Cold-storage roof-mount solar feasibility: Georgia USDA Feasibility Study Case Study

    Last updated 2026-11-08

    How to read this case study. The engagement summary reflects the published record. Client names, actual costs, loan terms and proprietary data are confidential, so the project budget, market sizing and financial projections below are a modeled example built from public data for this project type and location. They show the analysis a lender-grade study performs, not the client's figures.

    Data current as of November 2026.

    Engagement summary

    This engagement assessed a roof-mounted solar array on a cold-storage operation in Tifton, Georgia. It was prepared in 2023 for a CDFI lender, and its defining feature was right-sizing: the array was documented against the facility's own consumption. The rules have since changed. USDA rescinded the FY2025 to FY2027 REAP funding notice in April 2026 [2], and a new REAP rule took effect on 16 October 2026 [1]. This page describes the engagement type and models a south Georgia cold store and its rooftop array. It then shows how such a project is financed now and what a study must prove under the rule in force.

    ItemPublished record
    ProgramUSDA Rural Energy for America Program (REAP)
    Asset classCold storage
    ProjectRoof-mount solar on a cold-storage facility
    LocationTifton, Georgia (Tift County)
    RegionSoutheast
    Loan size tierUnder $5M
    Year prepared2023
    Lender typeCDFI lender
    OutcomePrepared with right-sized system documentation

    Sources: the site's engagement index [12]; county from Census place files [6].

    The record describes the method:

    • sizing with NREL's PVWatts approach at about 5.2 peak sun-hours a day for south and central Georgia;
    • array size held to the facility's historical consumption;
    • battery storage screened;
    • rural-area eligibility checked against the USDA map;
    • the operator's small-business status checked under SBA size standards (13 CFR 121).

    The record also lists the grant cap and cost-share terms of the program at the time. Those terms were superseded by the rescission and the 2026 rule, and none of them is used here.

    The question the lender and USDA needed answered

    A cold store is close to an ideal solar host on paper. Refrigeration runs day and night, summer loads peak when the sun is strongest, and the roof is large, flat and unshaded. The study's job is to turn that intuition into numbers a credit officer can sign, and to answer four questions.

    1. How big should the array be? Size it to the roof, and to the share of output the building will use itself rather than export at a low credit. The record's "right-sized" outcome is this question answered.
    2. What is a kilowatt-hour worth to this facility? On a commercial demand tariff, solar mostly avoids energy charges. It trims demand charges only when the array is producing at the moment of the monthly peak. A study that values every kilowatt-hour at the average bill rate overstates savings.
    3. Can the roof carry it? Insulated cold-storage roofs, attachment methods and remaining roof life decide whether the project is buildable without damaging the envelope that keeps the product cold.
    4. Who repays the loan? As with most solar on an operating business, the savings alone will not cover the debt service. The warehouse's cash flow does.

    Under 7 CFR part 5001, a REAP guaranteed loan for a renewable energy system needs a technical report, and a feasibility study when the lender or the Agency deems one necessary [3]. Since 16 October 2026, a REAP grant for a renewable system needs a resource assessment, or a feasibility study in its place, and projects of $200,000 or more need two years of pro forma statements and an engineer's completion certificate [1]. The new rule also makes the payback calculation an eligibility test: a project whose simple payback exceeds its useful life cannot receive a grant [1].

    What changed for this engagement type on 16 October 2026

    TopicRule effective 16 October 2026 [1]What it means for cold-storage solar
    TimingProject Period must end 12 to 24 months before the grant application (12 to 36 months in the first window)The loan builds the array; a grant can follow a year of metered output
    Data12 months of actual production plus 12 months of pre-installation dataInterval data before and after installation becomes the evidence
    Award sizeAt most 25% of cost and $500,000 for a renewable systemOn a $1.07 million project the 25% limit binds first
    Combined fundingGrant plus REAP guaranteed loan at most 75% of project costA 75% loan leaves no room for a later grant
    Loan aloneA REAP guaranteed loan without a grant is capped at 75% of eligible costs, with at least 25% from the borrower (7 CFR 5001.406(d))The operator funds a quarter even without a grant [3]
    CroplandGround-mount solar or wind on Cropland is ineligible for a grantThe roof is the right place; a field array next door would not qualify
    SizingGround-mount systems must show commensurate historical energy use; storage limited to 120% of prior annual useRoof arrays escape the clause, not the economics
    Foreign componentsSolar systems with any component from a foreign adversary under 15 CFR 791.4 are ineligibleCountry-of-origin list for modules, inverters, racking
    ExclusionsStand-alone storage, storage retrofits, EV chargers and retail energy dispensingBatteries only as part of the original system, if at all
    EconomicsSimple payback must not exceed useful lifeThe thin margin on cost and tariff becomes an eligibility risk
    GamblingAny gambling income bars a grant; the loan keeps the 15% test in 5001.127(b)A revenue screen of the operator and affiliates

    Project description (modelled)

    The modelled facility is an existing 60,000-square-foot cooler and freezer warehouse near Tifton, serving south Georgia's agricultural and food distribution trade. It uses a modelled 2,100,000 kWh a year, an average load of about 240 kW that never falls far because the compressors run around the clock. The roof can take about 488 kW of modules once setbacks, rooftop units and access paths are deducted.

    The project is a 400 kW (DC) rooftop array on ballasted or low-penetration racking engineered for the insulated roof, with string inverters, a production meter and monitoring. The timeline runs: interval-data analysis and design in the first quarter, structural review and interconnection application in parallel, installation over about five months, then permission to operate from the utility. Battery storage was screened and left out of the base case, for reasons set out below.

