How to read this case study. The engagement summary reflects the published record. Client names, actual costs, loan terms and proprietary data are confidential, so the project budget, market sizing and financial projections below are a modeled example built from public data for this project type and location. They show the analysis a lender-grade study performs, not the client's figures.
In 2023 a regional bank needed a financial feasibility study for a charter school addition in Hutchinson, Kansas, financed with a USDA Community Facilities (CF) guaranteed loan in the $5 million to $25 million tier. The study was prepared with enrollment and revenue analysis. This page works through the questions such a study answers, using a modeled 28,000 square foot addition that takes an existing K-8 charter school from 360 to 540 seats, and public data for Reno County.
A school's costs are mostly teachers and buildings, and its revenue is students times a per-pupil amount set by the state. The model shows that the addition can carry its debt if enrollment grows as planned and per-pupil funding holds, and it shows exactly how much room there is when either does not. Data current as of November 2026.
Engagement summary
| Published record | Detail |
|---|---|
| Program | USDA Community Facilities guaranteed loan |
| Asset | Charter school addition |
| Location | Hutchinson, Kansas (Reno County, Great Plains region) |
| Loan size tier | $5 million to $25 million |
| Year | 2023 |
| Lender | Regional bank |
| Outcome | Prepared with enrollment and revenue analysis |
Source: this site's engagement index [15]. The scope, budget, enrollment, revenue, staffing and projections below are a model.
The engagement card on the index carried a longer summary. This page keeps what the regulations and data on file support and marks the rest.
| Statement in the engagement card | Status on this page |
|---|---|
| CF guaranteed loans: up to $100 million, 1.25% initial fee, terms up to 40 years | Kept; Part 5001 and the FY2026 notice [1][5]. The card's "FY2025 guarantee 80%" is shown here as the FY2026 80% |
| CF guaranteed "explicitly lists educational services, including private schools, as eligible under 7 CFR 1942.17(d)" | Corrected. Section 1942.17 governs CF direct loans; for CF guaranteed loans, educational facilities are eligible under 5001.103(a)(3), and a nonprofit or charter school with significant community ties is an eligible borrower [1] |
| "CF Financial Feasibility Study with Review Report standard" | Corrected. Part 5001 names a financial feasibility analysis, a financial feasibility study with a CPA examination opinion, and an independent feasibility study for a new entity or activity; it has no "review report" tier (5001.304) [1][2] |
| Kansas school finance runs through the Kansas School Equity and Enhancement Act; base aid of $5,615 per student in 2025-26, up from $5,088 in 2023-24; weights for at-risk, career and technical education and transportation; charter funding flows through the sponsoring district | Kept as the card's statements; Kansas statutes and budget documents were not read for this page. The model's per-pupil revenue is its own assumption |
| Kansas per-pupil spending of $12,697; 497,753 students in 1,305 schools and 287 districts (2022) | Kept as the card's figures; not checked |
| A 2024 legislative task force reviewing the formula through 2027, and the end of court jurisdiction in the school finance adequacy case in February 2024 | Kept as the card's statements; not checked |
| No certificate of need for school construction in Kansas; intergovernmental consultation under 2 CFR part 415 completed | Kept as the card's statements; not checked |
| Deliverables: enrollment-driven revenue analysis, cost per student, enrollment absorption against local demographics, five-year pro forma | Consistent with the published outcome; this page shows each in model form |
What the modeled study finds
- Eligibility: Hutchinson qualifies for a CF guarantee but not for CF direct money or grants, and it competes outside the funds reserved for small places.
- Demand: Reno County's population is flat and its births are steady at 620 to 663 a year, so the third section in each grade has to come from the school's waiting list and transfers, not from growth in the number of children.
- Coverage: with enrollment rising from 352 to 518 over five years and per-pupil revenue holding, the school covers the modeled loan 1.19x in the first year and 1.44x by Year 3.
- Sensitivity: a 5% cut in per-pupil revenue or enrollment that stalls at 470 brings coverage close to 1.1 times; the plan has room for one of those, not both.
- Structure: the charter's term has to be matched to the loan, and working capital has to come from the school, because CF guaranteed loan funds cannot pay it.
The question the lender and USDA needed answered
A CF guaranteed loan is made by the bank and guaranteed in part by USDA, so the bank's credit evaluation and the State Office's review look at the same questions: is the borrower eligible, is Hutchinson an eligible rural area, will the school enroll enough students to fill the new seats, will per-pupil funding pay for the teachers those students need, and does the school cover the new debt service, with reserves, through the term of its charter and beyond.
