Wastewater Treatment Expansion Feasibility: Texas USDA Feasibility Study Case Study

    Last updated 2026-11-08

    How to read this case study. The engagement summary reflects the published record. Client names, actual costs, loan terms and proprietary data are confidential, so the project budget, market sizing and financial projections below are a modeled example built from public data for this project type and location. They show the analysis a lender-grade study performs, not the client's figures.

    In 2025 this practice prepared a feasibility study for a wastewater treatment plant expansion in Dalhart, Texas, under the USDA Water and Waste Disposal (WWD) program in the $5 million to $25 million tier. USDA was the lender, and the study was prepared with load and capacity analysis. This page works through the questions that kind of study answers, using a modeled plant, a modeled sewer utility of about 4,200 equivalent dwelling units (EDUs) and public data for Dalhart, Dallam County and Hartley County.

    A wastewater expansion asks a question a water plant upgrade does not: how big? Build too small and the city is back in the design office within a decade; build too large and today's households pay for capacity that tomorrow's users, or one industrial customer, will use. The engineer's preliminary engineering report (PER) designs the plant, and this practice does not prepare PERs. The load and capacity analysis supplies the demand side the PER sizes against: who sends flow and organic load to the plant now, how that changes over a twenty-year design period, which user groups drive the expansion, and what each alternative does to the rate. The model below finds that organic load, not flow, is what fills the plant, and that a single industrial user can decide both the right size and who should pay for it. Data current as of November 2026.

    Engagement summary

    Published recordDetail
    ProgramUSDA Water and Waste Disposal direct loan and grant (filed under WEP on the engagement index)
    ProjectWastewater treatment plant expansion
    LocationDalhart, Texas (Dallam and Hartley counties, Southwest region)
    Loan size tier$5 million to $25 million
    Year2025
    LenderUSDA direct
    OutcomePrepared with load and capacity analysis

    Source: this site's engagement index [11]. The plant, flows, loads, users, budget, rates and projections below are a model, not the city's permit, flows, rates or debt.

    The engagement card on the index carried a longer summary. This page keeps what the regulations and data on file support, corrects what they contradict, and marks the rest as the card's own statement.

    Statement in the engagement cardStatus on this page
    The U.S. wastewater sector has $99 billion of annual capital needs against about $30 billion of funding, a $69 billion gap (ASCE 2025 Infrastructure Report Card)Kept as the card's statement; not checked
    Renewal and replacement of large capital projects fell from 3% to 2% a decade; collection failures rose from 2.0 to 3.3 per 100 miles of pipeKept as the card's statement; not checked
    Residential wastewater bills rose from $35 to nearly $65 a month between 2010 and 2020Kept as the card's statement; not used in the model
    Texas rural utilities face growth, aging equipment and TCEQ discharge permits that require nutrient removal the original plants cannot provideKept as the card's general statement. The model leaves room for nutrient removal but does not assume a permit limit
    Texas Water Development Board commitment of $125 million for the Eagle Mountain water treatment plant expansion (2024), about $3.57 per gallon of capacityKept as the card's statement, but not used as a benchmark: it is a drinking water plant in a metropolitan system, not a rural wastewater plant
    Fort Bend County MUD 142's 1.2 MGD expansion at $25.7 million (about $21.4 million per MGD) as "a rural MUD cost benchmark"Kept as the card's statement; the arithmetic is consistent, but Fort Bend County is in the Houston metropolitan area, so this page does not treat it as a rural benchmark
    Texas construction escalation of 3% to 6% a yearKept as the card's statement; the model tests a 4% delay case
    Eligible borrowers are public entities (MUDs, WCIDs) and nonprofits in rural areasKept: public bodies and community-controlled nonprofits in areas not in a city or town over 10,000 (1780.3, 1780.7) [1]
    "At $5M to $25M, this engagement required a full Preliminary Engineering Report per RUS Bulletin 1780-7" with flows, loads, capacity headroom, growth projections and technology selectionCorrected in part. Every WWD application needs a PER regardless of size (1780.33(c)) [1]; the bulletin number was not checked. The PER contents listed are the engineer's; the flow and load projections are where the load and capacity analysis meets the PER
    The State Environmental Coordinator's environmental review ran concurrently and was completedKept as the card's statement; not checked
    The study modeled loan-only and grant and loan scenarios, with the rate per residential connection in each and the grant level needed to hold rates within USDA's affordability thresholdConsistent with the published outcome. This page shows both in model form

    The question USDA needed answered

    For a WWD direct loan Rural Development needs proof that the project is the right size and that users can pay for it. The size question has two rules pulling against each other: facilities must have adequate capacity for present needs and reasonably foreseeable growth (1780.7(c)) and must be modest in size, design and cost (1780.10(a)(1)) [1]. The payment question is the economic feasibility test: taxes, assessments, revenues or fees must cover operation and maintenance, reasonable reserves and debt payment (1780.7(f)), with rates set on realistic users (1780.39(c)(1)) [1]. And when the system depends on a business that is its primary user, that business's viability must be assessed (1780.7(f)), while costs a business would normally bear, such as pretreatment, are not eligible (1780.10(a)(5)) [1].

