USDA Feasibility Study for Solar and Renewable Energy (REAP) in Minnesota

    NAICS 221114

    Minnesota is one of the country's heaviest users of USDA's Rural Energy for America Program (REAP). USAspending shows 544 REAP grants in Minnesota from FY2024 to FY2026, and the hub reports that in February 2024 USDA announced $53.8 million for 495 Minnesota REAP projects, more than any other state. Yet Census counts only nine solar and other renewable generation businesses in the state, six of them solar with nine employees between them (computed), because the arrays REAP pays for belong to farms, wineries, grocers and manufacturers counted in their own industries. The rule effective 16 October 2026 changed how that money flows: a REAP grant now follows 12 months of operation, is capped at 25% of cost and $500,000, and can no longer finance construction. A Minnesota solar feasibility study now mostly supports the loan that builds the system.

    Data current as of November 2026.

    The REAP rule effective 16 October 2026, applied to a Minnesota project

    USDA published the final rule with comment period on 1 October 2026 (91 FR 62600), effective 16 October 2026, after rescinding the FY2025 to FY2027 funding notice in April 2026 (91 FR 20090). Its main terms, all from the rule text as summarised on the site's national renewable energy page:

    TopicRule effective 16 October 2026What it means for a Minnesota solar study
    TimingProject Period ends 12 to 24 months before the application (12 to 36 in the first window)Build first, apply for the grant later
    Data12 months of actual production and 12 months of pre-installation dataThe study's production estimate is later checked against meter data
    Award size$1,500 minimum; $500,000 maximum for renewable systems, $250,000 for efficiencyLarge arrays get a smaller share
    Cost shareAt least 75% of project cost from other sourcesGrant at most 25%
    Combined fundingGrant plus REAP guaranteed loan at most 75% of costCaps the loan if a grant is planned
    CroplandGround-mount solar on Cropland (7 CFR 718.2) ineligible; no retrofits of such systemsSite screening comes first on farms
    Foreign componentsSystems with any component from a foreign adversary under 15 CFR 791.4 ineligible (except installed before publication)Country-of-origin list for every component
    SizingGround-mount systems must match historical energy use; storage at most 120% of prior annual useLoad analysis is required
    EconomicsSimple payback may not exceed useful lifePayback is an eligibility test
    ExclusionsEV chargers, retail energy dispensing, stand-alone storage, storage retrofits, distribution-only projects; one location per applicationScope these out
    Applicant and installerOne application per federal fiscal year per highest-level owner group; site held 12 months before the Project Period; installer licensed with three similar installationsOwnership and installer evidence
    CompetitionNo state competitions: one for requests of $20,000 or less, one national for the restMinnesota projects compete nationally

    As of 7 November 2026 no new REAP funding notice under the rule had appeared in the Federal Register. A lender should therefore underwrite a Minnesota project without the grant and treat any award as a later prepayment or reserve.

    Program fit and when a study is required

    The REAP guaranteed loan finances the up-front cost: up to 75% of eligible costs and $25 million per borrower, with an FY2026 guarantee of 80%, a 1.0% fee and 0.25% retention (91 FR 11272; national page). The national page notes that a REAP loan needs a technical report and a feasibility study when the lender or Agency deems one necessary, and that a REAP grant needs a resource assessment or a study in its place. B&I's compulsory study applies to new businesses borrowing more than $1,000,000 (7 CFR 5001.306(a)(3)(i)), but the hub states that since a USDA letter of 19 August 2025 wind and solar projects are ineligible for B&I in Minnesota; this page follows the hub and treats B&I as unavailable for stand-alone solar until the lender confirms otherwise. The hub also points to Minnesota's statewide Commercial PACE program as an alternative for energy work. A conventional bank loan is the other comparison, and Community Facilities can fund renewable systems only where they serve an essential community facility, as the national page notes. SBA 7(a) has made eight loans to Minnesota generation businesses since FY2010. The hub reports a USDA pause on guarantees for biodigester projects through 31 December 2026.

    Borrowers and owners above 20% must clear the federal tax, debt, judgment and debarment screen in 7 CFR 5001.127(a), and the hub reports that the new REAP rule disqualifies applicants with any gambling income.

    Solar and renewable generation in Minnesota: market evidence

    Minnesota: solar and other renewable power generation, supply and rural footprint

    MeasureMinnesotaUnited States
    Establishments, 2019 → 20238 → 9 (+12.5%)405 → 942
    Per 100,000 residents (2023)0.20.3
    Average employees per establishment9.212.3
    Average annual pay per employee$132,735$138,631
    Share of establishments in non-metro counties0.0% (0 in 0 counties)
    Share of state population in non-metro counties (2025)21.9%

    Sources: U.S. Census Bureau, County Business Patterns 2019 and 2023 (state and county files; establishments with paid employees; employment and payroll suppressed in some cells); Vintage 2025 county population estimates; OMB metropolitan statistical area delineation, July 2023. Non-metro county is a proxy for USDA rural eligibility, not the eligibility test itself.

