Short answer
A USDA Water and Waste Disposal (WWD) application is judged on two documents that answer different questions. The preliminary engineering report (PER) answers whether the proposed water, sewer, solid waste or storm water facility is the right one and what it will cost. The feasibility and financial work answers whether the people who will use it can pay for it: how many users will connect, what the system will cost to run, what rate each household will pay, and how much of the project a grant must carry so that the rate stays reasonable. Rural Development decides the loan, the grant and the interest rate from that second set of numbers [1].
The direct loan and grant program is governed by 7 CFR part 1780. It serves public bodies, nonprofit associations and tribes in rural areas, defined as places not in a city or town of more than 10,000 people [1]. Guaranteed WWD loans made by commercial lenders sit in the OneRD rule at 7 CFR part 5001, carry a 90% guarantee and a 1.0% fee in fiscal year 2026, and are capped at $50 million per borrower [2][3].
Data current as of November 2026.
| Question | Answer from the rules |
|---|---|
| Which rule governs? | 7 CFR part 1780 for direct loans and grants; 7 CFR part 5001 for guaranteed loans [1][2] |
| Who can apply? | Public bodies, community-controlled nonprofits and federally recognized tribes [1] |
| Rural test, direct and grant | Not in a city or town over 10,000 people, from the latest decennial census [1] |
| What the engineer must deliver | A PER that conforms to customary professional standards, prepared by an engineer licensed in the state [1] |
| What the financial work must prove | Revenues cover operation and maintenance, reasonable reserves and debt payment [1] |
| Longest loan term | Useful life, state statute or 40 years, whichever is less [1] |
| Largest grant | 75% or 45% of eligible project cost, depending on median household income [1] |
| FY2026 guaranteed terms | 90% guarantee, 1.0% guarantee fee, no annual retention fee, 0.50% fee for a guarantee issued before construction is complete [3] |
The site's WWD article explains the program in general terms; read it first if the program is new to you: Water and Waste Disposal Program: Feasibility Requirements. This page is for a utility, district or nonprofit that is ready to assemble an application and needs to know exactly what the feasibility side must contain, how the grant is sized and who should prepare each piece.
Who prepares what in a WWD application
Part 1780 places the work on the owner. Applicants are responsible for "providing the services necessary to plan projects including design of facilities, environmental review and documentation requirements, preparation of cost and income estimates, development of proposals for organization and financing, and overall operation and maintenance of the facility" [1]. Those are three different professional jobs, and the rule treats them differently.
| Document or task | Rule | Who prepares it | What the Agency checks |
|---|---|---|---|
| Preliminary engineering report (two copies with the initial application) | 1780.33(c), 1780.55 | The owner's engineer, licensed in the state where the facility is built (1780.54) | Conformity with customary professional standards; State staff engineer review |
| Environmental report | 1780.33(f), 1780.55 | Environmental professionals under 7 CFR part 1970 | State Environmental Coordinator review; no action limiting alternatives before review ends (1780.57(a)) |
| Operating budget (Form RD 442-7) | 1780.33(h)(1), 1780.41(a)(2) | Applicant, usually with its accountant, fiscal advisor or feasibility consultant | Revenue covers O&M, reserves and debt service (1780.7(f)) |
| User estimates and rate schedule | 1780.39(c), 1780.35(c) | Applicant and its financial advisor or feasibility consultant | Realistic users, signed user agreements, cash contributions |
| Grant determination | 1780.35(b) | Processing office, from the applicant's numbers | Debt service share of median household income; similar system cost |
| Business viability assessment | 1780.7(f); 5001.305(c) for guaranteed loans | Applicant or lender, best documented by an independent business study, when a business is the main user | Whether the business the system depends on can pay |
| Credit elsewhere certification | 1780.7(d), 1780.33(d) | Applicant | Inability to finance at reasonable rates and terms |
| Bond transcript and notes | 1780.39(b)(3), subpart D | Recognized bond counsel, for public bodies | Evidence of indebtedness |
Two consequences follow. First, a general business consultant should not write the PER; the engineer of record does. The site's own WWD article says the same: engineering firms lead WWD project teams and feasibility consultants support the analytical components [5]. Second, the financial case is not a formality. The user count, operating budget, reserve schedule and rate design decide the loan amount, the grant amount and, through the median household income tests, the interest rate. If those numbers are weak, a sound engineering design can still produce a rate that the Agency will not accept.