    Facility and solar inputs

    Facility input (model)ValueHow a real study sets it
    Building60,000 sq ft cooler and freezer warehouseSite plan and lease
    Annual electricity use2,100,000 kWh (35 kWh per sq ft)Twelve months or more of bills and interval data
    Average load240 kWInterval data; refrigeration runs around the clock
    Roof area usable for modules65% of the roofRoof survey: setbacks, units, skylights
    Module density12.5 W per sq ft of usable roofLayout drawing
    Largest roof array488 kW DCComputed
    Peak sun-hours5.2Figure cited in the engagement record for south and central Georgia
    Performance ratio0.77Assumption; heat losses on a hot roof
    Year-1 output per kW DC1,461 kWhComputed
    Avoided energy value / export credit$0.085 / $0.035 per kWhAssumption; the tariff and export rider set them
    Demand-charge reduction10% of AC capacity at $14 per kW-monthAssumption; interval data shows coincident peaks
    Installed cost$2.30 per watt DC plus $80,000 fixed, plus 5% contingencyInstaller bids; range $1.90 to $3.10
    O&M and inverter reserve$24 per kW a yearO&M contract; inverter warranty
    Degradation / useful life0.5% a year / 25 yearsModule warranty

    Right-sizing the array

    Array (DC)Year-1 output (kWh)Share of annual loadAssumed share used on siteInstalled cost (model)Year-1 valueSimple paybackFits the roof?Payback within 25 years?
    250 kW365,36517%98%$687,750$34,19120.1 yearsYesYes
    400 kW584,58428%92%$1,050,000$52,95119.8 yearsYesYes
    480 kW701,50133%87%$1,243,200$61,78820.1 yearsYesYes
    600 kW876,87642%78%$1,639,312$73,28922.4 yearsNo: needs a carport or ground arrayYes

    Payback is almost flat between 250 kW and the full roof, so size is decided by fit, not by marginal economics. The 400 kW array produces 584,584 kWh in year one, 28% of the facility's use. The model assumes 92% of that output is used on site, with exports mainly on cool weekend middays when refrigeration load dips. Filling the roof at 480 kW adds output but pushes more of it into the export credit. Going to 600 kW means a carport structure, at a modelled premium of $0.90 a watt above roof cost, and lengthens payback to 22.4 years. A ground array on adjacent farmland would be ineligible for a grant if the land is Cropland [1]. "Right-sized" in the record means this trade-off was documented against the facility's own consumption, which is still the discipline a reviewer expects.

    Monthly match of output and load

    MonthFacility use (kWh, model)Solar output (kWh, model)Solar as share of use
    Jan151,20035,07523%
    Feb142,80039,75228%
    Mar159,60051,44332%
    Apr168,00057,28934%
    May184,80061,38133%
    Jun197,40059,62830%
    Jul205,80060,21229%
    Aug205,80057,87428%
    Sep189,00051,44327%
    Oct172,20046,76727%
    Nov159,60034,49022%
    Dec163,80029,22918%

    The monthly profile shows why cold storage suits solar. Facility use peaks in July and August, when output is high, and solar covers a fairly steady 27% to 34% of use from February to October. Winter months fall to 18% to 23%. A real study replaces these shapes with 15-minute interval data and an hourly production model, then counts exports hour by hour rather than assuming a share.

    Project cost and sources and uses (modelled)

    No construction-cost database sits behind these figures. Each line is a labelled assumption with a range, and a real study replaces it with installer bids, the structural engineer's letter and the utility's interconnection estimate.

    Line itemModel amountRangeSource in a real study
    Modules, inverters, racking and installation (400 kW DC at $2.30 per watt)$920,000$760,000 to $1,240,000Installer bids
    Roof structural assessment, attachment design and any reinforcement$35,000$15,000 to $120,000Structural engineer
    Interconnection application, utility study and metering$25,000$10,000 to $60,000Utility interconnection agreement
    Design engineering, production model and permits$15,000$8,000 to $25,000Engineer proposal
    Monitoring system$5,000$3,000 to $10,000Vendor quote
    Contingency (5% of hard cost)$50,0005% to 10%Lender and engineer judgment
    Feasibility study (within the cost page band for REAP loans above $600,000)$9,500$7,500 to $11,500Fixed-fee proposal
    Loan closing and legal$7,500$5,000 to $12,000Lender estimate
    Total eligible project cost (model)$1,067,000
    Cost outside the eligible budgetModel amountNote
    REAP guarantee fee, 1.0% of the guaranteed portion (Structure A)$6,402FY2026 REAP rate [4]
    Extra 0.50% if the guarantee issues before construction is complete$3,201Only if the lender asks for it [4]
    Interest during a five-month installation (half drawn on average)$11,670From operating cash
    Annual retention fee, year 1 (0.25% of guaranteed principal)$1,600Usually passed to the borrower [4]
    Roof replacement, if the roof has less life left than the arrayNot modelledA roof is not a REAP cost; replace first or move the array

    The engagement record cites Georgia commercial solar installation costs of $3.06 to $3.52 a watt in 2025. We have not verified that range, and it likely reflects smaller systems. The model uses $2.30 for a 400 kW roof array and tests the record's range in the sensitivity tables, where it decides the grant question.

