    Montana's public data on self-storage is thinner than the market itself. Census counts 89 facilities with paid employees, 7.9 per 100,000 residents against 5.5 nationally, but many storage sites run without staff and never enter that count, and SBA records only 8 Montana self-storage 7(a) loans since FY2010. For a USDA self-storage feasibility study in Montana, that scarcity is the central finding: a lender cannot rely on published comparables, so the study must build the market from the ground up, with a site-by-site inventory, rate and occupancy surveys of every competitor, and demand drawn from households, housing growth and rural uses that metro models miss.

    Self-storage in Montana: market evidence

    Montana: self-storage facilities, supply and rural footprint

    MeasureMontanaUnited States
    Establishments, 2019 → 202384 → 89 (+6.0%)16,904 → 18,564
    Per 100,000 residents (2023)7.95.5
    Average employees per establishment2.12.6
    Average annual pay per employee$32,892$40,550
    Share of establishments in non-metro counties22.5% (16 in 2 counties)
    Share of state population in non-metro counties (2025)44.7%

    Non-metro counties with the most self-storage facilities (2023): Flathead County (12); Ravalli County (4).

    Sources: U.S. Census Bureau, County Business Patterns 2019 and 2023 (state and county files; establishments with paid employees; employment and payroll suppressed in some cells); Vintage 2025 county population estimates; OMB metropolitan statistical area delineation, July 2023. Non-metro county is a proxy for USDA rural eligibility, not the eligibility test itself.

    What the thin numbers show. The 89 staffed facilities grew 6.0 percent from 2019 to 2023, under the national 9.8 percent, and average 2.1 employees with pay of $32,892, 18.9 percent below the U.S. $40,550. Payroll per facility is $68,371 against $105,683. Those figures describe small, lightly staffed operations, and they leave out the unstaffed facilities that make up much of rural supply, so the Census count understates competition. A reviewer will therefore ask where the study's supply figures come from. The answer must be a physical inventory: every facility in the trade area, with its unit count, unit mix, climate control, rates and occupancy, found by drive-around, listings and direct calls.

    Where the facilities are

    The county file places 71 of the 89 facilities, and 55 of those are in five metro counties: Yellowstone 18 (1.04 per 10,000 residents), Gallatin 13, Missoula 10, Cascade 9 and Lewis and Clark 5. Only two non-metro counties appear, Flathead with 12 (1.04 per 10,000) and Ravalli with 4. Eighteen facilities are unplaced, and the many unstaffed rural sites are absent altogether. The published data therefore say little about a small-town market, which is exactly where a B&I project would be.

    Regional comparison

    The neighbouring packs below are each state's own figures and are shown for context; none substitutes for a local survey.

    Measure (each state's pack)MontanaWyomingIdahoNorth DakotaSouth Dakota
    Staffed facilities, 202389541662048
    Facilities per 100k residents, 20237.99.28.42.55.2
    Share of placed facilities in counties outside metro areas22.5%65.1%9.2%18.8%20.6%
    Average pay per employee$32,892$29,924$34,926$49,141$40,011
    SBA 7(a) loans, fiscal 2020 to 2026611500
    SBA 504 loans, fiscal 2020 to 20265414315

    Wyoming, with a similar density and a far more rural pattern, is the closest structural match for a small Montana town; Idaho has the deepest SBA record in the region, 15 7(a) loans averaging $1,945,100 and 14 504 loans averaging $915,214 in FY2020 to FY2026. North and South Dakota show how thin staffed supply can be in plains states. None of these figures replaces local rates.

    National benchmarks

    Nationally, 975 self-storage 7(a) loans in FY2020 to FY2026 averaged $1,441,053, and 496 504 loans averaged $1,136,224. The national loss record is the best of any asset on this site: 0.7 percent of 574 FY2010 to FY2016 7(a) loans were charged off, on average 49 months after approval. That record helps the asset class, but it reflects mostly metro and suburban facilities; it does not prove that a rural Montana site will lease up.

    Rural footprint and B&I eligibility in Montana

    On the published data only 22.5 percent of placed facilities are in non-metro counties, against 44.7 percent of the population, 3.1 per 100,000 non-metro residents against 8.7 in metro counties. That gap partly reflects the missing unstaffed sites and partly a real shortage of modern, managed storage in small towns. For B&I, 7 CFR 5001.3 excludes cities over 50,000 and their contiguous urbanized areas: Billings, Missoula, Great Falls and Bozeman. Facilities in their outlying towns, in Helena, Butte-Silver Bow and Kalispell, and in every smaller place can qualify. Because self-storage rents space, sponsors should also confirm with the state office that the operating model is treated as a business rather than passive rental real estate; the site's national self-storage page treats rural facilities as eligible. The Montana state guide explains the parcel check.