Eligibility under 7 CFR part 1780
Eligibility has six parts, and an application fails if any one is missing.
| Test | What the rule says | Evidence the application needs |
|---|---|---|
| Applicant type | Public body; nonprofit association, cooperative or corporation controlled by local public bodies or broadly owned by local people; federally recognized tribe (1780.7(a)) | Organizational documents, membership records |
| Rural area | Not in a city or town over 10,000 inhabitants per the most recent decennial census (1780.3) | Census population of the place served |
| Rural share of the facility | Facilities may sit in non-rural areas, but funds pay only for the portion serving rural areas (1780.7(b)) | Cost allocation between rural and non-rural users |
| Project need and design | Will not decline below design population; adequate capacity for present and reasonably foreseeable growth; consistent with a current development plan (1780.7(c)) | Population trend, growth assumptions, plan consistency |
| Credit elsewhere | Applicant cannot finance from its own resources or commercial credit at reasonable rates and terms (1780.7(d)) | Written certification; lender responses where available |
| Legal authority | Authority to own, build, operate, borrow, pledge security and repay (1780.7(e)) | Statutes, charter, ordinances, attorney opinion |
| Economic feasibility | Taxes, assessments, income or fees sufficient for operation and maintenance, reasonable reserves and debt payment (1780.7(f)) | Operating budget, user estimates, rate schedule |
| Capability | Financial, technical and managerial capability to comply with federal and state requirements; alternatives of ownership, design and shared services considered (1780.1(j)) | Staffing, operator certification, audits, alternatives analysis |
The guaranteed program uses different eligibility language. A WWD guaranteed borrower must be a public body, tribe or nonprofit; it must certify that it cannot obtain credit elsewhere without the guarantee; and it must show significant community support through a certification from each affected local government [2]. The project must be in a rural area as defined in 5001.3, which for part 5001 means outside a city or town of more than 50,000 people and its contiguous urbanized area, and projects serving both rural and non-rural users are guaranteed only for the rural portion [2].
Eligible purposes and limits
Loan and grant funds may build, enlarge, extend or improve rural water, sanitary sewage, solid waste and storm wastewater facilities, plus the public and private relocations and connection charges needed for those facilities to work [1]. Some costs can be paid only with loan money, and some are barred altogether.
| Category | Loan or grant | Loan only | Not eligible |
|---|---|---|---|
| Construction and improvement | Facilities, relocations, connection charges under service contracts (1780.9(a) to (d)) | Facilities not modest in size, design and cost (1780.10(a)(1)) | |
| Professional fees | Legal, engineering, administrative, fiscal advisory, recording, environmental analyses, planning (1780.9(e)(1)(i)) | Loan or grant finder's fees (1780.10(a)(2)) | |
| Land and rights | Land, water rights, leases, permits, rights-of-way (1780.9(e)(1)(ii)) | ||
| Financing and start-up | Construction-period interest; initial operating expenses for ordinarily up to one year; purchase of existing facilities; limited refinancing (1780.9(e)(2)) | ||
| Business users | Costs normally borne by a business or industrial user, such as wastewater pretreatment (1780.10(a)(5)) | ||
| Sewer design | New combined storm and sanitary sewers (1780.10(a)(3)) | ||
| Broadband | Up to 10% of the amount provided, for related broadband infrastructure (1780.9(h)) |
Costs incurred before approval can be paid only if the applicant asks in writing and the Agency finds compelling reasons, with no commitment to make the loan or grant (1780.9(f)) [1]. That matters for planning budgets: fiscal advisory and feasibility fees are eligible project costs, but a utility that pays them before approval carries the risk.