Part 5001 requires a financial feasibility report for every CF guaranteed loan and sets its form by the borrower's situation [1][2]:
| Borrower situation (CF guaranteed, 7 CFR 5001.304) | Report the lender submits |
|---|---|
| Existing facility, loan of $25 million or less | Financial feasibility analysis under appendix B; the lender's credit evaluation can serve |
| Debt backed by general obligation bonds or tax revenue | Financial feasibility analysis |
| Three years of audited statements showing capacity to pay | Financial feasibility analysis |
| All other loans | Financial feasibility study with a CPA examination opinion under AICPA attestation standards |
| Loan over $1,000,000 to a new entity or an entity starting a new activity | Independent feasibility study by a qualified consultant acceptable to the Agency |
An addition to an existing school that adds seats in grades it already teaches is usually an existing facility under the first row. Adding grades the school has never run, such as a high school, would be a new activity and bring the independent study requirement [1]. The published record calls the work a financial feasibility study prepared with enrollment and revenue analysis; whatever the report type, the analysis the bank needed was the same.
Eligibility and program fit
| Test | Rule | Hutchinson result |
|---|---|---|
| CF direct loan population limit | City or town of 20,000 or less (1942.17) [3] | Not eligible: 40,007 residents in the Census Bureau's April 2020 estimates base, 39,595 in July 2025 [8] |
| CF grant | 20,000 or less with an income test (3570.53) [4] | Not eligible on population |
| CF guaranteed rural area | Outside cities over 50,000 and their contiguous urbanized areas (5001.3) [1] | Eligible on population; Reno County is non-metro in the OMB July 2023 delineation [9]; the parcel is confirmed on the USDA eligibility map |
| CF guaranteed funding priority | Funds reserved first for places of 20,000 or less, released on 1 July for places up to 50,000 (5001.103(c), 5001.316(e)) [1] | Outside the reserved pool; timing matters |
| Borrower | Public body, nonprofit with significant community ties, tribe, or a corporation operated on a not-for-profit basis [1] | Modeled as the school's nonprofit governing organization |
| Tax status | Interest on a guaranteed loan cannot be tax-exempt, and a guarantee cannot secure a tax-exempt issue [1] | The study compares the guaranteed loan with any tax-exempt alternative |
| Local support | Certification of support from each affected local government [1] | City, county and sponsoring district letters |
Hutchinson is the clearest example among this site's engagements of a town that falls between the two CF tracks. At about 40,000 people it is twice the CF direct limit and well under the OneRD rural ceiling. A CF guarantee is therefore the USDA route. Its cost is timing: the application competes outside the funds reserved for small places until July, and it misses the 15 priority points for communities under 20,000. It does earn 10 points as a primary or secondary education facility [1].
| CF guaranteed priority factor (7 CFR 5001.316) | Points available | This modeled project | Why |
|---|---|---|---|
| Community of under 20,000 people | 15 | 0 | Hutchinson had 40,007 residents in the Census Bureau's April 2020 base |
| Public safety, health clinic, early education, primary or secondary education facility | 10 | 10 | A K-8 school addition |
| Other funds committed: 5% to 19% / 20% to 49% / 50% or more | 5 / 10 / 15 | 10 | School, campaign and foundation funds are 25.7% of cost |
| Administrator points from a National Office reserve | up to 15 | not modeled | Discretionary |
Project description (modeled)
| Modeled scope | Before | After |
|---|---|---|
| Grades | K-8 | K-8 |
| Sections per grade | 2 | 3 |
| Seats (20 per section) | 360 | 540 |
| Enrolled students | 352 | 518 by Year 5 |
| Building area | 48,000 sq ft | 76,000 sq ft (28,000 added; 6,000 renovated) |
| Staff (full-time equivalents) | about 45 | 62.0 in Year 3 |
| Modeled timeline | Months | Notes |
|---|---|---|
| Feasibility study and appraisal | 0 to 2 | This site's cost page lists 6 to 8 weeks for a Community Facilities study [14] |
| Bank credit evaluation and State Office application | 2 to 5 | Conditional commitment depends on CF guaranteed funding |
| Design, bids and closing | 5 to 8 | Fixed-price contract before closing |
| Construction | 8 to 22 | 14 months, timed to open at the start of a school year |
| Enrollment growth | Years 1 to 5 | One added section per grade as demand allows |
Project cost and sources and uses
Every line is an assumption with a range. A real budget comes from the architect's estimate, contractor bids and equipment quotes.