    Document or taskRuleWho prepares itWhat it decides
    Preliminary engineering report1780.33(c), 1780.55The city's engineer, licensed in Texas (1780.54)Process, capacity, alternatives, cost estimate
    Load and capacity analysis1780.7(c), 1780.10(a)(1)Feasibility consultant, with the engineerDesign flows and loads; which alternative is modest yet adequate
    Environmental report1780.33(f), 1780.55Environmental professionals under 7 CFR part 1970No action that limits alternatives before review ends (1780.57(a))
    Operating budget and rate schedule1780.33(h)(1), 1780.35(c), 1780.39(c)Applicant, with its feasibility consultantRevenue covers O&M, reserves and debt service
    Business viability assessment1780.7(f)Independent business study when a business is the main userWhether the system can rely on that business
    Grant determination1780.35(b)Processing office, from the applicant's numbersDebt service share of income; similar system cost

    Eligibility and program fit

    TestRuleDalhart result
    Rural areaNot in a city or town over 10,000 under the latest decennial census (1780.3)Eligible: 8,429 residents in the April 2020 estimates base and 8,377 in July 2025 [4]
    ApplicantPublic body, community-controlled nonprofit or tribe (1780.7(a))A city is a public body
    Credit elsewhereCannot finance on reasonable rates and terms (1780.7(d))Certified; the study's financing comparison supports it
    Capacity and growthAdequate for present needs and reasonable growth; modest in size (1780.7(c), 1780.10(a)(1))The sizing alternatives below
    Business userViability assessed if a business is the primary user; pretreatment ineligible (1780.7(f), 1780.10(a)(5))The model's industrial user is a minority of flow but 28% of organic load
    County settingNon-metro proxyDallam and Hartley counties lie outside any metropolitan or micropolitan area in the OMB July 2023 delineation [6]

    WWD guaranteed loans under part 5001 carry a 90% guarantee, a 1.0% fee and no annual retention fee in fiscal 2026, up to $50 million per borrower, and use the broader 50,000 rural test [2][3]. A city of 8,400 eligible for direct loans will usually compare the direct program's 40-year term and income-based rate tiers with state revolving fund financing, which Texas runs through its water development board, rather than with a guaranteed bank loan.

    Texas has more places inside the WWD population line than any state but Illinois [8]. The Census file counts 988 incorporated places of 10,000 or fewer, 80.7% of the state's 1,224 [4]:

    Texas incorporated places, April 2020 basePlacesResidents, 2020 baseResidents, July 2025Places that lost populationWWD population priority points
    1,000 or fewer438206,600222,9919125
    1,001 to 2,500263433,876488,5467415
    2,501 to 5,500191729,618843,656535
    5,501 to 10,000 (Dalhart)96721,668816,753260
    10,001 to 50,0001683,698,3714,213,59143Outside the direct rural test
    Over 50,0006815,331,04016,248,6289Outside the direct rural test

    Source: Census Vintage 2025 subcounty estimates [4]; points from 1780.17(a) [1].

    Dalhart earns no population points. Its score has to come from the health priority, which a plant at its permit limits can earn with 25 points when the PER documents the inadequacy, and from income and other funds.

    Project description (modeled)

    The model treats Dalhart's plant as a mid-sized activated sludge facility with an assumed permitted average flow of 1.20 million gallons a day (MGD) and an assumed design organic capacity of 2,400 pounds a day of biochemical oxygen demand (BOD). The expansion adds a new aeration basin with zones that can be operated for nutrient removal if a renewed permit requires it, a new secondary clarifier, upgraded headworks and lift station, ultraviolet disinfection, more solids capacity, and the electrical, controls and standby power to run them.

    Modeled users and loads today

    User classConnectionsEDUs (flow basis)Flow (MGD, dry weather)BOD (lb/day)Share of BOD
    Residential3,0203,0200.5741,35958.6%
    Commercial, institutional and public3606900.13131013.4%
    One significant industrial user (assumed)14740.09065028.0%
    Total3,3814,1840.7952,320100.0%

    The industrial user is an assumption. County Business Patterns show 7 manufacturing establishments with 361 employees in Dallam County and 5 with 31 in Hartley County in 2023 [7]; the published county cells do not show which of them, if any, discharge to the city plant or at what strength. A real study reads the city's industrial user permits and billing records. The model includes one such user because a strong industrial discharge is the most common reason a small plant fills its organic capacity before its hydraulic capacity, and because Part 1780 treats a business user differently.

    Existing plant against its permit

    MeasureTodayPermitted or design capacityShare used
    Annual average daily flow, including 15% inflow and infiltration0.94 MGD1.20 MGD77.9%
    Maximum 30-day average flow (1.13 x annual average)1.06 MGD1.20 MGD88.1%
    Organic load (BOD)2,320 lb/day2,400 lb/day96.6%

    At 88% of permitted flow in the peak month and 97% of organic capacity, the modeled plant is out of room on load and close to it on flow. Texas permits are commonly read with planning and construction triggers at 75% and 90% of permitted flow; the engineer and the state permit writer apply the actual rule, and the model uses those two lines only as analysis thresholds.

    Modeled schedule

    PhaseMonths from engagementWhat happens
    Load and capacity analysis with the PER0 to 5Flow and load records, projections, sizing alternatives, rate work
    Application and review5 to 10Completeness within 15 federal working days; eligibility and funding advice within 45 days of a complete file (1780.32)
    Letter of conditions, design and permits10 to 20Rate ordinance, industrial user agreement, design, environmental review
    Bidding and construction20 to 38Eighteen-month build with interim financing (1780.39(d))
    Year 1 of operations38 to 50New rates and surcharges in force

    Market analysis: who sends flow and load, and how that changes

    Population and its geography

    Dalhart straddles a county line, and its two halves are moving in opposite directions. The part of the city in Dallam County grew from 5,493 in the April 2020 base to 5,770 in July 2025 (+5.0%); the part in Hartley County fell from 2,936 to 2,607 (-11.2%) [4]. Net, the city lost 52 people (-0.6%). Dallam County as a whole grew 5.2%, from 7,135 to 7,508, with 575 more births than deaths and 625 net international migrants offsetting 837 net domestic departures; Hartley County fell 8.6% [5]. A load study does not average those numbers away. It asks where the growth is happening relative to the sewer system, and whether a fall of that size on one side of town reflects households leaving or a change in group quarters, which counts as population but connects as a single customer.