Loan and grant terms you can confirm
The rule fixes the structure of WWD pricing; the quarterly rates themselves are set by the Agency.
| Term | Rule | Section |
|---|---|---|
| Rate setting | Set each quarter, rounded to the nearest one-eighth of 1%; the lower of the rate at approval or closing unless the applicant chooses otherwise | 1780.13(a) |
| Poverty rate | 60% of the market rate, not over 5%; requires a project to meet health or sanitary standards and service-area median household income below the higher of the poverty line or 80% of the statewide nonmetropolitan median household income | 1780.13(b) |
| Intermediate rate | 80% of the market rate, not over 7%; service-area median household income not more than 100% of the statewide nonmetropolitan median | 1780.13(c) |
| Market rate | Guided by the average Bond Buyer Index for the four weeks before the first Friday of the last month before the quarter | 1780.13(d) |
| Term | Useful life, state statute or 40 years from the note or bond date, whichever is less; maximum term when grant funds are used | 1780.13(e) |
| Principal deferral | Up to 36 months after the first interest installment, longer only with Agency authorization | 1780.13(e)(1) |
| Maximum grant | 75% of eligible project costs where income is below the higher of the poverty line or 80% of the statewide nonmetropolitan median and the project fixes a health or sanitary problem; 45% where income is above that level but not over 100% | 1780.10(c) |
| Grant bars | No grant to reduce user cost below similar system cost, where income exceeds 100% of the statewide nonmetropolitan median, or where the other loan is not at reasonable rates and terms | 1780.10(b) |
| Reserves | Debt reserve of at least one average annual installment, built at one-tenth of an installment per year, unless state law prohibits; reserves for short-lived asset replacement | 1780.39(e), 1780.35(c) |
| Interim financing | For loans over $500,000, commercial interim construction financing where available at reasonable rates | 1780.39(d) |
| Security | General obligation, taxes or assessments, or facility revenues for public bodies; assignment of income and liens for other borrowers | 1780.14 |
The guaranteed program has its own terms. For fiscal year 2026, USDA set the WWD guarantee at 90%, the guarantee fee at 1.0%, no periodic retention fee, and a 0.50% fee when the loan note guarantee is issued before construction is complete [3]. A $10,000,000 guaranteed WWD loan would therefore carry a $9,000,000 guaranteed portion and a one-time fee of $90,000. Part 5001 limits WWD guaranteed loans to $50 million per borrower, including existing WWD guaranteed debt, and requires the lender to certify that it would not make the loan without the guarantee [2].
What the PER must contain
Part 1780 does not print a PER outline. It says PERs "must conform to customary professional standards" and that PER guidelines for water, sanitary sewer, solid waste and storm sewer "are available from the Agency" [1]. Those guidelines are published on the Rural Development website, which this page does not cite; your engineer and the State staff engineer will work from the current version. What the regulation itself requires of the design is specific, and every item below needs a place in the PER.
| Design requirement | Section | What the PER should show |
|---|---|---|
| Environmental impact analysis built into planning and design | 1780.57(a), 1780.31(e) | Alternatives considered before any action that narrows them; mitigation in the design |
| Safe Drinking Water Act progress for water systems | 1780.57(g) | How the project moves the system toward compliance |
| Federal and state effluent standards for discharge or waste systems | 1780.57(h) | Effluent conformity |
| Water loss for existing systems | 1780.57(f) | Evidence that distribution losses do not exceed reasonable levels |
| Metering | 1780.57(m) | A meter on each water connection, or a justified exception |
| Fire protection and growth capacity | 1780.57(d), (e) | Capacity sized for reasonable fire protection and growth |
| Most economical service practicable | 1780.57(n), 1780.10(a)(1) | Least-cost alternative; facilities modest in size, design and cost |
| Combined sewers | 1780.57(i) | No new combined systems; extensions only where separation is impractical |
| Dam safety, seismic safety, pipe standards, leakage testing | 1780.57(j), (o), (k), (l) | Compliance with the cited federal guidelines and ASTM or AWWA standards |
For a guaranteed WWD loan, part 5001 sets a floor: engineering documentation at the level of detail a lender would require for a standard commercial loan, including at minimum a project description, a cost estimate, the number of residential and non-residential connections and the population served [2]. The Agency states that it does not provide technical oversight or recommendations on technical feasibility for guaranteed projects; the lender must ensure that the design follows accepted practice, meets federal requirements including American Iron and Steel, and will be completed within available funds [2].