| Use of funds (modeled) | Amount | Share | Assumption range and how a real study sources it |
|---|---|---|---|
| Site work, parking, bus and parent drop-off, utilities | $650,000 | 5.1% | $450,000 to $900,000; civil estimate |
| Classroom addition, 28,000 gross sq ft at $290/sq ft (9 classrooms, 2 science and technology labs, multipurpose room) | $8,120,000 | 63.3% | $250 to $340 per sq ft; contractor bids |
| Renovation of existing building, 6,000 sq ft at $150/sq ft (offices, entry security, restrooms) | $900,000 | 7.0% | $110 to $200 per sq ft; contractor bids |
| Hard cost subtotal | $9,670,000 | 75.3% | |
| Construction contingency, 7% | $677,000 | 5.3% | 5% to 10% |
| Architecture and engineering, 7.5% | $725,000 | 5.6% | Design contract |
| Furniture, classroom technology and lab equipment | $540,000 | 4.2% | Vendor quotes |
| Permits, survey, geotechnical, environmental, testing | $160,000 | 1.2% | Fee schedules |
| Feasibility study, appraisal, legal and lender closing costs | $190,000 | 1.5% | Engagement letters, term sheet |
| CF guarantee fee, 1.25% of the 80% guaranteed share | $95,400 | 0.7% | 91 FR 11272 (FY2026) |
| Interest during construction, 14 months, average draw 55% at 7.00% | $428,505 | 3.3% | Draw schedule |
| Opening working capital for added staff (school funds) | $350,000 | 2.7% | Not payable from CF guaranteed loan funds |
| Total project cost | $12,835,905 | 100.0% |
At $12,835,905 the project costs about $71,311 per added seat. The CF guarantee fee and interest during construction may be paid from the loan [1]. Opening working capital for the added staff may not: CF guaranteed loan funds cannot pay initial operating expenses or working capital (5001.122(m)) [1], so the school funds $350,000 from reserves.
| Source of funds (modeled) | Amount | Share | Note |
|---|---|---|---|
| CF guaranteed loan from the regional bank | $9,540,000 | 74.3% | 80% guaranteed ($7,632,000); $1,908,000 at the bank's risk |
| School reserves | $1,195,905 | 9.3% | Unrestricted cash on the closing balance sheet |
| Capital campaign gifts collected | $1,600,000 | 12.5% | Collected or firmly scheduled |
| Foundation grant | $500,000 | 3.9% | Committed in writing |
| Total | $12,835,905 | 100.0% |
The modeled loan of $9,540,000 sits inside the published tier. USDA guarantees $7,632,000 and the bank keeps $1,908,000 at its own risk. Part 5001 sets no fixed equity floor for CF guaranteed loans; school reserves, campaign gifts and the foundation grant, 25.7% of cost, earn 10 priority points [1].
Market analysis
Reno County and its neighbors
The data modules on this site carry no school enrollment by district, so the market section works from population and births, the raw material of every enrollment projection.
| County | OMB 2023 | Population, July 2025 | Change since April 2020 | Births, 2021 to 2025 | Births, 2025 | Deaths, 2025 | Natural change, 2025 | Net migration, 2025 |
|---|---|---|---|---|---|---|---|---|
| Reno County | non-metro | 61,539 | -0.6% | 3,245 | 663 | 789 | -126 | 297 |
| McPherson County | non-metro | 30,064 | -0.5% | 1,502 | 285 | 420 | -135 | 104 |
| Rice County | non-metro | 9,266 | -1.6% | 527 | 100 | 107 | -7 | -4 |
| Kingman County | non-metro | 7,029 | -6.0% | 358 | 67 | 170 | -103 | 108 |
| Pratt County | non-metro | 9,117 | -0.4% | 514 | 95 | 100 | -5 | 16 |
| Stafford County | non-metro | 4,005 | -1.7% | 262 | 61 | 56 | 5 | 82 |
| Harvey County | metro | 33,580 | -1.3% | 1,851 | 396 | 441 | -45 | 2 |
| Sedgwick County | metro | 538,433 | 2.8% | 32,780 | 6,645 | 5,093 | 1,552 | 2,447 |
Sources: Vintage 2025 county estimates [7]; OMB July 2023 delineation [9].
Reno County is stable but not growing: 61,539 people in July 2025, 0.6% fewer than the April 2020 base. Deaths (789) outnumbered births (663) in 2025, and net in-migration of 297 kept the total steady. Its birth rate, 10.8 per 1,000 residents, is below the Kansas rate of 11.6. Every non-metro neighbor except Stafford County also had more deaths than births. Only Sedgwick County, the Wichita metro area to the southeast, is growing by natural increase. For a school, that means enrollment growth has to come from market share, transfers and families moving in, not from a rising number of children.
| Place | Population, April 2020 base | Population, July 2025 |
|---|---|---|
| Hutchinson city | 40,007 | 39,595 |
| Rest of Reno County (outside incorporated places) | 13,362 | 13,447 |
| South Hutchinson city | 2,521 | 2,516 |
| Buhler city | 1,325 | 1,320 |
| Haven city | 1,163 | 1,169 |
| Nickerson city | 1,066 | 1,051 |
| Pretty Prairie city | 661 | 652 |
Source: Vintage 2025 subcounty estimates [8]. Hutchinson holds 64.3% of the county's people, and South Hutchinson, Buhler, Haven and Nickerson add about 6,000 more within commuting distance.