    Two ways to finance it

    UsesAmountStructure A: REAP loan onlyAmountStructure B: smaller loan, later grantAmount
    Solar installation and site costs$1,050,000REAP guaranteed loan from the CDFI (75%)$800,200REAP guaranteed loan$533,500
    Feasibility study$9,500Owner contribution (25%)$266,800Owner cash at construction$533,500
    Closing and legal$7,500REAP grant$0REAP grant applied for 12 to 24 months after completion$266,700
    Owner cash returned if the grant is awarded-$266,700
    Total eligible project cost$1,067,000Total$1,067,000Total net of grant, if awarded$1,067,000
    Grant test (rule effective 16 October 2026)ModelSource
    25% of project cost$266,750[1]
    Renewable system maximum$500,000[1]
    Largest possible grant$266,750Lower of the two
    Grant plus loan cap (75% of project cost)$800,250[1]
    Grant room left if the loan is at 75% (Structure A)$0[1]
    Structure B: loan and grant$533,500 + $266,700 = 75.0%[1][3]
    Earliest application12 to 24 months after the Project Period ends, with 12 months of production data[1]
    CompetitionOne national competition for requests over $20,000, in an annual window[1]

    Structure A borrows the full 75% and plans no grant. Structure B borrows 50% and asks the operator for $533,500 at construction. It returns $266,700 only if a national, competitive grant is awarded at least a year after completion. The new rule runs one national competition for requests over $20,000 [1], and as of 7 November 2026 no funding notice under the rule had appeared. The CDFI should underwrite Structure B on its own debt service and test whether the operator can carry the bridge.

    Market analysis

    For a behind-the-meter array, the market is the facility's own demand for electricity and the tariff that prices it. The market section also confirms that the host business, the refrigerated warehouse, will be there to use the power for the life of the loan. That makes the cold-storage market part of the solar study.

    The site and the rural test

    MeasureValueSource
    Tifton city population, April 2020 estimates base17,031Census Vintage 2025 subcounty estimates [6]
    Tifton city population, July 2025 estimate17,595[6]
    Tift County population, July 2025 estimate42,254Census Vintage 2025 county estimates [6]
    Tift County OMB status (2023)Non-metropolitanOMB list1_2023 [7]
    Georgia counties that are non-metropolitan85 of 159[7]
    Georgia places above 50,000 in the April 2020 base20[6]
    Nearest of those to TiftonAlbany (69,653); Valdosta (55,393)[6]
    Tift County manufacturing establishments with payroll, 202338 (1,690 employees)County Business Patterns 2023 [5]
    Of which food manufacturing8 (106 employees)[5]

    Tifton is far below the 50,000-person line in 7 CFR 5001.3. The nearest places above it in the Census file are Albany (69,653) and Valdosta (55,393), each a separate city with its own urbanized area. Tift County is one of Georgia's 85 non-metropolitan counties out of 159. The Georgia hub lists Tifton among the south Georgia towns that screen as eligible [13]. The rural test uses the latest decennial census, so the study cites the 2020 Census count and attaches a dated USDA eligibility map determination for the parcel. The estimates base above is a proxy for that count.

    Cold storage in Georgia and the Southeast

    Georgia: refrigerated warehousing, supply and rural footprint

    MeasureGeorgiaUnited States
    Establishments, 2019 → 202358 → 72 (+24.1%)1,350 → 1,367
    Per 100,000 residents (2023)0.70.4
    Average employees per establishment93.248.4
    Average annual pay per employee$57,904$56,901
    Share of establishments in non-metro counties0.0% (0 in 0 counties)
    Share of state population in non-metro counties (2025)16.6%

    Sources: U.S. Census Bureau, County Business Patterns 2019 and 2023 (state and county files; establishments with paid employees; employment and payroll suppressed in some cells); Vintage 2025 county population estimates; OMB metropolitan statistical area delineation, July 2023. Non-metro county is a proxy for USDA rural eligibility, not the eligibility test itself.

    StateRefrigerated warehouses 20192023ChangePer 100,000 residentsEmployees 2023Employees per siteAverage pay
    Georgia587224.1%0.656,71293.2$57,904
    Florida8274-9.8%0.325,11969.2$49,380
    North Carolina3221-34.4%0.1981238.7$53,828
    Alabama2120-4.8%0.3960430.2$55,118
    South Carolina1613-18.8%0.2433325.6$65,186

    County Business Patterns 2019 and 2023, NAICS 493120; per-resident figures use Census Vintage 2025 state estimates for July 2023 [5][6].

    Georgia added 14 refrigerated warehouses between 2019 and 2023 while every neighbour in the table lost sites. Its warehouses are large, averaging 93.2 employees against 48.4 nationally. Yet the county file places none of them in a non-metro county. A cold store in Tift County is therefore a rural exception in a metro-centred industry. That cuts both ways for the study. Competition for the same customers is thin locally, but the operator's market depends on agricultural and distribution flows the study must document with customer contracts and throughput history. Tift County's 38 manufacturers, 8 of them food manufacturers employing 106 people, are part of that local demand. Georgia's average refrigerated-warehouse wage of $57,904 is the benchmark for the operator's labour costs.

    REAP activity in Georgia and its neighbours

    StateREAP grantsREAP grant dollarsAverage grantDollars per residentRank: dollars / per resident (of 53)REAP guaranteed loansB&I guaranteed loans
    Georgia221$36,934,061$167,122$3.459 / 30013
    Florida67$19,015,422$283,812$0.8820 / 49124
    Alabama61$14,847,758$243,406$2.9626 / 3309
    South Carolina51$16,936,060$332,080$3.3122 / 31710
    North Carolina102$21,671,880$212,469$2.0815 / 371233

    USAspending prime awards by place of performance, FY2024 to FY2026, for REAP (10.868) and B&I (10.768); dollars per resident use the population figures in the USAspending data [9]. These awards were made under the pre-2026 rules.

    Georgia took 221 REAP grants worth $36,934,061 in three years, ninth among 53 states and territories by dollars. It recorded no REAP guaranteed loans. South Carolina (7) and North Carolina (12) used the loan program; Georgia did not. Under the 2026 rule the guaranteed loan becomes the construction money for solar, so a Georgia operator and its lender may be less familiar with it than with the grant. The Georgia hub reports that a cold-storage operator in the state has used REAP for a solar array [13], so the project type has precedent.