The point where engineering and feasibility meet is the user count. The PER's design population and connection count must be the same numbers the operating budget uses. A PER sized for 600 connections paired with a rate study built on 450 paying users is the kind of mismatch a reviewer stops on.
What the feasibility and financial work must contain
Part 1780 does not use the phrase "feasibility study" for direct loans the way part 5001 does for business loans. It uses tests: economic feasibility, realistic users, reasonable user charges, reserves and capability [1]. A lender-grade WWD feasibility package is the document that passes those tests with evidence.
| Component | Rule | What it must prove |
|---|---|---|
| Realistic users | 1780.39(c)(1) | Rates set on a realistic number of users, not the maximum the system could serve |
| Signed users | 1780.39(c)(3) | Enforceable user agreements with a penalty clause for new users, unless use is mandatory or users already receive service |
| User cash contributions | 1780.39(c)(2) | Contributions near one year's minimum user fee, paid before closing or construction, unless waived |
| Vacant lots | 1780.39(c)(4) | Vacant property counted only with development plans, a written payment agreement and a bond or escrow |
| Connection program | 1780.39(c)(5) | A plan to get every signed user connected as soon as service is available |
| Operating budget | 1780.33(h)(1) | Operation, maintenance, debt service and reserves on Form RD 442-7 |
| Reserves | 1780.39(e), 1780.35(c) | Debt reserve schedule and short-lived asset replacement without building a substantial surplus |
| Rate design | 1780.35(c) | User charges that are reasonable and cover all costs after completion |
| Grant need | 1780.35(b) | Debt service share of median household income; similar system cost comparison |
| Business dependence | 1780.7(f) | Viability of any business that is the primary user and on which the system depends |
| Population durability | 1780.7(c)(1) | The served area is not likely to fall below the design population |
| Service-area equity | 1780.11(b) | Unjustified differences in service within the area are remedied |
| Management capability | 1780.1(j), 1780.47 | Staff, operator capacity, accrual-basis statements and audits |
For guaranteed loans, part 5001 adds a parallel test: projected taxes, assessments, revenues or fees must cover operation and maintenance, any reserves the lender requires and debt payment, and the lender's credit analysis must account for any interest rate adjustment under the guarantee [2]. Where the majority user is a business and the system depends on it, the business's economic viability must be assessed [2]. That is the situation in which an independent business feasibility study is most clearly needed on a WWD file: a sewer extension built for a food processor, a water line serving a single industrial park tenant, or a solid waste facility whose tonnage comes from one hauler.
Priority points: how WWD applications are ranked
When funds are limited, the Agency ranks eligible direct loan and grant applications by points [1]. The feasibility package is where most of these points are documented.
| Priority (direct loans and grants) | Points | Section |
|---|---|---|
| Serves a rural area of 1,000 people or fewer | 25 | 1780.17(a)(1) |
| Serves 1,001 to 2,500 | 15 | 1780.17(a)(2) |
| Serves 2,501 to 5,500 | 5 | 1780.17(a)(3) |
| Emergency, water supply deterioration or Safe Drinking Water Act requirement | 25 | 1780.17(b)(1) |
| Corrects wastewater inadequacies or health standards | 25 | 1780.17(b)(2) |
| Solid waste administrative orders | 15 | 1780.17(b)(3) |
| Median household income below the poverty line, where that line is below 80% of the statewide nonmetropolitan median | 30 | 1780.17(c)(1) |
| Median household income below 80% of the statewide nonmetropolitan median | 20 | 1780.17(c)(2) |
| At or above the poverty line and between 80% and 100% | 15 | 1780.17(c)(3) |
| Merges smaller facilities | 15 | 1780.17(d)(1) |
| Extends service to additional rural areas | 10 | 1780.17(d)(2) |
| Public body or tribe | 5 | 1780.17(d)(3) |
| Other than RUS funds: 50% or more / 20% to 49% / 5% to 19% | 15 / 10 / 5 | 1780.17(d)(4) |
| Agency identified target areas | 10 | 1780.17(d)(5) |
| Primarily recycles solid waste | 5 | 1780.17(d)(6) |
| Unreliable drinking water quality or supply | 10 | 1780.17(d)(7) |
| State program official points, with written justification | up to 15 | 1780.17(e) |
| National Office points | up to 15 | 1780.17(g) |
Guaranteed WWD applications are scored on a separate 150-point scale [2].