Kindergarten cohorts: the share the school needs
| Birth year | Reno County births | Kindergarten year | Kindergarten-age children (births less 3%, assumed) | Share a 40-seat kindergarten (two sections) needs | Share a 60-seat kindergarten (three sections) needs |
|---|---|---|---|---|---|
| 2021 | 620 | 2026-27 | 601 | 6.7% | 10.0% |
| 2022 | 663 | 2027-28 | 643 | 6.2% | 9.3% |
| 2023 | 646 | 2028-29 | 627 | 6.4% | 9.6% |
| 2024 | 653 | 2029-30 | 633 | 6.3% | 9.5% |
| 2025 | 663 | 2030-31 | 643 | 6.2% | 9.3% |
Source: births from Vintage 2025 county estimates [7]; the 3% adjustment is an assumption. A third section at every grade means a kindergarten of 60, about 9% to 10% of the county's kindergarten-age children each year, against about 6% for the current two sections. Upper grades fill from the school's own kindergartens and from transfers, so the study tests both: kindergarten demand from the waiting list and lottery history, and transfer demand by grade. The model assumes the school's waiting list supports growth from 352 to 430 students in the first year of the addition and to 518 by Year 5; a real study counts the list by grade and removes duplicates and families who have enrolled elsewhere.
Absorption is where a study earns its fee. A third section in kindergarten fills from the lottery; a third section in seventh grade fills only from transfers, and families rarely move children in the middle grades without a reason. The model therefore adds sections from the bottom up as much as demand allows, reaching 22 sections in Year 1, 25 in Year 3 and 26 in Year 5. Three tests decide whether that path is credible. First, how many names on the waiting list are for each grade, and how many accepted a seat when one was offered in past years. Second, how many students leave the school each year by grade, because attrition in the upper grades has to be refilled before growth counts. Third, what other schools within commuting distance offer, including any district plans to add capacity. If the waiting list is concentrated in the early grades, the realistic path is slower and Year 1 coverage lower.
The national context for rural and town schools
| Locale (NCES) | Enrollment change, fall 2012 to fall 2022 | Average school size, 2022 |
|---|---|---|
| All public schools | -0.4% | 514 |
| Town (all) | -6.6% | 436 |
| Town, remote | -18.3% | 388 |
| Rural (all) | +9.2% | 372 |
| Rural, fringe | +20.5% | 560 |
| Rural, distant | -5.8% | 285 |
| Rural, remote | -5.4% | 164 |
Source: NCES, Digest of Education Statistics 2023, table 214.40, as compiled on this site's education facility page [10][13]. Locales are not USDA's population tests. Outside the fringe of large urban areas, town and rural enrollment has been falling, which is why a lender will not accept an enrollment plan that assumes growth without local evidence.
Childcare as the pipeline
Reno County had 4 child care centers with paid staff and 96 employees in 2023 [6], a thin early learning base for a county of about 61,500 people. Families who use a center near a school often enroll there, so the study notes any early learning partnership; the model assumes none.
USDA Community Facilities activity in the region
| State | CF loan awards | CF grant awards | CF awards, total |
|---|---|---|---|
| Kansas | 5 | 12 | 17 |
| Nebraska | 8 | 17 | 25 |
| Oklahoma | 10 | 37 | 47 |
| Colorado | 3 | 9 | 12 |
| Missouri | 8 | 24 | 32 |
| Iowa | 10 | 35 | 45 |
Source: USAspending, award counts by place of performance, 1 October 2023 to 30 September 2026 [11]. Kansas recorded 17 CF awards in that window, 5 of them loans, 37th of the 51 states with data. The closest CF precedents for charter schools on this site's state pages are outside Kansas: CF direct loans of $29,550,000 for five charter schools in Utah (2017), and a $1,775,000 CF guarantee for a public charter school in Kihei, Hawaii (2020) [13]. SBA does not lend to nonprofit schools, so there is no SBA benchmark for this borrower [12].
Financial feasibility
Revenue
Per-pupil revenue in the model is $10,800 in Year 1, rising 2% a year, plus $260,000 of other income. It stands for state and local formula money passed through by the sponsoring district, net of any amount the district keeps, plus federal program funds. The card describes the Kansas formula: base aid per student multiplied by weighted enrollment, with weights for at-risk students, career and technical education and transportation. A real study rebuilds the school's revenue from that formula line by line, using its own weighted enrollment and its charter agreement's pass-through terms, and treats any grant that ends before the loan as a downside item.
How the pass-through and the charter terms enter the revenue line
In the card's description of Kansas school finance, charter funding flows through the sponsoring local district. For a feasibility study that arrangement creates two separate questions. The first is the formula: how much the state and local formula generates for each student the school enrolls, including weights for students who qualify for them. The second is the pass-through: how much of that the district actually transfers to the school under the charter agreement, when, and whether the district keeps a share for administration or services it provides. The model assumes the district keeps 2% of per-pupil revenue. A real study reads the charter agreement and the district's budget for the school, reconciles both to the school's audited revenue for the last three years, and shows the bank which part of the per-pupil number comes from the formula and which from the agreement, because the two can change for different reasons and on different dates.