    Regional comparison: the northwest Texas Panhandle

    CountyCounty seatOMB 2023 statusApril 2020 baseJuly 2025ChangeBirths less deathsNet internationalNet domestic
    DallamDalhartNon-metro7,1357,508+5.2%+575+625-837
    HartleyChanningNon-metro5,3634,904-8.6%+108+18-598
    ShermanStratfordNon-metro2,7772,781+0.1%+110+84-192
    MooreDumasNon-metro21,36321,891+2.5%+1,003+1,434-1,918
    HansfordSpearmanNon-metro5,2754,944-6.3%+43+80-444
    OldhamVegaMetro1,7591,783+1.4%+6+47-28
    PotterAmarilloMetro118,622114,453-3.5%+704+2,828-7,736
    RandallCanyonMetro140,670152,351+8.3%+1,695+1,037+8,967

    Sources: Census Vintage 2025 county estimates, components summed from April 2020 to July 2025 [5]; OMB July 2023 delineation [6].

    The pattern across the northwest Panhandle is the same in every non-metro county: births and international arrivals keep populations roughly level while residents move away within the United States. Dallam and Moore counties are the two that grew. For a plant with a twenty-year design horizon, the honest base case is modest growth, about 0.5% a year in households and businesses, with a low case at the city's own trend and a high case that only an identified industrial expansion would justify.

    Flow and load projections

    ScenarioYear 5Year 10Year 20 (design year)
    Low: city trend, -0.12% a year; industry flat0.93 / 1.05 / 2,3110.93 / 1.05 / 2,3030.92 / 1.04 / 2,287
    Base: +0.5% a year households and business; industry +2% a year0.97 / 1.09 / 2,4291.00 / 1.13 / 2,5471.07 / 1.21 / 2,810
    High: +1.0% a year; industrial user doubles its load in Year 51.08 / 1.22 / 3,0551.13 / 1.27 / 3,1441.22 / 1.38 / 3,337

    When the existing plant runs out of room

    ScenarioMax 30-day flow reaches 75% of permitMax 30-day flow reaches 90%BOD reaches 90% of designBOD reaches 100% of design
    Low: city trend, -0.12% a year; industry flatnowbeyond Year 40nowbeyond Year 40
    Base: +0.5% a year households and business; industry +2% a yearnowYear 4nowYear 4
    High: +1.0% a year; industrial user doubles its load in Year 5nowYear 3nowYear 5

    In the low case, flows never reach 90% of the permit, but organic load is already at 90% of design and stays there. In the base case, flow and load both reach the 90% line in Year 4. In the high case, flow reaches it in Year 3 and load passes 100% of design when the industrial user doubles in Year 5. The analysis therefore points to an expansion now under any scenario, because of organic load, and leaves the size to be decided by how much of the high case is real.

    The commercial base

    County, 2023Hotels and motels (establishments / employees)Restaurants (establishments / employees)Gasoline stations with storesManufacturing (establishments / employees)
    Dallam8 / 6518 / 3065 / 667 / 361
    Hartleynot shown3 / 29not shown5 / 31

    Source: Census County Business Patterns 2023 [7]. Restaurants combine full-service and limited-service; "not shown" means fewer than three establishments in the county extract.

    Dalhart's commercial users are a highway town's: lodging, food service and fuel along the routes through town. They send ordinary-strength wastewater in volumes that follow travel seasons, and the model counts them as 690 EDUs on 360 connections.

    Sizing alternatives

    AlternativeTotal project costCost per gallon a day of capacity addedAnnual installmentInstallment per EDU a yearReaches 90% of capacity, base caseReaches 90%, high case
    A: rehabilitate and expand to 1.5 MGD, 3,100 lb/day$15,423,155$51$667,449$160Year 20Year 5
    B: expand to 1.8 MGD, 3,800 lb/day (model)$18,114,472$30$788,619$188Year 39Year 25
    C: expand to 2.2 MGD, 4,600 lb/day$20,985,210$21$917,895$219beyond Year 40beyond Year 40

    This table is the heart of a load and capacity study. Alternative A is cheapest and reaches 90% of capacity in Year 20 in the base case, which is the design year with no margin, but fails in Year 5 if the industrial user expands. Alternative C has the lowest cost per gallon of capacity added and never fills within the loan term, which is the argument a reviewer will challenge under the modest-size rule: households would pay for capacity nobody is projected to use. Alternative B covers the base case for 39 years and the high case for 25, at $28 a year per EDU more than A. The model carries B, with one condition that matters more than the size: if the high case depends on the industrial user, the industrial user should commit to it in writing and pay for it.

    Phasing instead of choosing

    A fourth answer is to build in phases: size the headworks, lift station, piping and site for alternative C, and build the biological and clarifier capacity of alternative A or B now, with room on the site and in the hydraulic profile for the next train. Phasing moves the decision about the high case to the moment the industrial user actually expands, when it can sign for the capacity it needs. The cost is a larger first phase than A alone, because the parts that are hard to enlarge later are built once, and a second mobilization later. The study prices phasing as its own alternative when the PER shows the site and process allow it, and Part 1780's modest-size rule tends to favor it when growth is uncertain [1].

    What the study reads in an industrial user agreement

    An agreement that protects the city and the loan carries six things: the reserved capacity in flow and pounds of BOD and suspended solids; a minimum monthly charge for that capacity whether it is used or not; a term at least as long as the share of debt the capacity supports, or a buy-out if the user leaves early; pretreatment limits and the user's duty to pay for pretreatment; sampling and metering rights; and a reopener if the user's discharge changes. Without those terms, the high case in this model is a hope, and a State Office reviewer is right to discount it.