| Priority (guaranteed loans) | Points | Section |
|---|---|---|
| Primarily serves a rural area under 10,000 people | 20 | 5001.317(a) |
| Health priorities (same three categories as direct) | 25 / 25 / 15 | 5001.317(b) |
| Long-term population decline over the last three censuses | 5 | 5001.317(c)(1) |
| Rural county with 20% or more in poverty for 30 years | 5 | 5001.317(c)(2) |
| Unemployment at 125% or more of the state rate | 5 | 5001.317(c)(3) |
| Merges facilities / extends to additional rural areas | 10 / 10 | 5001.317(d)(1), (2) |
| Public body or tribe | 5 | 5001.317(d)(3) |
| Non-Rural Development funds: 50% or more / 20% to 49% / 5% to 19% | 15 / 10 / 5 | 5001.317(d)(4) |
| Target areas / solid waste recycling / unreliable drinking water | 5 / 5 / 10 | 5001.317(d)(5) to (7) |
| Approval official and Administrator points | up to 15 each | 5001.317(e), (f) |
Two of these lines reward financial structure rather than need. The share of non-USDA money in the project moves an application by up to 15 points under either scale, which is why the funding plan, including any state revolving fund, community development block grant or local contribution, belongs in the feasibility package with commitment letters rather than as a hope.
Grant determination and affordability: the tests in order
Rural Development does not set the grant by negotiation. Part 1780 sets a sequence [1]:
- Compare the service area's median household income with the statewide nonmetropolitan median household income. Both come from five-year American Community Survey data unless the applicant documents that the data misrepresent the area and supplies a reliable survey (1780.1(b)).
- That ratio sets the maximum grant share (75% or 45%), the interest rate tier and the income priority points.
- The applicant is considered for a grant when the debt service portion of the average annual cost per equivalent dwelling unit (EDU) exceeds 0.5% of median household income (income at or below 80% of the statewide nonmetropolitan median) or 1.0% (income above that, up to 100%) (1780.35(b)(2)).
- If that grant would bring the annual EDU cost below the cost of similar systems in comparable communities, the grant is reduced so that it does not (1780.35(b)(3)).
- The loan carries the rest, at the maximum term (1780.13(e)).
| Service-area income vs statewide nonmetropolitan median | Interest rate tier | Maximum grant | Debt service threshold for grant consideration | Income priority points |
|---|---|---|---|---|
| Below the poverty line (where the line is below 80% of the median), health or sanitary project | Poverty (60% of market, max 5%) | 75% | 0.5% of income | 30 |
| Below 80%, health or sanitary project | Poverty (60% of market, max 5%) | 75% | 0.5% of income | 20 |
| Below 80%, other project | Intermediate (80% of market, max 7%) | 45% | 0.5% of income | 20 |
| 80% to 100% | Intermediate (80% of market, max 7%) | 45% | 1.0% of income | 15 |
| Above 100% | Market | No grant | Not applicable | 0 |
Read the poverty-rate and 75% grant rows together with the project purpose: both depend on the project meeting health or sanitary standards [1]. An extension for growth in a low-income area gets the intermediate rate and a 45% ceiling.
Worked example: user-rate affordability (illustrative)
The numbers below are illustrative. They follow the 1780 tests in order with stated assumptions; they are not a quote of current rates, which Rural Development publishes each quarter.