Enrollment plan
| School year | Enrolled students | Seats | Share of seats | Sections |
|---|---|---|---|---|
| Before the addition | 352 | 360 | 97.8% | 18 |
| Year 1 | 430 | 540 | 79.6% | 22 |
| Year 2 | 470 | 540 | 87.0% | 24 |
| Year 3 | 500 | 540 | 92.6% | 25 |
| Year 4 | 512 | 540 | 94.8% | 26 |
| Year 5 | 518 | 540 | 95.9% | 26 |
Staffing plan (modeled)
| Position (modeled, Year 3) | FTE | Year 1 salary |
|---|---|---|
| Classroom teachers (one per section) | 25.0 | $52,000 |
| Specials, special education and English learner teachers | 10.3 | $52,000 |
| Paraprofessionals | 13.1 | $26,000 |
| Principal | 1.0 | $105,000 |
| Assistant principal | 1.0 | $85,000 |
| Office and enrollment staff | 4.0 | $40,000 |
| Counselors | 2.0 | $60,000 |
| School nurse | 1.0 | $55,000 |
| Custodial and maintenance | 4.6 | $36,000 |
| Total staff, Year 3 | 62.0 | |
| Benefits and payroll taxes | 28% of salaries |
Teachers follow sections, not students: one classroom teacher per section of 20, with specials, special education and English learner staff, paraprofessionals and support positions that step up as sections are added. Salaries are assumptions; a real study uses the school's salary schedule and benefit costs. In Year 3, salaries and benefits are 66.1% of revenue.
Five-year pro forma
| Line (modeled) | Year 1 | Year 2 | Year 3 | Year 4 | Year 5 |
|---|---|---|---|---|---|
| Enrolled students (of 540 seats) | 430 | 470 | 500 | 512 | 518 |
| Class sections (20 students each) | 22 | 24 | 25 | 26 | 26 |
| Per-pupil revenue (state and local formula funds passed through, federal programs) | $4,644,000 | $5,177,520 | $5,618,160 | $5,868,056 | $6,055,558 |
| Other income (fees, food program, grants) | $260,000 | $265,200 | $270,504 | $275,914 | $281,432 |
| Total operating revenue | $4,904,000 | $5,442,720 | $5,888,664 | $6,143,970 | $6,336,991 |
| Salaries and benefits | $3,200,711 | $3,662,955 | $3,893,550 | $4,134,685 | $4,258,725 |
| Utilities, maintenance and insurance (76,000 sq ft) | $247,000 | $254,410 | $262,042 | $269,904 | $278,001 |
| Instructional supplies and technology refresh | $150,500 | $169,435 | $185,658 | $195,817 | $204,055 |
| Food service, net of reimbursement | $64,500 | $72,615 | $79,568 | $83,921 | $87,452 |
| Sponsoring district administrative share (2% of per-pupil revenue, assumed) | $92,880 | $103,550 | $112,363 | $117,361 | $121,111 |
| Audit, legal and professional fees | $60,000 | $61,800 | $63,654 | $65,564 | $67,531 |
| IT and student information systems | $90,000 | $92,700 | $95,481 | $98,345 | $101,296 |
| USDA retention fee passed through (0.50% of guaranteed balance) | $37,772 | $37,357 | $36,911 | $36,433 | $35,921 |
| Total operating expenses | $3,943,363 | $4,454,822 | $4,729,227 | $5,002,030 | $5,154,091 |
| Net operating income | $960,637 | $987,898 | $1,159,437 | $1,141,940 | $1,182,900 |
| Building reserve ($0.75 per sq ft) | $57,000 | $58,710 | $60,471 | $62,285 | $64,154 |
| Cash flow available for debt service | $903,637 | $929,188 | $1,098,966 | $1,079,655 | $1,118,746 |
| CF guaranteed loan debt service | $761,638 | $761,638 | $761,638 | $761,638 | $761,638 |
| Debt service coverage | 1.19x | 1.22x | 1.44x | 1.42x | 1.47x |
All figures are modeled. Coverage is cash flow after a building reserve divided by annual debt service on the CF guaranteed loan.
In Year 3 the school enrolls 500 students, earns $5,888,664 and covers debt service 1.44x. Year 1 coverage is 1.19x, positive but below a 1.25 times target while the third sections fill. Cost per student in Year 3 is about $9,458 before debt service.