    Computed: Minnesota renewable generation businesses by type, 2019 and 2023 (Census CBP state files)

    Type (NAICS)Establishments 2019 → 2023Employees 2019 → 2023Average pay 2023
    Solar electric power generation (221114)8 → 6111 → 9$125,778
    Biomass electric power generation (221117)n/a → 3n/a → 74$133,581

    Minnesota: SBA lending to solar and other renewable power generation

    Period7(a) loans7(a) dollars504 loans504 dollars
    FY2010 to FY20160$00$0
    FY2017 to FY20191$280,0000$0
    FY2020 to FY20236$4.1 million0$0
    FY2024 to FY20261$300,0000$0

    Average 7(a) loan, FY2020 to FY2026: $621,743. Minnesota had fewer than 30 seasoned 7(a) loans for solar and other renewable power generation; nationally, 12.9% of 31 FY2010 to FY2016 loans were charged off, on average 51 months after approval.

    Source: SBA 7(a) and 504 FOIA loan data, as of 30 Sep 2026 (project state; disbursed loans only; cancelled and undisbursed loans excluded).

    The Census figures say almost nothing about REAP demand, and that is the finding. Solar generation businesses fell from eight to six between 2019 and 2023 and their employment from 111 to 9; the apparent growth to nine establishments comes from three biomass plants with 74 employees (computed). The county file places four establishments in one metro county, so the pack's 0.0% non-metro share reflects the file, not the location of Minnesota's solar. SBA's eight 7(a) loans, averaging $621,743 in FY2020 to FY2026, financed generation businesses, not the farm and business arrays that REAP funds.

    A lender reviewing a Minnesota REAP project therefore cannot benchmark it against local generation firms. The evidence must come from the host business: its utility bills, load profile, roof or site, and the production estimate for the specific array.

    Regional comparables (other states' figures, labelled)

    Computed: solar and renewable generation businesses in Minnesota, Wisconsin and Iowa (each state's pack and pack JSON)

    MeasureMinnesotaWisconsinIowa
    Establishments, 2019 → 20238 → 94 → 50 → 7
    Per 100,000 residents (2023)0.20.10.2
    Average employees per establishment9.28.421.1
    Average annual pay per employee$132,735$128,000$152,784
    Establishments placed in the county file / non-metro among them4 / 00 / 00 / 0
    SBA 7(a) loans, FY2010 to FY2026832
    SBA 504 loans, FY2010 to FY2026000
    SBA 7(a) and 504 loans, FY2020 to FY2026 (count; average)7; $621,7433; $426,6671; $302,700

    The neighbours show the same thinness: Wisconsin has five generation businesses and three SBA loans averaging $426,667, Iowa seven businesses and one loan. On the site's national renewable page, Iowa leads REAP grant awards in FY2024 to FY2026 with 586 and Minnesota follows with 544, so REAP activity, not generation businesses, is where the region's solar lending happens.

    National benchmarks

    Nationally, 942 solar and other renewable generation establishments had paid employees in 2023, up from 405 in 2019, and SBA approved 138 7(a) loans averaging $478,591 and 17 504 loans averaging $638,588 in FY2020 to FY2026 (computed from the pack). The national seasoned 7(a) loss rate is high: 12.9% of 31 loans approved in FY2010 to FY2016 were charged off, on average 51 months after approval. The national renewable page also reports 6,722 REAP grant awards across the states in FY2024 to FY2026.

    Evidence the study must build

    • Load and bills. Twelve months or more of utility bills and interval data, and 12 months of pre-installation data for the grant application.
    • Production estimate. Array design, orientation, shading and expected output, with degradation, ready to be reconciled against 12 months of meter data.
    • Tariff and interconnection. The utility's rate schedule and interconnection terms, which set the value of each kilowatt-hour (Minnesota utility specifics are not in the inputs).
    • Site screening. Roof structure or ground site, and confirmation that a ground mount is not on Cropland under 7 CFR 718.2.
    • Components. Country of origin for each major component under 15 CFR 791.4.
    • Installer. State licence and at least three similar installations; procurement under 2 CFR 200.318 to 200.327.