    Project cost and sources and uses

    Line itemAmountAssumed range
    Headworks: screening and grit removal$1,250,000$1,000,000 to $1,500,000
    Influent lift station upgrade$1,100,000$850,000 to $1,350,000
    Biological treatment: new aeration basin with zones that can be run for nutrient removal$4,200,000$3,400,000 to $5,100,000
    Blowers and fine-bubble aeration$1,050,000$850,000 to $1,300,000
    Secondary clarifier$1,600,000$1,300,000 to $1,950,000
    Ultraviolet disinfection$750,000$600,000 to $950,000
    Solids: digester expansion and dewatering$1,500,000$1,200,000 to $1,850,000
    Electrical, SCADA and standby power$1,350,000$1,100,000 to $1,650,000
    Site work and yard piping$900,000$700,000 to $1,150,000
    Laboratory and operations building rehabilitation$400,000$300,000 to $520,000
    Construction subtotal$14,100,000
    Construction contingency, 10% at PER stage$1,410,0005% to 15%
    Engineering: PER, design, bidding, construction administration and inspection (12%)$1,692,000Engineer's contract
    Environmental report and review (7 CFR part 1970)$60,000Environmental consultant
    Legal and bond counsel$75,000Counsel's engagement letter
    Fiscal advisory: load, capacity, rate and affordability analysis$15,000Inside the site's $5,000 to $15,000+ range for rate analysis; not this engagement's fee
    Administration, permits and publication$40,000Assumed
    Interest on interim construction financing (18 months, 50% average draw, 5.50%)$722,472Interim lender; 1780.39(d)
    Total project cost$18,114,472
    UseAmountShare
    Construction and contingency$15,510,00085.6%
    Engineering$1,692,0009.3%
    Environmental, legal, fiscal and administration$190,0001.0%
    Interim interest$722,4724.0%
    Total$18,114,472100.0%
    SourceAmountShareTerms
    USDA Water and Waste Disposal direct loan$17,514,00096.7%40 years at an illustrative 3.25% intermediate rate
    City wastewater fund reserves$600,4723.3%Deposited before loan funds
    USDA grant$00.0%Not triggered in the base case
    Total$18,114,472100.0%

    At $18,114,472 the modeled project sits in the middle of the published tier and costs $4,330 per EDU. Construction-period interest is eligible only from loan funds, and fiscal advisory, engineering and environmental fees are eligible project costs (1780.9(e)) [1]; costs paid before approval need a written request and a finding of compelling reasons (1780.9(f)) [1]. The city's $600,472 of reserves is 3.3% of the project, below the 5% that earns other-funds points (1780.17(d)(4)) [1]. A state revolving fund loan or grant for 20% or more of the cost would earn 10 points and reduce the WWD loan, which is why the funding plan belongs in the feasibility package with commitment letters.

    Financial feasibility

    Modeled operating budget

    ItemAmountPer EDU a year
    Personnel: 6.0 FTE (licensed operators, collections, share of billing) at $74,000 loaded$444,000$106
    Electricity, mostly aeration$185,000$44
    Chemicals$40,000$10
    Biosolids hauling and disposal$95,000$23
    Laboratory and permit monitoring$30,000$7
    Repairs and maintenance, plant and lift stations$160,000$38
    Insurance$45,000$11
    Billing, administration, audit and allocated overhead$140,000$33
    Operation and maintenance before the expansion$1,139,000$272
    Added O&M from the expansion (aeration, UV, solids)$120,000$29
    Short-lived asset replacement reserve$160,000$38

    Grant determination: loan only

    StepCalculationResult
    1. Income ratio$54,000 / $60,000 (both assumed)90.0%: intermediate tier, 45% ceiling, 1.0% threshold
    2. Threshold per EDU1.0% x $54,000$540 a year
    3. Proposed debt service$17,514,000 at 3.25% for 40 years$788,619 a year
    4. Debt service per EDU$788,619 / 4,184 EDUs$188 (0.35% of MHI)
    5. Grant considered?$188 vs $540No
    6. Loan at which the test would start$540 x 4,184 / 0.04503about $50,173,000

    At an assumed service-area income of $54,000, 90% of an assumed $60,000 Texas statewide non-metro median, the debt service per EDU is $188 a year against a $540 threshold, so no grant is considered and the project proceeds on the loan. The illustrative rates are those this site's national WWD page uses: market 4.125%, intermediate 3.25% and poverty 2.50%; Rural Development publishes the actual rates each quarter [9].

    Loan only or grant and loan: the grant level needed to hold the threshold

    Service-area MHI (share of assumed $60,000 state non-metro)Existing sewer debt service a year (assumed)Rate tierThreshold per EDUDebt service per EDU, loan onlyGrant neededGrant share of project
    $42,000 (70%)$0Poverty (health or sanitary project)$210$167$00.0%
    $42,000 (70%)$250,000Poverty (health or sanitary project)$210$227$1,735,0569.6%
    $42,000 (70%)$500,000Poverty (health or sanitary project)$210$286$8,010,75044.2%
    $46,000 (77%)$0Poverty (health or sanitary project)$230$167$00.0%
    $46,000 (77%)$250,000Poverty (health or sanitary project)$230$227$00.0%
    $46,000 (77%)$500,000Poverty (health or sanitary project)$230$286$5,910,30832.6%
    $54,000 (90%)$0Intermediate$540$188$00.0%
    $54,000 (90%)$250,000Intermediate$540$248$00.0%
    $54,000 (90%)$500,000Intermediate$540$308$00.0%

    The engagement record describes loan-only and grant and loan scenarios and the grant needed to hold rates within the affordability threshold. This table shows how that answer depends on two facts this site does not have: the service area's median household income and the debt the sewer system already carries. At 90% of the state non-metro median the threshold is 1.0% of income and no plausible existing debt reaches it. Below 80%, and with a project that corrects a wastewater inadequacy, the threshold falls to 0.5% and the grant ceiling rises to 75%; a system already paying $500,000 a year would then need a grant of $5.9 million to $8.0 million to hold its debt service at the threshold. How existing debt enters the test should be confirmed with the processing office.