Debt service on the CF guaranteed loan (illustrative rate)
The rate is an assumption: 7.00% fixed over 30 years, the rate this site's education facility page uses for its school example [13]. CF guaranteed rates are negotiated between bank and borrower, may be fixed or variable, and may not exceed the bank's rate on similar loans without a guarantee; the term runs to useful life, up to 40 years or state law, with no balloon [1]. The 0.50% retention fee is charged on the guaranteed share of the balance and is passed through to the school in the model [5].
| Loan year | Opening balance | Interest | Principal | Debt service | Closing balance | Guaranteed portion (80%) | Retention fee |
|---|---|---|---|---|---|---|---|
| Year 1 | $9,540,000 | $664,730 | $96,908 | $761,638 | $9,443,092 | $7,554,473 | $37,772 |
| Year 2 | $9,443,092 | $657,725 | $103,914 | $761,638 | $9,339,178 | $7,471,342 | $37,357 |
| Year 3 | $9,339,178 | $650,213 | $111,426 | $761,638 | $9,227,752 | $7,382,202 | $36,911 |
| Year 4 | $9,227,752 | $642,158 | $119,481 | $761,638 | $9,108,272 | $7,286,617 | $36,433 |
| Year 5 | $9,108,272 | $633,520 | $128,118 | $761,638 | $8,980,154 | $7,184,123 | $35,921 |
Annual debt service is $761,638; cash flow of $952,048 would give 1.25 times coverage. Over 30 years the school would pay $22,849,149, $13,309,149 of it interest at the assumed rate.
Break-even enrollment
| Enrolled students (Year 3) | Share of 540 seats | Sections | Revenue | Cash flow for debt service | Coverage |
|---|---|---|---|---|---|
| 425 | 78.7% | 22 | $5,045,940 | $810,796 | 1.06x |
| 450 | 83.3% | 23 | $5,326,848 | $952,118 | 1.25x |
| 475 | 88.0% | 24 | $5,607,756 | $957,644 | 1.26x |
| 500 | 92.6% | 25 | $5,888,664 | $1,098,966 | 1.44x |
| 520 | 96.3% | 26 | $6,113,390 | $1,187,882 | 1.56x |
| Break-even: about 375 | 69.4% | 1.00x | |||
| 1.25x: about 474 | 87.9% | 1.25x |
The school covers its debt down to about 375 students in Year 3, 69.4% of the new capacity, and reaches 1.25 times at about 474. The steps in the table are real: a school saves a teacher only when a whole section closes, so coverage moves in jumps as enrollment crosses multiples of 20. The low break-even also assumes the school would cut sections and staff as enrollment fell; teacher contracts make that slower in practice, which is why the study shows both the arithmetic and the contracts.
Per-pupil funding
| Cut in per-pupil revenue | Per-pupil revenue, Year 3 | Cash flow for debt service, Year 3 | Coverage, Year 3 |
|---|---|---|---|
| 0% | $11,236 | $1,098,966 | 1.44x |
| 2% | $11,012 | $988,850 | 1.30x |
| 5% | $10,675 | $823,676 | 1.08x |
| 8% | $10,337 | $658,502 | 0.86x |
A 5% cut in per-pupil revenue takes Year 3 coverage to 1.08 times, and an 8% cut below 1.00. Per-pupil funding is set by the legislature, so the study models the formula and shows what a cut at the next budget would do.
Sensitivity and stress tests
| Scenario (modeled) | Year 1 coverage | Year 3 coverage | Year 5 coverage | Note |
|---|---|---|---|---|
| Base case | 1.19x | 1.44x | 1.47x | |
| Enrollment 5% lower every year | 1.19x | 1.26x | 1.27x | |
| Enrollment 10% lower every year | 1.06x | 1.25x | 1.06x | |
| Enrollment stalls at 470 | 1.19x | 1.19x | 1.12x | |
| Per-pupil revenue 3% lower | 1.01x | 1.23x | 1.24x | |
| Per-pupil revenue 5% lower | 0.89x | 1.08x | 1.08x | |
| Salaries 5% higher | 0.98x | 1.19x | 1.19x | |
| Variable rate 1 point higher, re-amortized | 1.08x | 1.31x | 1.33x | |
| Variable rate 2 points higher, re-amortized | 0.98x | 1.19x | 1.21x | |
| Construction overrun of 10% of hard cost, added to the loan | 1.07x | 1.30x | 1.32x | loan $10,560,000 |
- Enrollment that stalls is the main risk. If enrollment stops at 470, coverage falls to 1.12 times by Year 5; 10% lower enrollment every year gives 1.06 by Year 5.
- Funding and salaries matter as much. Per-pupil revenue 5% lower gives 1.08 times in Year 3; salaries 5% higher, 1.19.
- Rate and cost are manageable. A variable rate two points higher re-amortized leaves 1.19 times in Year 3; a 10% overrun added to the loan raises it to $10,560,000 and leaves 1.30.
Equity test under the CF guaranteed rule
Part 5001 sets no fixed equity percentage for CF guaranteed loans; the B&I table in 5001.105(d) does not apply [1]. The test is the school's balance sheet after closing and the share of other funds, which earns priority points. In the model the school puts in $3,295,905, 25.7% of cost, and still holds the working capital it needs for the added staff.