    Rural footprint and eligibility in Minnesota

    For REAP guaranteed loans, the rural definition in 7 CFR 5001.3 applies, as it does to B&I: the site must lie outside any city of more than 50,000 residents in the 2020 census and its attached urbanized area, and eligibility cannot be granted subject to later compliance. Farm sites almost always pass; rural small businesses in regional centres need the usual check against Rochester, St. Cloud, Duluth and the Twin Cities urbanized area. Agricultural producers have their own REAP eligibility rules, which are not restated here. The hub's named Minnesota awards are in Spring Valley (Fillmore County), St. Charles (Winona County) and Stewartville (Olmsted County). See the Minnesota USDA page.

    Worked example (illustrative)

    Inputs. An installed project cost of $1,000,000, chosen for illustration because Minnesota has fewer than ten SBA loans in this code and the REAP structure, not SBA, governs. Column one assumes no grant; column two assumes a 25% grant ($250,000) will be awarded after 12 months of operation, which limits the REAP guaranteed loan so that grant plus loan stay within 75% of cost. FY2026 REAP guarantee terms apply (80%, 1.0% fee, 0.25% retention). The rate is an assumed 7.0% fixed over 20 years with monthly payments; neither the rate nor the useful life has been quoted by a lender or engineer.

    Computed: REAP guaranteed loan with and without a later grant (Python, exact to the cent)

    LineNo grant plannedGrant of 25% expected later
    Installed project cost (illustrative)$1,000,000.00$1,000,000.00
    REAP grant, at most 25% of cost and $500,000$0.00$250,000.00
    REAP guaranteed loan (grant plus loan at most 75% of cost)$750,000.00$500,000.00
    Owner cash and other funds$250,000.00$250,000.00
    Guaranteed amount (REAP FY2026: 80%)$600,000.00$400,000.00
    Upfront guarantee fee (1.0%)$6,000.00$4,000.00
    Retention fee on the balance after 12 payments (0.25%)$1,464.32$976.21
    Annual debt service (7.0%, 20 years, illustrative)$69,776.90$46,517.94
    Energy savings plus sales needed for 1.25x$87,221.13$58,147.42
    Simple payback if savings equal that 1.25x figure11.47 years17.20 years
    Coverage if production is 15% below the estimate1.06x1.06x
    Coverage at a rate 2 points higher1.08x1.08x

    Without a grant, the business borrows $750,000 and needs $87,221.13 a year of energy savings and sales for 1.25x, a simple payback of 11.47 years on the full cost. If a grant is planned, the loan falls to $500,000 and the required savings to $58,147.42, but the owner must fund the $250,000 grant portion until the award arrives a year or more later, and the payback on those lower savings, 17.20 years, must still be shorter than the system's useful life. Production 15% below estimate takes coverage to 1.06x in both cases. For a Minnesota project the practical lesson is to size the loan on the no-grant case.

    What a lender-grade solar feasibility study in Minnesota must prove

    1. The site and applicant are eligible, including the Cropland and single-location tests.
    2. Historical energy use that justifies the system size, and storage within 120% of prior use.
    3. A production estimate with design basis, ready for reconciliation with meter data.
    4. Tariff and interconnection terms and the resulting annual savings and sales.
    5. Simple payback shorter than useful life, with the useful life evidenced.
    6. Component origins and installer qualifications under the new rule.
    7. Debt service coverage on the REAP loan without the grant, and the bridge for any grant expected later.
    8. Stress cases for production, tariff changes and rates.

    Hiring a USDA solar feasibility study consultant in Minnesota

    Under the new rule, a Minnesota solar study usually supports a REAP guaranteed loan or a bank loan, with the grant application following once the system has a year of data. The USDA feasibility study consultant should be independent of the installer, the equipment supplier and the lender, and able to reconcile engineering estimates with utility data.

    The cost page prices REAP work in two tiers: $4,900 to $8,500 over four to five weeks where the REAP loan is under $600,000, and $7,500 to $11,500 over five to seven weeks for a guaranteed loan above $600,000 with full projections and coverage analysis. Grant application drafting and engineering are not included. Bring 12 months or more of utility bills, the installer's proposal and design, component origin details, site or roof information, ownership documents and the lender's terms, then request a REAP study proposal; the contact page says a senior analyst replies within one business day.

    Minnesota REAP precedents (as listed on the hub)

    • Four Daughters Winery, Spring Valley (Fillmore County): $167,500 (2024) for a 207 kilowatt solar array.
    • Miller's Market, St. Charles (Winona County): $64,000 for a 50 kilowatt array.
    • Mark and Karen Goldberg, Stewartville (Olmsted County): nearly $78,000 (2024) for a farm wind turbine.

    All were awarded under the rules before 16 October 2026. Under the current rule, comparable projects would apply after a year of operation, and their grants would be capped at 25% of cost.

    Last updated 2026-11-08

    David Miller, CPA

    USDA Feasibility, Inc.