    Program fit

    For a storage project in an eligible town, B&I can carry the land, buildings, paving, fencing, gates and security systems, with amortization tied to how long those improvements last. In Montana, SBA has been used almost equally through 7(a) (8 loans) and 504 (7 loans) since FY2010, both averaging close to $2 million recently. Once a facility has run for 12 months, REAP can help with lighting, efficiency or rooftop solar. Community Facilities does not fund commercial storage. A conventional lender may finance a stabilised facility without a guarantee; B&I helps most with new construction and lease-up risk.

    Financing benchmarks: USDA B&I next to SBA

    Montana: SBA lending to self-storage facilities

    Period7(a) loans7(a) dollars504 loans504 dollars
    FY2010 to FY20162$4.6 million1$498,000
    FY2017 to FY20190$01$724,000
    FY2020 to FY20233$4.2 million3$4.6 million
    FY2024 to FY20263$7.1 million2$3.9 million

    Average 7(a) loan, FY2020 to FY2026: $1.9 million. Average 504 loan: $1.7 million. Montana had fewer than 30 seasoned 7(a) loans for self-storage facilities; nationally, 0.7% of 574 FY2010 to FY2016 loans were charged off, on average 49 months after approval.

    Source: SBA 7(a) and 504 FOIA loan data, as of 30 Sep 2026 (project state; disbursed loans only; cancelled and undisbursed loans excluded).

    TermUSDA B&I, fiscal 2026Source
    Guarantee, loans under $5 million85%91 FR 11272
    Guarantee, $5 million to $25 million80%91 FR 11272
    Upfront guarantee fee3.0% of the guaranteed amount91 FR 11272; 7 CFR 5001.454
    Annual retention fee0.55% of the guaranteed share of principal outstanding on December 3191 FR 11272; 7 CFR 5001.455
    Reduced-fee loans (criteria in 5001.454)1.0% fee, 0.50% retention, 80% guarantee91 FR 11272
    Guarantee issued before construction is completeadditional 0.50% fee91 FR 11272; 7 CFR 5001.454
    Maximum loan per borrower$25 million7 CFR 5001.406(c)
    Termuseful life of the collateral, 40 years at most, no balloon7 CFR 5001.402
    Interest ratenegotiated, fixed or variable, no higher than the lender's similar non-guaranteed loans7 CFR 5001.401
    Equity, existing business10% balance sheet equity (or debt to equity of 9:1), or 10% of project cost7 CFR 5001.105(d)(1)
    Equity, new business20% balance sheet equity (or 4:1), or 25% of project cost; 25% (or 3:1) when the guarantee issues before construction is complete7 CFR 5001.105(d)(3), (d)(4)
    Independent feasibility studyrequired above $1,000,000 for a new business; at the Agency's discretion otherwise7 CFR 5001.306(a)(3)
    SBA 7(a), for comparison85% guarantee up to $150,000, 75% above13 CFR 120.210
    SBA 504, for comparisonborrower injection 10%; 15% if new or single purpose; 20% if both13 CFR 120.910

    What it means for a Montana facility. The Montana SBA record is small but shows large loans: six 7(a) loans in FY2020 to FY2026 averaging $1,882,450, 0.62 percent of the U.S. total, and five 504 loans averaging $1,698,200. Neither of Montana's two seasoned 7(a) loans was charged off. A new facility near either average crosses the $1,000,000 line, so a new business borrowing under B&I must provide an independent study, and at these sizes the 85 percent tier applies.

    Worked example (illustrative)

    Montana has fewer than 10 SBA 7(a) self-storage loans, so Loan A uses $1,450,000, rounding the national FY2020 to FY2026 average of $1,441,053, and Loan B uses $1,900,000, rounding Montana's six-loan average of $1,882,450. Both use an illustrative 7.25 percent fixed rate over 25 years.

    Input or resultLoan ALoan B
    Loan amount$1,450,000.00$1,900,000.00
    Guarantee percentage (fiscal 2026 tier)85%85%
    Guaranteed amount$1,232,500.00$1,615,000.00
    Upfront guarantee fee (3.0% of the guaranteed amount)$36,975.00$48,450.00
    Upfront fee if the guarantee issues before construction is complete (+0.50%)$43,137.50$56,525.00
    First annual retention fee (0.55% of the guaranteed share of the balance after 12 payments)$6,678.97$8,751.75
    Interest rate (illustrative, fixed)7.25%7.25%
    Amortization (years, no balloon)2525
    Monthly payment$10,480.70$13,733.33
    Annual debt service (NOI for 1.00x, break-even on debt)$125,768.39$164,799.97
    NOI for 1.25x coverage$157,210.49$205,999.96
    Coverage at that NOI if the rate is 2 points higher1.06x1.06x
    Coverage at that NOI if the term is 5 years shorter1.14x1.14x
    Equity, new business, 25% of total project cost (5001.105(d)(4))$483,333.33$633,333.33
    Total project cost on that basis$1,933,333.33$2,533,333.33
    Equity, new business, 20% balance sheet route if this loan is the only liability$362,500.00$475,000.00
    Equity, existing business, 10% of project cost (5001.105(d)(1))$161,111.11$211,111.11
    Independent feasibility study (5001.306(a)(3))required for a new business (5001.306(a)(3)(i))required for a new business (5001.306(a)(3)(i))