Technical and environmental feasibility
- Building program. Classroom sizes, labs and a multipurpose room sized to the added enrollment; secure entry and restrooms in the renovated building. The architect's report and code review set them.
- Accessibility. Private schools are places of public accommodation under 28 CFR part 36, and public schools fall under the rules for public entities [16]. A charter school's status decides which applies; accessible design belongs in the budget either way.
- Construction while school is in session. Phasing, separation of the work area and summer scheduling for the renovation.
- Environmental review. USDA completes an environmental review before committing; the addition sits on the existing campus.
- Construction timing. Construction completed before the application is ineligible for a CF guarantee (5001.116(c)) [1].
- Collateral. Real estate over $250,000 needs a USPAP appraisal with as-is and prospective values, the appraisal may be no more than a year old at closing, and an appraisal review is required [1]. A school is special-purpose collateral: if the school closed, the building's value would depend on whether another school, the district or a different user could take it over. The study cannot replace the appraisal, but it can describe the alternative uses and the district's own space needs, which the bank uses when it discounts the collateral.
The charter and the loan term
| If the charter ended at | Loan balance | Share of original loan | USDA-guaranteed share | Bank's unguaranteed share |
|---|---|---|---|---|
| End of Year 5 | $8,980,154 | 94.1% | $7,184,123 | $1,796,031 |
| End of Year 10 | $8,186,501 | 85.8% | $6,549,201 | $1,637,300 |
| End of Year 15 | $7,061,400 | 74.0% | $5,649,120 | $1,412,280 |
| End of Year 20 | $5,466,427 | 57.3% | $4,373,142 | $1,093,285 |
| End of Year 25 | $3,205,354 | 33.6% | $2,564,283 | $641,071 |
The table shows what is at stake if the charter ended before the loan. Even after 15 years, about three quarters of the original balance would be outstanding, most of it guaranteed by USDA. That is why the bank and the State Office read the charter as carefully as the pro forma: its term, its renewal history with the sponsoring district, the performance conditions it sets and what happens to the building if it ends. The study recommends a structure that answers the gap, such as a covenant tied to renewal, a reserve that builds before each renewal date, or an agreement with the sponsor on the building's use.
Financing alternatives
| Financing option for the same amount (illustrative) | Annual debt service | Retention fee, Year 1 | Year 3 coverage |
|---|---|---|---|
| CF guaranteed loan (model) | $761,638 | $37,772 | 1.44x |
| Same loan at 7.00% over 40 years | $711,415 | $37,980 | 1.54x |
| Tax-exempt borrowing at an illustrative 5.25%, 30 years (no USDA guarantee) | $632,163 | none | 1.80x |
| Conventional bank loan at an illustrative 7.75%, 20 years (no guarantee) | $939,822 | none | 1.21x |
All rates are illustrative. A 40-year term, which Part 5001 allows where the building's useful life supports it [1], lowers the payment by about $50,000 a year. Tax-exempt borrowing would cost less again, but a CF guarantee cannot be combined with it [1], and whether this borrower can issue tax-exempt debt is a legal question outside the study. A conventional loan without a guarantee, typically shorter, would leave coverage near 1.2 times. The study's job is to set these side by side so the board and the bank choose with the numbers in view.
Management and governance feasibility
For a charter school the central management question is the charter itself. The study reads the charter agreement with the sponsoring district: its term, renewal history, performance conditions and what happens to the building if the charter ends. A loan longer than the charter needs a plan for that gap, such as a covenant, a reserve or a guarantee [13]. The study also reviews the governing board's ties to the community, which CF requires [1], the school's audited statements, its enrollment history by grade, its academic and financial reporting to the sponsor, and its leadership's record running a school of the larger size.
Process and documents
| Step | What happens | Rule |
|---|---|---|
| Eligibility and lender | The bank confirms program, borrower and rural area with the State Office | 5001.3; 5001.103 [1] |
| Feasibility and credit | Financial feasibility report or study; the bank's written credit evaluation of it | 5001.202, 5001.304 [1][2] |
| Local support | Certification of support from each affected local government | Part 5001 [1] |
| Commitment | Conditional commitment from the State Office | Part 5001 [1] |
| Closing | Appraisal, closing balance sheet, loan note guarantee at closing or, for 0.50% more, before construction is complete | 5001.203; 91 FR 11272 [1][5] |
Documents the bank and the State Office will look for: three years of audited statements; enrollment by grade for five to ten years; the waiting list by grade; the charter agreement and its renewal history; the funding formula worksheet and the sponsor's pass-through terms; board resolutions and organizational documents; the architect's preliminary report and cost estimate; and local government support letters. This site's cost page lists Community Facilities studies at $6,900 to $12,000 and 6 to 8 weeks from the engagement letter [14].