    Five-year pro forma

    LineYear 1Year 2Year 3Year 4Year 5
    EDUs (households and business, +0.4% a year, plus the industrial user)4,1844,2084,2334,2574,282
    Base charge per EDU a month (+3% a year)$22.87$23.56$24.27$24.99$25.74
    Volume charge per 1,000 gallons of winter water use (+3% a year)$4.95$5.10$5.25$5.41$5.57
    Revenue: households and business$2,036,532$2,106,018$2,177,876$2,252,185$2,329,029
    Revenue: industrial user, including strength surcharge$364,273$380,027$396,498$413,720$431,728
    Total revenue$2,400,805$2,486,046$2,574,374$2,665,905$2,760,757
    Operation and maintenance (+3% a year)$1,259,000$1,296,770$1,335,673$1,375,743$1,417,016
    Net revenue before reserves and debt$1,141,805$1,189,276$1,238,701$1,290,161$1,343,741
    Short-lived asset reserve$160,000$164,800$169,744$174,836$180,081
    WWD loan installment$788,619$788,619$788,619$788,619$788,619
    Debt reserve deposit (one tenth of an installment)$78,862$78,862$78,862$78,862$78,862
    Surplus$114,324$156,995$201,476$247,844$296,179
    Coverage of the installment, before reserves1.45x1.51x1.57x1.64x1.70x
    Coverage after the short-lived asset reserve1.24x1.30x1.36x1.41x1.48x
    Average monthly residential bill (4,560 gallons billed)$45.74$47.12$48.53$49.99$51.49

    Households and businesses pay a base charge and a volume charge on winter water use, a common way to bill sewer service without charging for lawn watering; the industrial user pays the same charges plus a surcharge on BOD above domestic strength. Year 1 charges are set to collect about 5% more than the full revenue requirement and rise 3% a year. Coverage after the short-lived asset reserve starts at 1.24 times and improves as the base grows.

    Rate design is not neutral. A higher base charge protects the utility against wet years and conservation, because sewer volume billed on winter water use moves with weather and household size; a higher volume charge is easier on small households and single residents. The model splits household and business revenue evenly between the two. A council that wants a lower base charge for affordability can have it, but the study then shows the coverage at a 10% lower billed volume, which in this model falls from 1.24 to about 1.12 times in Year 1 before indexing lifts it back.

    Who pays for the plant

    User groupShare of BOD loadShare of flowShare of revenue
    Households and business72.0%88.7%84.8%
    Industrial user28.0%11.3%15.2%
    MeasureValue
    Industrial user's flow share / BOD share11.3% / 28.0%
    Blended cost-of-service share19.7%
    Revenue at that share, Year 1$472,304
    Revenue the model's rates collect from it$364,273 (15.2%)
    Shortfall carried by households and business$108,030
    BOD above domestic strength, a year159,447 lb
    Strength surcharge: model / cost-of-service$0.45 / $1.13 per lb

    At a surcharge of $0.45 a pound, the industrial user pays 15.2% of revenue while it causes 28.0% of the organic load and 11.3% of the flow. If half the system's costs follow flow and half follow strength, its fair share is 19.7%, and households and businesses carry about $108,000 a year of its cost. A surcharge near $1.13 a pound closes the gap. The allocation method is a policy choice for the council, but USDA's rule points the same way: costs a business would normally bear are not WWD costs (1780.10(a)(5)) [1].

    Residential bill and affordability

    MeasureValue
    Average monthly residential bill$45.74
    Annual bill$549
    Share of assumed MHI of $54,0001.02%
    Debt service per EDU (rule's measure)$188 a year, 0.35% of MHI
    Threshold at which a grant is considered$540 a year (1.0%)
    ItemPer yearPer EDU a month
    Loan installment$788,619$15.71
    Debt reserve$78,862$1.57
    Added O&M$120,000$2.39
    Total$987,481$19.67

    The modeled bill is 1.02% of the assumed income, and the expansion adds about $19.67 a month per EDU. The rule's measure, debt service per EDU, is 0.35% of income, well under the 1.0% threshold.

    Interest rate tier sensitivity

    RateInstallmentPer EDU a yearCoverage after reserve, Year 1Surplus, Year 1
    Poverty rate 2.50%$697,692$1671.41x$214,344
    Intermediate rate 3.25% (model)$788,619$1881.24x$114,324
    Market rate 4.125%$901,396$2151.09x-$9,730
    Market plus one point, 5.125%$1,038,212$2480.95x-$160,228

    The tier matters more here than in a small water upgrade because the loan is larger: the difference between the intermediate and market rates is $112,777 a year, enough to erase the Year 1 surplus. The borrower gets the lower of the rate at approval or closing unless it chooses otherwise (1780.13(a)) [1], so the rate study should show the market-tier case and the increase it would require.

    Industrial user and growth sensitivity

    CaseRevenue, Year 1Coverage after reserve, Year 3Coverage after reserve, Year 5Surplus, Year 5
    Model$2,400,8051.36x1.48x$296,179
    Industrial user leaves in Year 3$2,400,8050.85x0.93x-$135,549
    Industrial user's load halves$2,283,6741.19x1.29x$153,478
    Household and business growth stalls (0% a year)$2,400,8051.33x1.43x$259,284
    Billed winter volume 10% lower$2,298,9791.22x1.33x$179,727

    The industrial user is the largest single risk. If it leaves in Year 3, coverage falls to 0.85 times and the city needs about $195,000 more revenue, a 9.0% increase. Growth stalling barely matters by comparison. The mitigants are contractual: a user agreement with a capacity reservation, a minimum charge for the reserved capacity whether it is used or not, a term that runs with the debt, and a pretreatment requirement the business pays for. Where the business is the primary user and the system depends on it, Part 1780 requires its viability to be assessed [1], which in practice means an independent business study.