    Per-square-foot test. If Loan A finances an illustrative 55,000 net rentable square feet, 1.25x coverage needs $2.86 of net operating income per rentable square foot per year, about $0.24 a month; Loan B over an illustrative 70,000 square feet needs $2.94 a year, about $0.25 a month. Those are amounts after operating costs and vacancy, so the study converts them into required occupancy at the surveyed street rates for each unit size. Lease-up is the risk: until occupancy stabilises the facility will not reach these figures, so the study needs an absorption schedule and an interest reserve or interest-only period, which 5001.402 permits if full payments begin within three years. Coverage at those figures falls to 1.06x with a rate two points higher and to 1.14x on a 20-year term.

    Evidence the study must build when local comparables are thin

    1. A physical inventory of every storage facility within the trade area, staffed or not, with units, square footage and features.
    2. A rate survey by unit size and climate control, repeated at least twice to capture changes, and occupancy estimates from operators or observed availability.
    3. Demand from households, renters, recent movers and housing construction in the trade area, plus rural demand for vehicle, boat, RV and equipment storage.
    4. An adjustment for farm outbuildings and garages, which the site's national self-storage page notes dampen rural demand, and for wider rural trade areas.
    5. Letters or waiting lists from businesses, contractors or RV owners where demand is specific.
    6. Absorption evidence from facilities that opened in the region, with months to stabilisation.

    What a lender-grade self-storage feasibility study in Montana must prove

    1. Trade-area supply per resident from the physical inventory, compared with the state's 7.9 staffed facilities per 100,000.
    2. Street rates and achievable occupancy by unit size, from the survey.
    3. A lease-up schedule and the reserve that carries debt service until stabilisation.
    4. Construction cost and phasing, with the option to build later phases only when earlier ones fill.
    5. Operating costs including management, insurance, property tax, snow removal and security.
    6. Parcel eligibility under 5001.3 and the state office's view on the operating model.

    Risks and mitigants in Montana

    Hidden supply is the main risk; the mitigant is a full physical inventory. Slow lease-up in a small market can stretch for years, so phasing and reserves matter. New competitors can open quickly because storage is simple to build, so the study checks permits and land listings. Winter snow loads and removal raise costs. Rates may be lower than national benchmarks suggest, given Montana's lower pay levels. Collateral is a single-purpose property; under 5001.203 going-concern value is deducted before discounting, so the as-stabilised value should not carry the loan alone.

    Process, documents and what gets a study returned

    Storage studies reach USDA inside the lender's B&I application, and the Montana Rural Development state office does the review. A self-storage sponsor gathers the site plan, unit mix, construction budget and phasing, zoning approval, any operating history and rent roll, statements for each principal, and guarantees from every 20 percent owner (5001.204). Studies are sent back when supply counts rely on Census or online listings alone, when rates are national averages, or when lease-up is assumed to be immediate.

    Program example

    The Montana inputs name no USDA-financed self-storage facility. The site's Greater Minnesota self-storage case study is linked below and is outside Montana.

    Hiring a USDA self-storage feasibility study consultant in Montana

    Both Montana SBA averages exceed $1,000,000, the point at which 5001.306(a)(3)(i) requires a new storage company's study to come from an independent self-storage feasibility study consultant USDA accepts. The cost page treats self-storage as an asset class with good comparable data in metro areas; in rural Montana, the survey work above can move a study toward the complex band of $10,500 to $14,500 and 7 to 9 weeks, from the standard $6,900 to $12,500 and 6 to 7 weeks. Deliverables are the inventory and rate survey, a lease-up and operating model with rate and absorption stresses, technical, management and economic chapters, and the report and spreadsheet, with one revision. Appraisals and engineering are separate. Because Census misses unstaffed sites, ask any USDA feasibility study consultant whether its rate survey will cover every facility in the trade area.

    Open a request on the contact page with the facility's town, program, cost range and lender status; the page says a senior analyst replies within one business day.

    Last updated 2026-11-08

    David Miller, CPA

    USDA Feasibility, Inc.

    Frequently Asked Questions

    Does USDA require a feasibility study for a self-storage facility in Montana?

    For a new business borrowing more than $1,000,000 under B&I, 7 CFR 5001.306(a)(3)(i) requires one from an independent consultant the Agency accepts. Montana's SBA self-storage 7(a) loans averaged $1,882,450 in FY2020 to FY2026 and its 504 loans $1,698,200, so a new facility usually crosses the line. Smaller loans and existing operators are at the Agency's discretion.