Economic and community impact (modeled)
| Impact measure (modeled) | Value | Basis |
|---|---|---|
| Seats added | 180 | Capacity from 360 to 540 |
| Students enrolled by Year 5 | 518 | Enrollment plan |
| Staff positions added by Year 3 | 17.0 | Staffing model |
| Year 3 salaries and benefits | $3,893,550 | Pro forma |
| Construction spending (hard cost and contingency) | $10,347,000 | Budget |
| Reno County population, July 2025 | 61,539 | Census Vintage 2025 |
The impact the State Office weighs is educational access in a county where the number of children is flat: 180 more seats in a school families are waiting to enter, and about 17 more school jobs.
Risks and mitigants
| Risk | How it shows up in the model | Mitigant the study tests |
|---|---|---|
| Enrollment stalls | At 470 students, 1.12x by Year 5 | Waiting list by grade; lottery history; transfer demand |
| Per-pupil funding cut | 5% lower gives 1.08x | Formula rebuilt line by line; budget scenario |
| Salaries rise faster | 5% higher gives 1.19x | Salary schedule; staffing by section |
| Charter not renewed | Revenue stops | Charter term and renewal record; covenant or guarantee covering the gap |
| Variable rate | +2 points gives 1.19x | Fixed rate or cap |
| Construction overrun | 10% gives 1.30x | Contingency; fixed-price contract |
| Funding timing | Hutchinson is outside the funds reserved for places of 20,000 or less | Schedule around the State Office's funding calendar |
What the five Part 5001 components showed
| Component | What the model shows | What a reviewer still asks |
|---|---|---|
| Economic | 180 seats and about 17 jobs | Local construction labor |
| Market and need | Flat population; a third section needs about 9% to 10% of each kindergarten cohort | Waiting list by grade; transfers |
| Technical | A 28,000 sq ft addition on the existing campus | Architect's report; accessibility |
| Financial | Coverage 1.19x in Year 1 and 1.44x in Year 3 | Formula revenue rebuilt; staffing by section |
| Management | Board, leadership and charter | Charter term against loan term |
Why school studies are sent back
- Enrollment assumed at capacity, or projected without births, waiting lists and transfers by grade.
- Per-pupil revenue taken as a single number instead of the state formula.
- Grants that end before the loan treated as permanent.
- A loan term set without addressing charter renewal.
- The wrong report type for the borrower's situation [1][2].
- Working capital placed in a CF guaranteed loan that cannot pay it [1].
Program terms that applied
| Term | CF guaranteed rule | Source |
|---|---|---|
| Guarantee | 80% in FY2026; 90% is the regulatory ceiling | 91 FR 11272; 5001.407 [1][5] |
| Up-front fee | 1.25% of the guaranteed amount ($95,400 on the modeled loan) | 91 FR 11272 [5] |
| Annual retention fee | 0.50% of the guaranteed balance ($37,772 in Year 1) | 91 FR 11272 [5] |
| Fee if the guarantee is issued before construction completion | 0.50% | 91 FR 11272 [5] |
| Maximum loan | $100 million per borrower | Part 5001 [1] |
| Term | Useful life, up to 40 years or state law; no balloon | 5001.402 [1] |
| Rural area and priority | Outside cities over 50,000 and their urbanized areas; funds reserved first for places of 20,000 or less | 5001.3, 5001.103(c), 5001.316(e) [1] |
| Tax status | Interest cannot be tax-exempt | Part 5001 [1] |
| Feasibility evidence | Financial feasibility report always; independent study over $1 million to a new entity or activity | 5001.304 [1][2] |
The FY2026 notice governs loans obligated in fiscal year 2026 [5]; a 2023 obligation, like this engagement, was priced under that year's notice, which this site has not read.
Lessons for sponsors of similar projects
- Check the population count first. A town between 20,000 and 50,000 can use a CF guarantee but not CF direct money or grants.
- Count the waiting list by grade. A third section at every grade needs about one kindergartner in ten in a county like Reno.
- Rebuild the funding formula. Per-pupil revenue is a set of weights, not a single number, and a 5% cut changes the answer.
- Match the loan to the charter. If the charter ends before the loan, the study and the bank need a plan for the gap.
- Keep working capital out of the loan. CF guaranteed funds cannot pay it.
- Expect coverage to step with sections. Teachers are added and removed by section, so coverage moves in jumps.
Related pages
- The CF guaranteed engagement page lists this program's engagements, including this one.
- The national education facility feasibility study page sets out CF rules for schools, enrollment tests and worked examples [13].
- The Kansas state page carries the State Office in Topeka and the state's precedents; the site does not yet have state education facility pages.
- The Community Facilities feasibility study page explains the program, and the case studies page lists long-form work.
If your school is planning an addition and needs a USDA feasibility study consultant, the engagement index describes the process: a fifteen-minute scoping call, a written proposal inside one business day and a firm fixed fee before you sign [15]. Request a proposal for your study [17].
Data current as of November 2026.