Inputs
| Input | Value | Basis |
|---|---|---|
| Project | Wastewater treatment upgrade required to meet health standards | Qualifies for the poverty rate and 75% grant ceiling if income test is met |
| Eligible project cost | $7,500,000 | Assumed |
| Realistic paying users | 450 EDUs (420 residential, 30 commercial EDUs) | 1780.39(c)(1): realistic, not maximum |
| Service-area median household income | $46,000 | Assumed ACS five-year figure |
| Statewide nonmetropolitan median household income | $60,000 | Assumed; 80% is $48,000 |
| Income ratio | 76.7% | Below 80%, so 0.5% debt service threshold |
| Illustrative market rate | 4.125% | Assumed for the example |
| Poverty rate | 2.5% (60% of 4.125% = 2.475%, rounded to the nearest one-eighth) | 1780.13(a), (b) |
| Term | 40 years, annual payments | 1780.13(e) |
| Operation and maintenance per EDU | $420 per year | Assumed operating budget |
| Short-lived asset reserve per EDU | $45 per year | Assumed |
Results
| Step | Calculation | Result |
|---|---|---|
| Debt service threshold per EDU | 0.5% x $46,000 | $230 per year |
| Debt service the users can carry at the threshold | 450 x $230 | $103,500 per year |
| Annual payment factor, 2.5% for 40 years | 0.039836 | |
| Supportable loan | $103,500 / 0.039836 | about $2,598,000 |
| Grant | $7,500,000 - $2,598,000 | $4,902,000 (65.4%, under the 75% ceiling) |
| Debt reserve build | One-tenth of the annual installment | about $10,350 per year, $23 per EDU |
| Annual cost per EDU | $230 debt service + $420 O&M + $23 debt reserve + $45 short-lived asset reserve | $718 per year |
| Monthly bill per EDU | $718 / 12 | $59.83 |
| Bill as share of median household income | $718 / $46,000 | 1.56% |
Sensitivity: what moves the grant and the bill
| Scenario | Effect | Annual cost per EDU | Monthly |
|---|---|---|---|
| Base case above | Loan about $2.60 million, grant $4.90 million | $718 | $59.83 |
| Only 400 users connect; loan unchanged | Debt service rises to about $259 per EDU (0.56% of income) | $750 | $62.47 |
| Similar systems cost $760 per year | Grant reduced so the EDU cost is not below $760; loan rises to about $3.03 million, grant falls to about $4.47 million (59.6%) | $760 | $63.33 |
| No grant, poverty rate, full $7.5 million loan | Debt service about $664 per EDU | $1,195 | $99.61 |
| No grant, at the 4.125% illustrative market rate | Debt service about $858 per EDU | $1,409 | $117.38 |
| Income at 90% of the state median ($54,000), intermediate rate 3.25% | Threshold 1.0% = $540 per EDU; loan about $5.40 million; grant about $2.10 million (28.0%, under the 45% ceiling) | $1,059 | $88.25 |
Three lessons come out of the arithmetic. The user count drives everything: every user that does not connect raises the bill for everyone else, which is why the rule requires signed user agreements, cash contributions and a connection program [1]. The similar system cost test can take grant away from a community that has kept rates low for years, so the comparison set of systems must be chosen and documented with care. And income data decides the tier: a service area at 79% of the state median and one at 81% face different thresholds, rates and grant ceilings, so where five-year ACS figures look wrong for a small area, the rule allows a reliable income survey (1780.1(b)) [1].
The market: how many places the 10,000 test reaches
The direct program's population line is low, but most American municipalities fall under it. In the Census Bureau's Vintage 2025 incorporated place estimates, 16,331 of 19,483 incorporated places (83.8%) had an April 2020 estimates base of 10,000 or fewer people, together home to about 28.2 million residents [4].