    Solar and cold-storage financing benchmarks

    Georgia: solar and other renewable power generation, supply and rural footprint

    MeasureGeorgiaUnited States
    Establishments, 2019 → 20236 → 26 (+333.3%)405 → 942
    Per 100,000 residents (2023)0.20.3
    Average employees per establishment2.812.3
    Average annual pay per employee$213,230$138,631
    Share of establishments in non-metro counties62.5% (5 in 1 counties)
    Share of state population in non-metro counties (2025)16.6%

    Non-metro counties with the most solar and other renewable power generation (2023): Jeff Davis County (5).

    Sources: U.S. Census Bureau, County Business Patterns 2019 and 2023 (state and county files; establishments with paid employees; employment and payroll suppressed in some cells); Vintage 2025 county population estimates; OMB metropolitan statistical area delineation, July 2023. Non-metro county is a proxy for USDA rural eligibility, not the eligibility test itself.

    Georgia: SBA lending to solar and other renewable power generation

    Period7(a) loans7(a) dollars504 loans504 dollars
    FY2010 to FY20160$00$0
    FY2017 to FY20191$350,0000$0
    FY2020 to FY20234$6.2 million0$0
    FY2024 to FY20260$00$0

    Average 7(a) loan, FY2020 to FY2026: $1.6 million. Georgia had fewer than 30 seasoned 7(a) loans for solar and other renewable power generation; nationally, 12.9% of 31 FY2010 to FY2016 loans were charged off, on average 51 months after approval.

    Source: SBA 7(a) and 504 FOIA loan data, as of 30 Sep 2026 (project state; disbursed loans only; cancelled and undisbursed loans excluded).

    Georgia's generation establishments are project companies and developers, not hosts like this warehouse. The SBA record is thin, and nationally 12.9% of seasoned solar 7(a) loans were charged off. The cold-storage pack records no SBA 7(a) or 504 loans to Georgia refrigerated warehouses from FY2010 to FY2026 [8]. The lesson for the CDFI is that neither benchmark describes a rooftop array on an operating cold store. The credit rests on the warehouse, and the study should present it that way.

    Tariff and price evidence the study must source

    The model's avoided energy value ($0.085 a kWh), export credit ($0.035) and demand-charge reduction are labelled assumptions. The engagement record cites several Georgia electricity figures that we have not verified:

    • commercial rates up 18% from 2020 to 2024, to 14.14 cents a kWh;
    • a further increase of about 3.5% in January 2025;
    • a Plant Vogtle Unit 4 surcharge;
    • an export buyback of about 7.2 cents a kWh.

    The average commercial price is not the value of a solar kWh to a large refrigerated load on a demand tariff, which is why the model uses a lower energy-only figure and tests the record's numbers as sensitivities. The Georgia hub notes that the state's electric membership corporations serve most of its land area [13]. Whether this parcel is served by an investor-owned utility or an EMC sets the tariff, the export terms and the interconnection process, and the study names it.

    Financial feasibility

    Five-year pro forma at project level

    Line (Structure A)Year 1Year 2Year 3Year 4Year 5
    Energy charges avoided and export credits (tariff +2.5% a year, 0.5% degradation)$47,351$48,252$49,170$50,107$51,063
    Demand-charge reduction$5,600$5,740$5,884$6,031$6,181
    Total energy value$52,951$53,992$55,054$56,138$57,244
    O&M and inverter reserve-$9,600-$9,600-$9,600-$9,600-$9,600
    Insurance increment-$3,150-$3,150-$3,150-$3,150-$3,150
    Property tax increment (placeholder)-$2,500-$2,500-$2,500-$2,500-$2,500
    Net project benefit (project NOI)$37,701$38,742$39,804$40,888$41,994
    REAP loan debt service (7.00%, 20 years)-$74,447-$74,447-$74,447-$74,447-$74,447
    Retention fee-$1,600-$1,562-$1,522-$1,478-$1,431
    Project-level coverage0.50x0.51x0.52x0.54x0.55x

    The array does not pay its own debt service on the model: 0.50 times coverage in year one, rising to 0.55 times by year five as tariffs escalate. That is the normal result for commercial rooftop solar financed over 20 years at 7.00% with no tax credit and no grant at construction. The study says so directly and moves the credit question to the warehouse.

    Global coverage: the warehouse carries the loan

    YearWarehouse cash flow before project (model)Project NOICash availableExisting debt service (model)New REAP debt service and feeCoverage beforeGlobal coverage after
    Year 1$1,100,000$37,701$1,137,701$720,000$76,0481.53x1.43x
    Year 2$1,100,000$38,742$1,138,742$720,000$76,0101.53x1.43x
    Year 3$1,100,000$39,804$1,139,804$720,000$75,9691.53x1.43x
    Year 4$1,100,000$40,888$1,140,888$720,000$75,9251.53x1.43x
    Year 5$1,100,000$41,994$1,141,994$720,000$75,8781.53x1.43x

    The warehouse's cash flow and existing debt service are modelled placeholders, since they are the operator's confidential figures. The method follows Part 5001's global credit evaluation [3]. Adding the REAP loan takes modelled coverage from 1.53 times to 1.43 times, and the solar savings recover a little each year.

    Term choice

    Term at 7.00%Annual debt serviceProject-level coverage, year 1Global coverage, year 1Useful-life check (5001.402)
    15 years$86,3090.43x1.41xWithin module life
    20 years$74,4470.50x1.43xWithin module life
    25 years$67,8680.54x1.44xEqual to module life: no margin

    A 25-year term would match the module warranty exactly and leave nothing for a shorter-than-expected life. Twenty years keeps a five-year margin and costs only 0.01 times of global coverage against the longer term. Under 5001.402 the term must stay within useful life with no balloon [3], and inverters, which wear out sooner than modules, need a funded replacement reserve, which the pro forma carries.

