How does USDA decide how much grant a water or sewer project gets?

    In a fixed order. The service area's median household income is compared with the statewide nonmetropolitan median. That sets the grant ceiling (75% or 45%) and the debt service threshold (0.5% or 1.0% of median household income per EDU). A grant is considered when debt service per EDU would exceed the threshold, and it is cut back if it would push the annual cost per EDU below the cost of similar systems. No grant is available where median household income exceeds 100% of the statewide nonmetropolitan median.

    What interest rate will a WWD direct loan carry?

    One of three tiers set each quarter and rounded to the nearest one-eighth of 1%. The poverty rate is 60% of the market rate, capped at 5%, for health or sanitary projects in areas with income below the higher of the poverty line or 80% of the state nonmetropolitan median. The intermediate rate is 80% of market, capped at 7%, for areas up to 100% of that median. Everyone else pays the market rate, which follows the Bond Buyer Index. The borrower gets the lower of the rate at approval or at closing.

    How long can a WWD loan run?

    Up to the useful life of the facility, the term allowed by state statute, or 40 years from the date of the note or bond, whichever is shortest. When grant funds are part of the package, the loan is normally set at the maximum permitted term. Principal can be deferred for up to 36 months after the first interest installment, but not to postpone taxes or full user rates.

    What reserves must a WWD borrower build?

    Borrowers that pledge facility revenues must build a debt reserve of at least one average annual loan installment, accumulating at one-tenth of an installment each year unless state law prohibits it, plus reserves for emergency maintenance, extensions and replacement of short-lived assets. General obligation or special assessment bonds that provide for annual tax or assessment collection ordinarily satisfy the reserve requirement. The operating budget and rate design must include these reserves.

    How much does a WWD feasibility study cost?

    This site quotes every engagement at a firm fixed fee in a written proposal. Its WWD article estimates $8,500 to $18,500 or more for a separate feasibility study on a substantial WWD application and $5,000 to $15,000 or more for rate analysis that is not bundled with the PER. Engineering and environmental work are priced by those firms. Under part 1780, fiscal advisory, engineering and planning fees are eligible project costs, but costs incurred before approval are paid only with written Agency approval.

    How long does the WWD process take?

    The rule sets some clocks: the processing office reports missing items within 15 federal working days and advises on eligibility and funding within 45 days of a completed application, and public notice must run within 60 days of filing. The longer path runs through environmental review, funding cycles, bids and closing. This site's feasibility engagements typically take 4 to 8 weeks, with a 3 to 4 week rush option.

    Can a WWD feasibility consultant be paid from the loan or grant?

    Yes, when the work is a necessary part of the project. Part 1780 lists reasonable legal, engineering, administrative, fiscal advisory, environmental and planning fees as eligible loan or grant costs. Every contract with a professional or technical representative must be in writing and is subject to Rural Development concurrence, and fees are reasonable when they are not above what the profession charges for similar work without USDA financing.

    What changes if the project relies on a single business customer?

    The rule then requires an assessment of that business. Part 1780 says that if the primary use of the facility is by a business and the facility's success depends on it, the business's economic viability must be assessed; part 5001 says the same for guaranteed WWD loans. The cost of pretreatment or other items a business would normally provide is not eligible for WWD funds. An independent study of the business is the cleanest way to meet the test.

    What do WWD guaranteed loans cost in fiscal year 2026?

    USDA's fiscal year 2026 notice set the WWD guarantee at 90%, the one-time guarantee fee at 1.0% of the guaranteed amount, no periodic retention fee, and a 0.50% fee if the loan note guarantee is issued before construction is complete. On a $10 million loan that is a $90,000 fee. Part 5001 caps WWD guaranteed debt at $50 million per borrower and requires the lender to certify it would not make the loan without the guarantee.

    Sources

    [1] 7 CFR part 1780, Water and Waste Loans and Grants (CFR 2026 edition, title 7 vol. 12, revised 1 Jan 2026), govinfo; sections 1780.1, 1780.3, 1780.7, 1780.9 to 1780.14, 1780.17, 1780.19, 1780.31 to 1780.47, 1780.53 to 1780.57. https://www.govinfo.gov/content/pkg/CFR-2026-title7-vol12/xml/CFR-2026-title7-vol12-part1780.xml (accessed 8 Nov 2026)

    [2] 7 CFR part 5001, OneRD Guaranteed Loans (CFR 2026 edition, title 7 vol. 15, revised 1 Jan 2026), govinfo; sections 5001.3, 5001.104, 5001.117, 5001.121(b), 5001.126(c), 5001.303, 5001.305, 5001.317, 5001.406(b). https://www.govinfo.gov/content/pkg/CFR-2026-title7-vol15/xml/CFR-2026-title7-vol15-part5001.xml (accessed 8 Nov 2026)

    [3] USDA, OneRD Annual Notice of Guarantee Fee Rates, Periodic Retention Fee Rates, Loan Guarantee Percentage and Fee for Issuance of the Loan Note Guarantee Prior to Construction Completion for Fiscal Year 2026, 91 FR 11272 (9 Mar 2026). https://www.govinfo.gov/content/pkg/FR-2026-03-09/html/2026-04581.htm (accessed 6 Nov 2026)

    [4] U.S. Census Bureau, Vintage 2025 subcounty resident population estimates (sub-est2025), incorporated places, April 1 2020 estimates base and July 1 2025 estimates. https://www2.census.gov/programs-surveys/popest/datasets/2020-2025/cities/totals/sub-est2025.csv (file obtained 8 Nov 2026)

    [5] usda-feasibility-study.com, Water & Waste Disposal Program: Feasibility Requirements (site article). https://usda-feasibility-study.com/blog/usda-water-waste-feasibility (read 8 Nov 2026)

    [6] usda-feasibility-study.com, USDA Feasibility Study Cost & Timeline (site page). https://usda-feasibility-study.com/usda-feasibility-study-cost (read 8 Nov 2026)

    [7] usda-feasibility-study.com, Contact & Request a Proposal (site page). https://usda-feasibility-study.com/contact (read 8 Nov 2026)

    Ready to Start Your USDA Project?

    Get your free consultation today and take the first step toward securing USDA funding for your rural development project.

    Our USDA feasibility study consultants scope every engagement against the five Part 5001 components in a free consultation.

    Get Your Free Consultation

    Fill out the form below and we'll contact you within 24 hours to discuss your project.

    We'll respond within 24 hours