    Cost overrun and delay

    CaseAdded costLoanInstallmentDebt and reserve per EDU a monthCoverage after reserve, Year 1
    Model$0$17,514,000$788,619$17.281.24x
    Bids 10% over$1,410,000$18,924,000$852,109$18.671.15x
    Bids 20% over$2,820,000$20,334,000$915,598$20.061.07x
    Twelve-month delay at 4% escalation$620,400$18,134,400$816,555$17.891.20x

    A 20% overrun takes the loan to about $20.3 million, still inside the published tier, and adds $2.78 a month per EDU in debt and reserve. A year's delay costs about $620,000 at 4% escalation, but in this plant the larger cost of delay is regulatory: with load at 97% of design, a year without the expansion is a year of permit risk.

    Combined stress case

    StressSetting
    Construction bids+15%, financed
    Rate tierMarket 4.125%
    Industrial userLeaves in Year 3
    Household and business growth0% a year
    Fixed O&M+5%
    Loan$19,629,000
    Coverage after reserve, Year 1 / Year 3 / Year 50.92x / 0.59x / 0.62x
    Revenue increase needed in Year 3 to cover all costs and reserves23.9%

    Everything going wrong at once, including losing the industrial user, would require a 23.9% revenue increase in Year 3. That is the case that justifies the user agreement: a minimum charge that survives the user's departure turns the worst line in the table into a much smaller one.

    Technical and environmental feasibility

    • The PER designs the plant. Process, sizing, alternatives and cost are the engineer's, reviewed by the State staff engineer (1780.33(c), 1780.55) [1]. The load and capacity analysis supplies the flows, loads and growth cases the PER designs against, and the study adopts the PER's cost.
    • Effluent standards. Discharge facilities must meet federal and state effluent standards (1780.57(h)) [1]. The model leaves room in the aeration basin for nutrient removal so a tighter renewed permit does not force another project.
    • Industrial pretreatment. Pretreatment and other costs a business would normally bear are ineligible (1780.10(a)(5)) [1]; the industrial user agreement should require them.
    • Inflow and infiltration. The model assumes 15% of average flow is inflow and infiltration. Capacity spent treating groundwater is capacity households pay for, so the PER should test collection repairs as an alternative to part of the expansion.
    • Environmental review. The review under 7 CFR part 1970 must be complete before the city commits to a site or process that would narrow the alternatives (1780.57(a)) [1].

    Management and governance feasibility

    The study looks for the capability Part 1780 requires: financial, technical and managerial capacity, and evidence that alternatives of ownership, design and shared services were considered (1780.1(j)) [1]. For a plant expansion that means licensed operators at the level the new process requires, a sewer enterprise fund with audited accrual statements (1780.47), a council with a record of adjusting rates, an industrial pretreatment and surcharge program that is enforced, and a capital plan that carries the short-lived asset reserve. The industrial user agreement is a management document as much as a financial one: the city has to be able to measure the user's flow and strength and bill for it.

    Priority points the feasibility package documents (modeled)

    CriterionPointsSection
    Population 5,501 to 10,000 (Dalhart 8,429 in the 2020 base)01780.17(a)
    Corrects wastewater inadequacies or meets health standards, if the PER documents it251780.17(b)(2)
    Income 80% to 100% of state non-metro median (assumed)151780.17(c)(3)
    Public body51780.17(d)(3)
    Other than RUS funds: city reserves of $600,472 (3.3%)01780.17(d)(4): below 5%
    Modeled total before discretionary points45
    With a state revolving fund or other non-RUS share of 20% to 49%+101780.17(d)(4)
    State program official and National Office pointsup to 15 each1780.17(e), (g)

    Process and documents

    StageWhat happensRule
    Early contact and optional PER reviewEligibility discussion; PER may be submitted early1780.31, 1780.33(c)(1)
    ApplicationSF 424.2, two PER copies, environmental report, credit elsewhere certification1780.33
    Completeness and eligibilityMissing items within 15 federal working days; advice within 45 days of a complete file1780.32
    Public notice and meetingNotice within 60 days of filing; public information meeting unless a vote authorizes the debt1780.19
    Full applicationOperating budget on Form RD 442-7, user agreements, professional service contracts1780.39
    Letter of conditions and obligationIssued when funds are available; sets the rate1780.39(i), 1780.41
    ConstructionInterim financing for loans over $500,000 where available1780.39(d)

    Sources: [1], summarized from this site's national WWD page [9]. The load study needs: three to five years of daily influent flow and BOD and suspended solids data; the discharge permit; billing records by class with winter water use; industrial user permits and sampling; the PER or its draft; audits; existing debt instruments; and any income survey. This site's engagements typically run 4 to 8 weeks from a signed engagement letter, with a 3 to 4 week rush option [12].

    Economic and community impact (modeled)

    MeasureValueBasis
    Residents served8,377Census Vintage 2025 [4]
    Realistic users4,184 EDUs on 3,381 connectionsModel
    Treatment capacity after the project1.8 MGD and 3,800 lb/day BODAlternative B
    Construction spending (construction and contingency)$15,510,000Budget
    On-site job-years (35% labor share at $70,000 loaded, assumed)78Arithmetic, not a multiplier model
    Monthly bill added by the project$19.67 per EDUModel

    The community impact is permit compliance and room to grow. A plant at its organic limit cannot take a new restaurant, hotel or processor without risking its permit, and a city in that position effectively has a moratorium on the kinds of business its highway economy depends on.