    Payback: the grant eligibility test

    Payback testValueSource
    Total project cost used in the test (installed cost)$1,050,000Budget; study and closing excluded as non-system costs (confirm)
    Year-1 dollar value of energy produced$52,951Energy, export and demand value
    Simple payback19.8 yearsCost / annual value [3]
    Including study and closing costs20.2 yearsConservative reading
    Useful life assumed25 yearsModule warranty
    Passes the grant eligibility test?Yes, with a thin marginPayback must not exceed useful life [1]

    Part 5001 defines simple payback as total project cost divided by the annual dollar value of energy produced or saved, excluding one-time benefits and tax credits [3]. On the model the array passes with about five years to spare. The margin is the issue. The break-even and cost tables below show how little it takes to lose it.

    Break-even and stress tests

    Break-even test (year 1)ValueModel baseMargin
    Avoided energy value for project-level 1.00x$0.156 per kWh$0.08584%
    Avoided energy value at which payback equals the 25-year life$0.065 per kWh$0.085-24%
    Output at which payback equals 25 years77% of modelled output100%-23%
    Installed cost at which payback equals 25 years$2.95 per watt$2.3028%
    Warehouse cash flow for global 1.00x$758,346$1,100,000-31%
    Warehouse cash flow for global 1.25x$957,358$1,100,000-13%

    Coverage break-even is out of reach at the project level: the avoided value would need to reach $0.156 a kWh. The payback test is closer to the edge in the other direction. A 24% lower avoided value, 23% less output or a 28% higher installed cost each push payback past 25 years and disqualify the array from a grant, though not from the loan.

    Installed cost per watt (400 kW)Installed costSimple paybackPasses the grant payback test?REAP loan at 75%Owner shareGlobal coverage, year 1
    $1.90$882,00016.7 yearsYes$674,200$224,8001.45x
    $2.30$1,050,00019.8 yearsYes$800,200$266,8001.43x
    $2.70$1,218,00023.0 yearsYes$926,200$308,8001.41x
    $3.06 (record-cited 2025 range)$1,369,20025.9 yearsNo$1,039,600$346,6001.39x
    $3.52 (record-cited 2025 range)$1,562,40029.5 yearsNo$1,184,600$394,8001.37x

    This table is the main finding of the modelled study. At the record's cited 2025 installed costs of $3.06 to $3.52 a watt, a 400 kW array would pay back in 25.9 to 29.5 years and fail the 2026 grant test. The lender's case would survive, with global coverage of 1.37 to 1.39 times, but the grant would be lost. Competitive installer bids are therefore an eligibility matter, not just a cost matter.

    Avoided energy value per kWhOutput 10% below modelOutput as modelledOutput 5% above
    $0.0650.31x; payback 27.2 yrs0.35x; payback 24.9 yrs0.38x; payback 23.9 yrs
    $0.0750.37x; payback 24.2 yrs0.43x; payback 22.1 yrs0.45x; payback 21.1 yrs
    $0.0850.43x; payback 21.8 yrs0.50x; payback 19.8 yrs0.53x; payback 19.0 yrs
    $0.1000.53x; payback 18.9 yrs0.60x; payback 17.2 yrs0.64x; payback 16.5 yrs
    $0.1414 (record-cited commercial average)0.79x; payback 13.9 yrs0.89x; payback 12.6 yrs0.95x; payback 12.0 yrs

    If the facility's true avoided value is nearer the record's average commercial price of 14.14 cents, payback falls to 12.6 years and project coverage rises to 0.89 times. The study cannot assume that. It shows the tariff arithmetic line by line from interval data.

    Export credit per kWh400 kW (base)480 kW (full roof)600 kW (roof plus carport)
    $0.025$52,484; payback 20.0 yrs$60,876; payback 20.4 yrs$71,360; payback 23.0 yrs
    $0.035$52,951; payback 19.8 yrs$61,788; payback 20.1 yrs$73,289; payback 22.4 yrs
    $0.072$54,682; payback 19.2 yrs$65,162; payback 19.1 yrs$80,427; payback 20.4 yrs

    The export credit barely matters at 400 kW, because 92% of output is used on site. It matters more as the array grows, which is the economic reason to size to the load.

    Fixed rate (20 years)Budget as modelledOverrun 10%Overrun 20%
    6.00%$70,395; owner $266,800; global 1.44x$77,442; owner $293,400; global 1.43x$84,479; owner $320,100; global 1.41x
    7.00%$76,048; owner $266,800; global 1.43x$83,660; owner $293,400; global 1.42x$91,263; owner $320,100; global 1.40x
    8.00%$81,919; owner $266,800; global 1.42x$90,119; owner $293,400; global 1.40x$98,309; owner $320,100; global 1.39x
    9.00%$87,996; owner $266,800; global 1.41x$96,804; owner $293,400; global 1.39x$105,601; owner $320,100; global 1.38x
    Delay caseBase year 1Permission to operate six months late
    Months of output in year 1126
    Project NOI, year 1$37,701$18,851
    Debt service and fee$76,048$76,048
    Global coverage1.43x1.41x
    REAP grant clockStarts at the end of the Project PeriodStarts six months later; 12 months of data still needed

    A late permission to operate costs half a year of savings, but global coverage barely moves (1.41 times) because the warehouse carries the debt. The bigger cost of delay falls on Structure B. The grant clock starts only when the Project Period ends, and twelve months of data are still needed, so a late interconnection pushes any grant back by at least as long.