    What does a self-storage feasibility study consultant cost in Montana?

    On the site's cost page a storage study costs $6,900 to $12,500 in the standard band and $10,500 to $14,500 when comparable data are limited. Because Montana's published data miss many unstaffed facilities, rural studies often need a full drive-around inventory and rate survey, which can place them in the complex band. The fee is fixed in the proposal.

    How long does a Montana self-storage study take?

    Plan on six to seven weeks for a standard storage study and seven to nine for a complex one, per the cost page. A Montana study's timing depends mostly on the rate survey: facilities that do not publish rates must be called or visited, and a second survey round adds time but strengthens the case.

    Who can prepare it?

    A qualified, independent consultant acceptable to USDA (5001.306(a)(3)(i)), with no interest in the land, construction, management contract or loan. A builder's or management company's market report is useful input, not the study. For storage the decisive test of the author is whether it surveyed every competing facility, staffed or not, rather than relying on listings; the state office judges that when it reviews the file.

    How long is a self-storage study valid?

    No validity period is set by Part 5001. The site's cost page puts USDA's typical data limit at 18 months, and appraisals older than a year are rejected under 5001.203. Because storage can be built quickly, a new competitor or a rate change in the trade area is reason to update the survey before closing.

    Can the same self-storage study serve SBA and USDA?

    Yes, if it names both lenders and keeps one projection. Under 13 CFR 120.160(b) SBA may require one. Montana storage projects have used SBA 7(a) and 504 almost equally, 8 and 7 loans since FY2010, so sponsors often compare 504 with B&I. SBA 504's borrower injection of 10 to 20 percent (13 CFR 120.910) compares with B&I's 20 percent balance sheet or 25 percent of cost test for a new business.

    Why does Census undercount self-storage in Montana?

    County Business Patterns counts only establishments with paid employees, and many rural storage facilities run without staff. The published 89 facilities, 55 of the placed ones in metro counties, therefore understate supply in small towns. A lender-grade study counts every facility in the trade area directly. Flathead and Ravalli are the only non-metro counties in the published data.

    Is self-storage eligible for B&I as a business rather than rental real estate?

    The site's national self-storage page treats rural self-storage as eligible, and the operator controls the services offered, which distinguishes it from a building leased to a tenant. Part 5001 does exclude property used mainly for commercial rental when the owner controls neither tenants nor services, so confirm the operating model with the state office before scoping.

    How long does lease-up take in a small Montana town?

    There is no published Montana figure, which is why the study must find comparable openings in the region and measure their months to stabilisation. The worked example needs $2.86 of net operating income per rentable square foot a year at 1.25x on Loan A; the study shows when occupancy reaches that level and what reserve covers the gap.

    Sources

    1. U.S. Census Bureau, County Business Patterns 2019 and 2023, state and county files: https://www2.census.gov/programs-surveys/cbp/datasets/
    2. U.S. Census Bureau, Vintage 2025 population estimates (state, county and incorporated places): https://www2.census.gov/programs-surveys/popest/datasets/2020-2025/
    3. Office of Management and Budget, metropolitan and micropolitan delineation, July 2023: https://www2.census.gov/programs-surveys/metro-micro/geographies/reference-files/2023/delineation-files/list1_2023.xlsx
    4. U.S. Small Business Administration, 7(a) and 504 FOIA loan data, as of 30 Sep 2026: https://data.sba.gov/dataset/7-a-504-foia
    5. 7 CFR Part 5001, OneRD Guaranteed Loanmaking and Servicing, CFR 2026 edition (govinfo): https://www.govinfo.gov/content/pkg/CFR-2026-title7-vol15/xml/CFR-2026-title7-vol15-part5001.xml
    6. 91 FR 11272, OneRD annual notice of guarantee fee rates, retention fee rates and guarantee percentages for FY2026 (govinfo): https://www.govinfo.gov/content/pkg/FR-2026-03-09/html/2026-04581.htm
    7. 90 FR 57351, OneRD guaranteed loan regulation technical amendments, December 11, 2025 (govinfo): https://www.govinfo.gov/content/pkg/FR-2025-12-11/html/2025-22567.htm
    8. 13 CFR Part 120, SBA business loan programs: https://www.ecfr.gov/current/title-13/chapter-I/part-120
    9. Site pages: /self-storage-feasibility-study-usda, /usda-feasibility-study-cost, /contact

    Data current as of November 2026.

    Ready to Start Your USDA Project?

    Get your free consultation today and take the first step toward securing USDA funding for your rural development project.

    Our USDA feasibility study consultants scope every engagement against the five Part 5001 components in a free consultation.

    Get Your Free Consultation

    Fill out the form below and we'll contact you within 24 hours to discuss your project.

    We'll respond within 24 hours