    Risks and mitigants

    RiskHow it shows up in the modelMitigant the study tests
    Industrial user leavesCoverage 0.85x in Year 3; 9.0% increase neededCapacity reservation, minimum charge, term with the debt
    Industrial user under-chargedHouseholds carry about $108,000 a yearStrength surcharge near cost of service
    OversizingAlternative C never fills within the loanModest-size test; growth evidence; signed commitments
    UndersizingAlternative A fails in Year 5 in the high caseBase and high cases; phasing
    Interest tierMarket rate erases the Year 1 surplusLower of approval or closing rate; income survey if data look wrong
    Construction cost+20% bids add $2.78 a month per EDUContingency; bid alternates
    Permit tighteningNutrient limits in a renewed permitBasin zones designed for nutrient removal
    Inflow and infiltrationCapacity spent on groundwaterCollection repairs tested as an alternative

    What the five Part 5001 components showed

    WWD direct is governed by part 1780, and the plant design belongs to the PER. This site still organizes the load and capacity work around its five components:

    ComponentWhat the model showsWhat a reviewer still asks
    EconomicA highway service town; city flat, Dallam side growing, Hartley side fallingWhat explains the Hartley-side decline
    Market (users and loads)4,184 EDUs; organic load at 97% of designDaily flow and load records; industrial sampling
    Technical1.8 MGD, 3,800 lb/day expansion covering the high case to Year 25The PER, alternatives and permit outlook
    FinancialDebt service $188 per EDU against a $540 threshold; bill 1.02% of assumed incomeAudits, existing debt, actual income, user agreement
    ManagementOperators, enterprise fund, surcharge programPretreatment enforcement and rate history

    Why wastewater expansion studies are sent back

    • Growth projected from a regional rate that the city's own trend does not support.
    • Flow analyzed and organic load ignored, or the reverse.
    • An industrial user's expansion used to size the plant without a signed commitment from that user.
    • Pretreatment or other business costs included in eligible project costs (1780.10(a)(5)) [1].
    • No assessment of a business the system depends on (1780.7(f)) [1].
    • Rates built on all connections including vacant lots, rather than realistic users (1780.39(c)) [1].
    • A grant assumed before the threshold test shows one.

    Program terms that applied

    TermWWD direct ruleSource
    Rural areaNot in a city or town over 10,0001780.3 [1]
    Rate tiersPoverty (60% of market, not over 5%), intermediate (80% of market, not over 7%), market; quarterly, nearest one-eighth1780.13 [1]
    TermUseful life, state statute or 40 years, whichever is less; principal deferral up to 36 months1780.13(e) [1]
    Grant ceiling75% (low income, health or sanitary project) or 45%1780.10(c) [1]
    Grant thresholdDebt service per EDU above 0.5% or 1.0% of median household income; similar system cost1780.35(b) [1]
    Business usersViability assessed when a business is the primary user; pretreatment ineligible1780.7(f), 1780.10(a)(5) [1]
    ReservesOne average installment, built at one tenth a year; short-lived asset reserves1780.39(e), 1780.35(c) [1]
    Guaranteed alternative (FY2026)90% guarantee, 1.0% fee, no retention fee; $50 million cap91 FR 11272; part 5001 [2][3]

    Lessons for sponsors of similar projects

    1. Measure load, not just flow. In this model the plant fills on BOD years before it fills on gallons.
    2. Size to evidence. The base case supports a smaller plant than the high case; only a signed commitment justifies the difference.
    3. Make the industrial user pay its share. A surcharge at cost of service and a capacity agreement protect households and the loan.
    4. Read the city's geography. A city flat in total can be growing on one side and shrinking on the other.
    5. Run the grant test early. At 4,200 EDUs a grant appears only with low income and existing debt.
    6. Treat delay as permit risk. At 97% of design, waiting costs more than escalation.

    If your city or district is sizing a wastewater expansion for a WWD application and needs a USDA feasibility study consultant for the load, capacity and rate work alongside your engineer's PER, the engagement index describes the process: a fifteen-minute scoping call, a written proposal inside one business day and a firm fixed fee before you sign [11]. Request a proposal for your study [14].

    Data current as of November 2026.

    David Miller, CPA

    USDA Feasibility, Inc.

    Frequently Asked Questions

    Is Dalhart, Texas eligible for USDA Water and Waste Disposal financing?

    On population, yes. Part 1780 treats as rural any area not in a city or town of more than 10,000 people under the latest decennial census, and Dalhart had 8,429 residents in the Census Bureau's April 2020 estimates base and 8,377 in July 2025. The applicant must be a public body, a community-controlled nonprofit or a tribe, must certify it cannot borrow elsewhere on reasonable terms, and must show legal authority and economic feasibility. Dalhart earns no population priority points, so its score rests on health, income and other funds.

    What is a load and capacity analysis in a USDA wastewater application?

    It is the demand side of the plant design. The analysis measures today's flow and organic load by user group, projects them over the design period under low, base and high cases, and shows when the existing plant and each expansion alternative reach planning and construction thresholds. It then prices each alternative into the rate. The engineer's PER designs the plant against those numbers. Part 1780 asks for capacity adequate for reasonable growth but facilities modest in size, and this analysis is how a city shows both.

    Why does organic load matter as much as flow?

    Because a plant has two capacities. Its hydraulic capacity limits the gallons it can pass, and its organic capacity limits the BOD its biology can treat. In this page's model, flow uses 88% of the permit in the peak month while BOD uses 97% of design, mostly because one industrial user sends 28% of the load in 11% of the flow. A study that looks only at gallons would conclude the plant has years of room when it has almost none.

    How does a study decide how big the expansion should be?

    It compares alternatives against projected loads. In the model, a 1.5 MGD option reaches 90% of capacity in Year 20 in the base case but in Year 5 if the industrial user expands; a 1.8 MGD option lasts 39 years in the base case and 25 in the high case; a 2.2 MGD option never fills within the loan. Part 1780's modest-size rule argues against the largest, and the high case justifies the middle option only if the user commits in writing.

    Will a Dalhart wastewater expansion qualify for a USDA grant?

    On the model's assumptions, no. A $17,514,000 loan at an illustrative 3.25% over 40 years costs $788,619 a year, or $188 per EDU, against a threshold of $540 at an assumed $54,000 income. A grant appears only if service-area income is below 80% of the state non-metro median, the project corrects a wastewater inadequacy and the system already carries substantial debt: at $500,000 of existing debt service, the grant needed is $5.9 million to $8.0 million.

    What happens if the industrial user leaves?