    Equity and loan-size tests

    TestRequirementModel result (Structure A)Source
    REAP guaranteed loan sizeAt least $5,000 and at most 75% of eligible project costs$800,200 = 75.0% of $1,067,0007 CFR 5001.406(d) [3]
    Borrower contributionAt least 25% of eligible project costs, with or without a grant$266,800 = 25.0%5001.406(d) [3]
    REAP loans to one borrowerAt most $25 million$800,2005001.406(d)(1) [3]
    Grant plus loanAt most 75% of Project CostStructure B: $800,200 = 75.0%4280.122(b)(20) [1]
    Equity certificationLender certifies at closing against a closing balance sheetPro forma closing balance sheet in the study5001.306(a)(2) [3]

    The operator's 25% can come from cash or from documented contributions to eligible cost. For a CDFI, the closing balance sheet and the global coverage table are the two documents that carry the credit memo.

    Technical and environmental feasibility

    • Roof. Cold-storage roofs are insulated assemblies over a vapour barrier, and a poorly detailed penetration can let in moisture that freezes inside the panel. The study needs a structural engineer's letter on dead load, wind uplift and the attachment method, and the roofer's confirmation that the roof warranty survives. It also needs the roof's remaining life. If the roof will need replacing within the array's life, replace it first, because removing and reinstalling an array costs more than the roof work.
    • Electrical. Interconnection at the facility's service, protection settings, and the utility's study and upgrade costs. The production meter must support the 12 months of data a grant application needs [1].
    • Equipment. Commercially available modules and inverters with a country-of-origin record for every component [1]. The installer must be licensed in Georgia with at least three similar installations, and procurement must follow 2 CFR 200.318 to 200.327 for a grant [1].
    • Fire and access. Rooftop pathways and setbacks required by the fire code reduce usable roof area. The model's 65% usable-roof assumption stands in for the layout drawing.
    • Storage. The record says battery storage was analysed. Under the 2026 rule, storage must be part of an eligible system and is limited to 120% of prior annual use. Stand-alone storage and storage retrofits are excluded [1]. A battery's value here would come from cutting demand charges and riding through outages, which matter to a freezer. The modelled base case leaves it out until interval data show demand peaks a battery could reliably shave.
    • Environmental. A roof array on an existing building disturbs no ground. REAP grants carry environmental review requirements [1], and the study places them in the schedule.

    Management and governance feasibility

    The study confirms who owns the building and the roof, and whether the operator leases them. REAP requires site ownership or a lease of at least 12 months before the Project Period [1], and a lease must outlast the loan or include the array. It names who monitors production and acts on alarms, who holds the O&M contract, and who keeps the interval data a grant application will need. It screens the operator and affiliates under 5001.127: federal judgments, delinquent federal debt and debarment for the loan, and for a grant also the 2026 rule's bar on any gambling income [3][1]. The record notes that the operator was confirmed as a small business under SBA size standards (13 CFR 121), which the 2026 rule uses for rural small business applicants [1]. Finally, the study notes how a CDFI lender fits the REAP guarantee, since the lender files the application and evaluates the study and technical report in writing [3].

    Economic and community impact (modelled)

    Measure (modelled)ValueBasis
    Electricity generated on site, year 1584,584 kWh400 kW at 1,461 kWh per kW
    Share of facility use28%Of 2,100,000 kWh
    Energy cost avoided, year 1$52,951Pro forma
    Peak installation labourRegional electrical and roofing crews for about five monthsSchedule
    Permanent jobs addedNone claimedThe project protects an existing employer's cost base

    The community case is a lower, more stable energy cost for a rural employer whose product spoils without power. REAP's 2026 scoring rewards energy per award dollar, the share of energy replaced and environmental benefits [1], and the modelled output above is the evidence base for those points if a grant is sought later.

    Risks and mitigants

    RiskEffectMitigant the study documents
    Installed cost at the record's cited 2025 rangePayback exceeds 25 years; grant lostCompetitive bids; cost sensitivity; size to the roof
    Avoided value lower than modelledThinner payback marginTariff analysis from interval data; rate sensitivity
    Roof failure or leakProduct loss, removal costStructural letter, roofer sign-off, roof life check
    Interconnection delay or upgrade costLost output, later grant clockEarly application; utility study in the budget
    Foreign-adversary componentGrant ineligibleCountry-of-origin list before purchase
    Grant not awardedBridge not repaidStructure A as base case
    Warehouse throughput fallsGlobal coverage weakensCustomer contracts, throughput history, global sensitivity
    Lease shorter than the loanArray strandedLease extension or landlord consent before closing
    Battery added laterStorage retrofit excluded from a grantDecide on storage at design
    Gambling income in an affiliateGrant barScreen all entities

    What the five Part 5001 components showed

    Component [10]What it tests hereWhat the modelled study shows
    EconomicResource, tariff, contracts and cost against benefit$52,951 a year of value on a $1,050,000 system; payback 19.8 years
    MarketWhether the energy has a use and the host will last92% of output used on site; a cold store in a non-metro county with thin local competition
    TechnicalRoof, equipment, installer, interconnection400 kW fits the usable roof; roof and interconnection letters required
    FinancialRepayment source, equity, sensitivityProject coverage 0.50x; global 1.43x; owner 25%
    ManagementSite control, O&M, monitoring, reportingLease and roof control documented; data kept for a later grant

    Why studies like this are returned

    • Savings valued at the average bill rate, not the tariff's energy and demand components.
    • An array sized to roof area or to an aspirational load, with exports valued at retail.
    • No structural letter, or no plan for a roof with less life left than the array.
    • Production at nameplate, or a generic regional yield with no heat losses.
    • Debt service shown as covered by the solar savings, or by a grant not yet awarded.
    • A loan above 75% of eligible cost, or a grant planned on top of a 75% loan.
    • No country-of-origin record.
    • Battery storage added after the fact, which the 2026 rule excludes from a grant.