| Incorporated places by April 2020 population base | Places | Share of places | Population | Share of incorporated-place population |
|---|---|---|---|---|
| 1,000 or fewer (25 priority points) | 9,282 | 47.6% | 3,614,062 | 1.7% |
| 1,001 to 2,500 (15 points) | 3,362 | 17.3% | 5,485,315 | 2.6% |
| 2,501 to 5,500 (5 points) | 2,289 | 11.7% | 8,628,906 | 4.1% |
| 5,501 to 10,000 (eligible, no population points) | 1,398 | 7.2% | 10,447,321 | 5.0% |
| 10,001 to 50,000 (outside the direct rural test) | 2,354 | 12.1% | 51,592,735 | 24.6% |
| Over 50,000 | 798 | 4.1% | 129,986,120 | 62.0% |
| Total | 19,483 | 100% | 209,754,459 | 100% |
Source: U.S. Census Bureau, Vintage 2025 subcounty population estimates, incorporated places (summary level 162), ESTIMATESBASE2020 [4]. Townships and unincorporated areas are not places in this file and are also rural under the 10,000 test. The rule uses the decennial census count, which the estimates base approximates.
The same file shows why the "will not decline below design population" test in 1780.7(c)(1) deserves real analysis. Between the April 2020 base and July 2025, 8,407 of those 16,331 small places (51.5%) lost population in the Census estimates [4].
| Population band (April 2020 base) | Places | Places that lost population by 2025 | Share losing | Band population change 2020 to 2025 |
|---|---|---|---|---|
| 1,000 or fewer | 9,282 | 5,064 | 54.6% | +1.1% |
| 1,001 to 2,500 | 3,362 | 1,731 | 51.5% | +2.2% |
| 2,501 to 5,500 | 2,289 | 1,019 | 44.5% | +3.6% |
| 5,501 to 10,000 | 1,398 | 593 | 42.4% | +4.1% |
The smallest places are where priority points are highest and where population loss is most common. A WWD feasibility package for a town of 800 should therefore show the town's own trend, the user count it implies over the loan term, and a rate case at a lower user count.
| State | Incorporated places of 10,000 or fewer | Share of the state's incorporated places |
|---|---|---|
| Illinois | 1,072 | 82.8% |
| Texas | 988 | 80.7% |
| Pennsylvania | 943 | 93.0% |
| Iowa | 897 | 95.5% |
| Missouri | 856 | 91.5% |
| Minnesota | 754 | 88.1% |
| Ohio | 747 | 80.8% |
| Kansas | 590 | 94.4% |
| Oklahoma | 547 | 92.6% |
| Nebraska | 512 | 97.0% |
Source: as above [4]. Counts are places, not water or sewer systems; many small places are served by rural water districts that cross place lines.
Process and timeline
The rule sets several clocks. The rest of the timeline depends on engineering, environmental review, funding cycles and bids.
| Stage | What happens | Rule or timeframe |
|---|---|---|
| Early contact | Processing office explains eligibility; can point to technical assistance on income surveys and rate schedules | 1780.31(a), (b) |
| Eligibility determination (optional) | Written request instead of a full SF 424.2; does not give funding priority | 1780.31(c) |
| PER preliminary review (optional) | PER may be submitted before the rest of the application | 1780.33(c)(1) |
| Initial application | SF 424.2, intergovernmental review, two PER copies, credit elsewhere certification, eligibility documents, environmental report | 1780.33 |
| Completeness check | Applicant told within 15 federal working days what is missing | 1780.32(a) |
| Eligibility and funding advice | Within 45 days of a completed application | 1780.32(b) |
| Public notice of intent | Newspaper notice within 60 days of filing | 1780.19(a) |
| Public information meeting | Before approval, with notice at least 10 days ahead, unless a vote or referendum authorizes the debt | 1780.19(b) |
| Selection for further processing | Highest priority scores first, subject to funds | 1780.36 |
| Processing conference and full application | Operating budget, user agreements, professional service contracts, insurance | 1780.39 |
| Letter of conditions and obligation | Issued only when funds are available; obligation on Form RD 1940-1 sets the approval-date rate | 1780.39(i), 1780.41 |
| Before closing or construction | Insurance, verification of users and contributions, applicant funds deposited, other funds committed, title and rights-of-way | 1780.44 |
| Construction | Interim financing for loans over $500,000 where available; multiple advances only for loans over $100,000 | 1780.39(d), 1780.45(b) |
The feasibility and financial work belongs early, ideally alongside the PER and before the initial application, because the user count, budget and income evidence decide the score, the rate tier and the grant. The site's general engagement schedule runs 4 to 8 weeks from signed engagement letter to final report, with a 3 to 4 week rush option [6].