    In the model, coverage after reserves falls to 0.85 times in Year 3 and the city needs about $195,000 more revenue, a 9.0% increase. That is why the study recommends a user agreement with a capacity reservation, a minimum charge for reserved capacity, a term that runs with the debt, and pretreatment the business pays for. Where a business is the primary user and the system depends on it, Part 1780 requires an assessment of the business's viability.

    Should the industrial user pay more than households?

    It should pay for what it sends. In the model the user causes 28.0% of organic load and 11.3% of flow but pays 15.2% of revenue at a $0.45 per pound strength surcharge. Allocating half of costs by flow and half by strength gives a fair share of 19.7%, and households carry about $108,000 a year until the surcharge rises to about $1.13 a pound. Part 1780 also excludes pretreatment and other business costs from eligible project costs.

    How much does the expansion add to a residential sewer bill?

    About $19.67 a month per EDU in the model: $15.71 for the loan installment, $1.57 for the debt reserve and $2.39 for added operating costs. The full modeled residential bill is $45.74 a month, 1.02% of the assumed median household income. These are modeled figures for a 4,184-EDU utility at an illustrative intermediate rate, not Dalhart's actual rates.

    Can a state revolving fund loan be combined with a WWD loan?

    Yes. Part 1780 rewards other money in the project: other-than-USDA funds of 5% to 19%, 20% to 49% or 50% or more earn 5, 10 or 15 priority points, and they reduce the WWD loan. In Texas the state revolving fund programs are run by the state's water development board. The feasibility package should carry commitment letters for every other source, because funds that are hoped for do not score and leave a gap if they fail.

    How long does a load and capacity study take, and what does it cost?

    This site's engagements typically run 4 to 8 weeks from a signed engagement letter, with a 3 to 4 week rush option, and every proposal is quoted at a firm fixed fee. The site's WWD article estimates $8,500 to $18,500 or more for a separate feasibility study and $5,000 to $15,000 or more for rate analysis not bundled with the PER. The study goes fastest when the city supplies several years of daily influent data, industrial sampling and billing records at the start.

    Sources

    [1] 7 CFR part 1780, Water and Waste Loans and Grants (CFR 2026 edition, title 7 vol. 12, revised 1 Jan 2026), govinfo; sections 1780.1, 1780.3, 1780.7, 1780.9, 1780.10, 1780.13, 1780.17, 1780.19, 1780.31 to 1780.47, 1780.54 to 1780.57. https://www.govinfo.gov/content/pkg/CFR-2026-title7-vol12/xml/CFR-2026-title7-vol12-part1780.xml (accessed 8 Nov 2026)

    [2] 7 CFR part 5001, OneRD Guaranteed Loans (CFR 2026 edition, title 7 vol. 15, revised 1 Jan 2026), govinfo. https://www.govinfo.gov/content/pkg/CFR-2026-title7-vol15/xml/CFR-2026-title7-vol15-part5001.xml (accessed 8 Nov 2026)

    [3] USDA, OneRD Annual Notice of Guarantee Fee Rates, Periodic Retention Fee Rates, Loan Guarantee Percentage and Fee for Issuance of the Loan Note Guarantee Prior to Construction Completion for Fiscal Year 2026, 91 FR 11272 (9 Mar 2026). https://www.govinfo.gov/content/pkg/FR-2026-03-09/html/2026-04581.htm (accessed 6 Nov 2026)

    [4] U.S. Census Bureau, Vintage 2025 subcounty population estimates (incorporated places and county parts, April 2020 estimates base and July 2025). https://www2.census.gov/programs-surveys/popest/datasets/2020-2025/cities/totals/sub-est2025.csv (accessed 8 Nov 2026)

    [5] U.S. Census Bureau, Vintage 2025 county population estimates and components of change. https://www2.census.gov/programs-surveys/popest/datasets/2020-2025/counties/totals/co-est2025-alldata.csv (accessed 7 Nov 2026)

    [6] OMB metropolitan and micropolitan statistical area delineation file, July 2023. https://www2.census.gov/programs-surveys/metro-micro/geographies/reference-files/2023/delineation-files/list1_2023.xlsx (accessed 7 Nov 2026)

    [7] U.S. Census Bureau, County Business Patterns 2023, county file. https://www2.census.gov/programs-surveys/cbp/datasets/2023/cbp23co.zip (accessed 7 Nov 2026)

    [8] usda-feasibility-study.com, national WWD page, table of states by incorporated places of 10,000 or fewer (Vintage 2025). https://usda-feasibility-study.com/usda-water-waste-disposal-feasibility-study (read 13 Nov 2026)

    [9] usda-feasibility-study.com, USDA Water and Waste Disposal Feasibility Study and PER Support (national page: part 1780 rules, grant tests, priority points, illustrative rates). https://usda-feasibility-study.com/usda-water-waste-disposal-feasibility-study (read 13 Nov 2026)

    [10] usda-feasibility-study.com, Water & Waste Disposal Program: Feasibility Requirements (site article). https://usda-feasibility-study.com/blog/usda-water-waste-feasibility (read 8 Nov 2026)

    [11] usda-feasibility-study.com, Selected USDA Feasibility Study Engagements. https://usda-feasibility-study.com/engagements (read 11 Nov 2026)

    [12] usda-feasibility-study.com, USDA Feasibility Study Cost & Timeline. https://usda-feasibility-study.com/usda-feasibility-study-cost (read 8 Nov 2026)

    [13] usda-feasibility-study.com, USDA Feasibility Studies in Texas (state page: state office in Temple). https://usda-feasibility-study.com/texas (read 11 Nov 2026)

    [14] usda-feasibility-study.com, Contact & Request a Proposal. https://usda-feasibility-study.com/contact (read 8 Nov 2026)

    Data current as of November 2026.

    Ready to Start Your USDA Project?

    Get your free consultation today and take the first step toward securing USDA funding for your rural development project.

    Our USDA feasibility study consultants scope every engagement against the five Part 5001 components in a free consultation.