    Program terms that applied

    TermREAP guaranteed loan (FY2026)B&I guaranteed loan under $5 million (FY2026)Source
    Guarantee80%85%91 FR 11272 [4]
    Upfront guarantee fee1.0% of the guaranteed portion3.0%[4]
    Annual retention fee0.25% of guaranteed principal outstanding0.55%[4]
    Extra fee if the guarantee issues before construction is complete0.50%0.50%[4]
    Loan size$5,000 to 75% of eligible project costs; $25 million per borrowerUp to $25 million per borrower5001.406(c), (d) [3]
    Borrower moneyAt least 25% of eligible project costs10% (existing business) to 25% (new business with construction)5001.406(d); 5001.105(d) [3]
    TermUseful life, at most 40 years, no balloonSame5001.402 [3]
    RateNegotiated; fixed, variable or bothSame5001.401 [3]
    Rural testOutside cities over 50,000 and their contiguous urbanized areas (latest decennial census)Same5001.3 [3]
    Gambling screenMore than 15% of gross revenue from gambling bars the loanSame5001.127(b) [3]
    Feasibility studyWhen the lender or Agency deems it necessary; technical report requiredRequired over $1,000,000 to a new business5001.306(a)(3), 5001.307 [3]

    These FY2026 rates apply to loans obligated in FY2026 unless a later appropriation changes them [4]. The 2026 CFR still lists solar and other renewable energy systems as B&I uses where REAP cannot finance them or REAP funds are unavailable (5001.105(b)(21)) [3]. A USDA press release of 19 August 2025 announced a policy on solar on farmland, so ask the Rural Development state office in Athens before planning a B&I guarantee for a solar project. A REAP guaranteed loan, which has no cropland restriction in part 5001 [3], is the natural route for a rooftop array.

    Lessons for sponsors of similar projects

    1. Size to the load and the roof, not to ambition. On a cold store the economics are flat across sensible sizes, and oversizing only adds exports and structure.
    2. Price the kilowatt-hour from the tariff. Energy charges, demand charges and export credits each need their own line. The average bill rate overstates the value.
    3. Get bids before you plan a grant. At the record's cited 2025 installed costs, the modelled array fails the 25-year payback test. A competitive bid can be the difference between eligible and ineligible.
    4. Fix the roof first. A roof with less life left than the array is the most expensive mistake on a cold store.
    5. Plan for 25% of your own money. The REAP loan stops at 75% of eligible cost, and a grant cannot be stacked on a 75% loan.
    6. Underwrite without the grant. It arrives, if at all, a year or more after completion through a national competition.
    7. Decide on storage at design. A battery added later is a storage retrofit, which the 2026 rule excludes from a grant.
    8. Bring the warehouse's numbers. The lender's decision rests on the operator's global cash flow, so give the analyst financial statements, debt schedules and customer contracts at kickoff.

    The site's cost page lists REAP studies at $4,900 to $8,500 and 4 to 5 weeks for a loan under $600,000, and $7,500 to $11,500 and 5 to 7 weeks above it, each as a firm fixed fee in a written proposal [11]. For a cold-storage, packing or processing operator planning rooftop solar in Georgia or elsewhere, an independent USDA feasibility study consultant can build the sizing, tariff and credit case together.

    Request a scoped proposal for your REAP solar feasibility study at the contact page.

    David Miller, CPA

    USDA Feasibility, Inc.

    Frequently Asked Questions

    Can a cold-storage warehouse finance rooftop solar with REAP after October 2026?

    Yes. A REAP guaranteed loan under 7 CFR part 5001 can finance up to 75% of eligible project costs, with at least 25% from the borrower, and carries an 80% guarantee in FY2026. A REAP grant of up to 25% of cost and $500,000 can follow only after the array has run for at least a year and the operator can show 12 months of production and 12 months of pre-installation data. A rooftop array avoids the new bar on ground-mount solar on cropland.

    How should a solar array on a cold store be sized?

    To the facility's measured load and the usable roof. Cold stores run refrigeration around the clock, so most output is used on site up to a point, and beyond that it is exported at a low credit. In the modelled case, a 400 kW array produces 28% of annual use with 92% consumed on site and pays back in 19.8 years. A 600 kW system would need a carport and pay back in 22.4 years.

    Will the solar savings cover the loan payments?

    Usually not on their own. In the model, net savings of about $37,700 a year cover only half of the $76,048 of debt service and retention fee on a 20-year loan at 7.00%. The lender therefore underwrites the warehouse's global cash flow, as Part 5001's credit evaluation requires. Modelled global coverage falls from 1.53 times to 1.43 times with the new loan. A study that shows the savings covering the debt is likely to be sent back.

    What simple payback does REAP require?

    Under the rule effective 16 October 2026, simple payback must not exceed the system's useful life for a grant. Part 5001 defines payback as total project cost divided by the annual dollar value of energy produced, excluding one-time benefits and tax credits. The modelled array passes at 19.8 years against a 25-year life. At the record's cited 2025 installed costs of $3.06 to $3.52 a watt it would fail, at 25.9 to 29.5 years.

    Can I add battery storage to a REAP solar project?

    Only as part of the original eligible system, and within limits. The 2026 rule caps storage at 120% of prior annual energy use and excludes stand-alone storage and storage retrofits from grants. A battery on a cold store could cut demand charges and protect product during outages, but its value depends on interval data showing peaks it can reliably shave. Decide at design: a battery added after the array is built is a retrofit.

    Can a CDFI make a REAP guaranteed loan?

    The published record lists a CDFI lender for this engagement. REAP guaranteed loans are made by lenders that meet the Part 5001 lender requirements, which file the application and evaluate the study and technical report in writing. A CDFI should confirm its standing to request a REAP guarantee with the Rural Development state office. Under the FY2026 notice the guarantee is 80%, with a 1.0% upfront fee and a 0.25% annual retention fee on the guaranteed portion.