Common reasons WWD files stall
- The rate study uses the maximum possible users rather than a realistic count (1780.39(c)(1)).
- New users have not signed enforceable user agreements or paid contributions (1780.39(c)(2), (3)).
- Vacant lots are counted as paying users without bonds or escrow (1780.39(c)(4)).
- The PER and the operating budget use different connection counts or design populations.
- The operating budget omits the debt reserve or short-lived asset replacement (1780.39(e)).
- Service area boundaries leave out users in a way that raises a nondiscrimination or inequity question (1780.35(a), 1780.11(b)).
- The project depends on one business, and nobody has assessed that business (1780.7(f)).
- Project costs include items a business user should pay, such as pretreatment (1780.10(a)(5)).
- Work started or land was committed before environmental review ended, limiting alternatives (1780.57(a)).
- Engineering was not procured on qualifications, or professional service contracts were not sent for Agency concurrence (1780.39(b)).
- Median household income data are disputed late, after the grant has been calculated (1780.1(b)).
Hiring a WWD feasibility study and PER consultant
Start with the engineer. Part 1780 requires the owner to announce engineering and architectural service needs publicly and to negotiate those contracts on demonstrated competence and qualifications at a fair and reasonable price; state procurement law can be used if the State Director finds it meets the same intent (1780.39(b)(1)) [1]. The engineer must be licensed in the state where the facility will be built (1780.54) [1].
Then decide who prepares the financial case. Part 1780 lists accountants, auditors, appraisers, environmental professionals and financial advisors among the professional services a project may need, and requires that every contract between the applicant and its professional and technical representatives be in writing and be subject to Rural Development concurrence (1780.39(b)) [1]. Fees count as reasonable when they do not exceed what the profession charges for similar work without USDA financing [1]. That concurrence requirement is a useful screen: a feasibility consultant whose scope and fee you cannot show to the processing office is the wrong one.
This site does not prepare PERs and does not lead WWD engineering; it works with the applicant's engineering firm on the feasibility and financial components, as its WWD article states [5]. For a WWD application that means:
- User and demand analysis: realistic user counts, signed-user status, vacant property, growth and decline scenarios.
- Operating budget review and projection consistent with Form RD 442-7, including debt and short-lived asset reserves.
- Rate design and affordability analysis: debt service per EDU against the median household income thresholds, similar system cost comparison, sensitivity cases.
- Grant determination modelling so the governing body sees the likely loan and grant split before it adopts rates.
- Business viability assessment where a business is the primary user (1780.7(f), 5001.305(c)).
- Management and capability review for the five feasibility components where a lender or the Agency asks for a full study.
On this site's standard terms, an engagement is quoted at a firm fixed fee in a written proposal, includes a projection with sensitivity analysis, a PDF and Word report with an Excel workbook, a kickoff and a midpoint call and one round of revisions; engineering, environmental assessments, legal work and appraisals are separate [6]. The site's WWD article estimates, for substantial WWD applications, $8,500 to $18,500 or more for a separate feasibility study and $5,000 to $15,000 or more for rate analysis when it is not bundled with the PER, alongside engineering and environmental costs that the engineer and environmental consultants quote [5].
What you provide: the PER or its draft and the engineer's cost estimate; the current rate ordinance and three years of audits or financial statements; the customer list by class and the signed user agreements; existing debt instruments; any income survey; and letters for other funding sources. A senior analyst responds to each inquiry within one business day with a scoped proposal or follow-up questions [7].
Request a scoped proposal for the feasibility and rate work on your WWD application at the contact page.
Related pages
- Water and Waste Disposal Program: Feasibility Requirements, the program explainer.
- USDA Community Facilities feasibility study, for nonprofit utility and public facility projects that fall under Community Facilities.
- USDA feasibility study requirements under 7 CFR part 5001, for the guaranteed side.
- USDA rural definition, on the population thresholds that differ across programs.
- The USDA Feasibility Study Framework.
- USDA feasibility study cost and timeline.