    Is Tifton, Georgia a rural area for USDA?

    On the data here, yes. Tifton had 17,031 residents in the Census April 2020 estimates base, far below the 50,000 limit in 7 CFR 5001.3. Tift County is non-metropolitan under OMB's 2023 delineation, and the nearest larger cities, Albany and Valdosta, are separate places. The Georgia hub lists Tifton among the eligible south Georgia towns. The test uses the latest decennial census and the USDA eligibility map, so attach a dated determination for the parcel.

    Do I need a feasibility study for a REAP solar loan?

    A REAP guaranteed loan for a renewable energy system requires a technical report, and a feasibility study when the lender or Agency deems one necessary. Lenders often ask for one when the savings do not cover the debt and the credit depends on the host business. For a grant, a feasibility study can replace the resource assessment. This site's cost page lists REAP studies at $4,900 to $11,500 depending on loan size, as a firm fixed fee.

    What happens if my roof needs replacing during the array's life?

    Plan for it before installation. Removing and reinstalling an array to replace a roof costs far more than doing the roof first, and a cold-storage roof is an insulated assembly where poorly detailed penetrations can let in moisture that freezes inside the panels. The study should include a structural letter on load and attachment, the roofer's view of the warranty and the roof's remaining life. A roof replacement is not a REAP cost, so budget it separately.

    How long does a REAP solar feasibility study take?

    The site's cost page lists 4 to 5 weeks for REAP studies under a $600,000 loan and 5 to 7 weeks above it, with a rush option at a premium. Most of the time goes into the interval data, the tariff analysis, the roof and interconnection evidence and the operator's financial statements, so having those ready at kickoff shortens the schedule. Under the 2026 rule, any grant application comes later, after a year of metered production.

    Sources

    [1] USDA RBCS, Unleashing American Energy and Economic Prosperity; Rural Energy for America Program (REAP), final rule with comment period, 91 FR 62600 (1 Oct 2026), effective 16 Oct 2026; sections 4280.106, 4280.120, 4280.122, 4280.125, 4280.131, 4280.140. https://www.govinfo.gov/content/pkg/FR-2026-10-01/html/2026-20178.htm (accessed 7 Nov 2026)

    [2] USDA RBCS, Notice of Rescission of Funding Opportunity for the Rural Energy for America Program, 91 FR 20090 (15 Apr 2026). https://www.govinfo.gov/content/pkg/FR-2026-04-15/html/2026-07332.htm (accessed 7 Nov 2026)

    [3] 7 CFR part 5001, OneRD Guaranteed Loans (CFR 2026 edition, title 7 vol. 15, revised 1 Jan 2026), sections 5001.3, 5001.105, 5001.106, 5001.127, 5001.202, 5001.306, 5001.307, 5001.401, 5001.402, 5001.406, 5001.454, 5001.455. https://www.govinfo.gov/content/pkg/CFR-2026-title7-vol15/xml/CFR-2026-title7-vol15-part5001.xml (accessed 8 Nov 2026)

    [4] USDA, OneRD Annual Notice of Guarantee Fee Rates, Periodic Retention Fee Rates, Loan Guarantee Percentage and Fee for Issuance of the Loan Note Guarantee Prior to Construction Completion for Fiscal Year 2026, 91 FR 11272 (9 Mar 2026). https://www.govinfo.gov/content/pkg/FR-2026-03-09/html/2026-04581.htm (accessed 6 Nov 2026)

    [5] U.S. Census Bureau, County Business Patterns 2019 and 2023, state and county files. https://www2.census.gov/programs-surveys/cbp/datasets/ (accessed 7 Nov 2026)

    [6] U.S. Census Bureau, Vintage 2025 population estimates, state, county and subcounty totals. https://www2.census.gov/programs-surveys/popest/datasets/2020-2025/ (accessed 8 Nov 2026)

    [7] OMB metropolitan and micropolitan statistical area delineation file, July 2023 (list1_2023). https://www2.census.gov/programs-surveys/metro-micro/geographies/reference-files/2023/delineation-files/list1_2023.xlsx (accessed 7 Nov 2026)

    [8] U.S. Small Business Administration, 7(a) and 504 FOIA loan data, as of 30 Sep 2026. https://data.sba.gov/dataset/7-a-504-foia (accessed 7 Nov 2026)

    [9] USAspending.gov, award counts and amounts by place of performance for Assistance Listings 10.768 (B&I) and 10.868 (REAP), 1 Oct 2023 to 30 Sep 2026, API v2. https://api.usaspending.gov/api/v2/search/spending_by_award_count/ (accessed 7 Nov 2026)

    [10] OneRD Guaranteed Loan Regulation, 85 FR 42494 (14 Jul 2020), appendix A to subpart D of part 5001, Elements of an Acceptable Feasibility Study. https://www.govinfo.gov/content/pkg/FR-2020-07-14/pdf/2020-13991.pdf (accessed 7 Nov 2026)

    [11] usda-feasibility-study.com, USDA Feasibility Study Cost & Timeline (site page). https://usda-feasibility-study.com/usda-feasibility-study-cost (read 7 Nov 2026)

    [12] usda-feasibility-study.com, USDA Feasibility Study Engagements (published engagement record). https://usda-feasibility-study.com/engagements (read 11 Nov 2026)

    [13] usda-feasibility-study.com, USDA Feasibility Study Consultant in Georgia (state hub). https://usda-feasibility-study.com/georgia (read 13 Nov 2026)

    Ready to Start Your USDA Project?

    Get your free consultation today and take the first step toward securing USDA funding for your rural development project.

    Our USDA feasibility study consultants scope every engagement against the five Part 5001 components in a free consultation.