    Frequently Asked Questions

    Do I need a feasibility study for a REAP solar project in Minnesota?

    It depends on the financing. A REAP guaranteed loan needs a technical report and a feasibility study when the lender or Agency deems one necessary, and a REAP grant needs a resource assessment or a study in its place, according to the site's national renewable page. Under the rule effective 16 October 2026 the grant comes after 12 months of operation, so the study mainly supports the construction loan.

    What does a solar energy feasibility study consultant cost for a Minnesota REAP project?

    The site's cost page lists $4,900 to $8,500 for a REAP study where the loan is under $600,000, and $7,500 to $11,500 where a REAP guaranteed loan exceeds $600,000 and needs full projections. The fee is fixed before signing. Engineering design and grant application drafting are separate. Most farm and small-business arrays fit the lower tier.

    How long does a Minnesota REAP solar study take?

    Four to five weeks for a smaller REAP scope and five to seven for a guaranteed loan above $600,000, from the engagement letter, on the cost page's schedule. Collecting a full year of utility bills and the installer's design is usually the slowest step, so gather them before signing. Rush delivery, where offered, costs 20% to 35% more.

    Who can prepare a solar study for USDA?

    A consultant the Agency accepts as qualified, independent of the installer, the equipment supplier and the lender. Installers prepare production estimates and designs, which are inputs; the study must test them against the site's load data and the utility tariff, and must show payback and coverage independently. Knowing the new REAP data and component rules is part of the job.

    How long does a Minnesota solar study stay valid?

    No expiry is set in Part 5001, but under the new rule the study's production estimate will be compared with 12 months of actual meter data before any grant. Tariff or interconnection changes, or a change of installer or components, should trigger an update. Appraisals used for a loan must be under a year old (5001.203).

    Can a Minnesota solar project get a B&I guarantee?

    The Minnesota hub says no: since a USDA letter of 19 August 2025, wind and solar projects are ineligible for B&I. The site's national renewable page describes B&I as available for renewable systems not otherwise eligible under REAP. Until the lender confirms the current position with the state office, plan on REAP guaranteed loans, bank loans or Commercial PACE.

    How does the 25% grant cap change a Minnesota project budget?

    Grants now cover at most 25% of cost and $500,000 for renewable systems, and grant plus REAP loan may not exceed 75% of cost. On a $1,000,000 project, a planned $250,000 grant limits the REAP loan to $500,000, and the owner funds the grant share until it is paid. Projects that relied on the old larger share need a new capital plan.

    Can farm solar in Minnesota still use REAP?

    Yes, with new limits. Ground-mount solar on Cropland under 7 CFR 718.2 is ineligible, ground-mount systems must match historical energy use, and components from foreign adversaries are barred. Roof-mounted arrays and ground mounts on non-cropland can still qualify. Farms should also check the one-application-per-year limit for owner groups. A site plan showing land use is the first document a reviewer will ask for.

    Sources

    1. USDA RBCS, Rural Energy for America Program final rule with comment period, 91 FR 62600 (1 Oct 2026): https://www.govinfo.gov/content/pkg/FR-2026-10-01/html/2026-20178.htm
    2. USDA RBCS, Notice of Rescission of Funding Opportunity for REAP, 91 FR 20090 (15 Apr 2026): https://www.govinfo.gov/content/pkg/FR-2026-04-15/html/2026-07332.htm
    3. U.S. Census Bureau, County Business Patterns 2019 and 2023, state and county files: https://www2.census.gov/programs-surveys/cbp/datasets/
    4. U.S. Census Bureau, County Business Patterns 2019 and 2023 state files by detailed industry and employment size class (computed tables on this page): https://www2.census.gov/programs-surveys/cbp/datasets/
    5. U.S. Census Bureau, Vintage 2025 population estimates (state, county and incorporated places): https://www2.census.gov/programs-surveys/popest/datasets/2020-2025/
    6. Office of Management and Budget, metropolitan and micropolitan delineation, July 2023: https://www2.census.gov/programs-surveys/metro-micro/geographies/reference-files/2023/delineation-files/list1_2023.xlsx
    7. U.S. Small Business Administration, 7(a) and 504 FOIA loan data, as of 30 Sep 2026: https://data.sba.gov/dataset/7-a-504-foia
    8. 7 CFR Part 5001, OneRD Guaranteed Loanmaking and Servicing, CFR 2026 edition (govinfo): https://www.govinfo.gov/content/pkg/CFR-2026-title7-vol15/xml/CFR-2026-title7-vol15-part5001.xml
    9. 91 FR 11272, OneRD annual notice of guarantee fee, retention fee and guarantee percentage for FY2026 (govinfo): https://www.govinfo.gov/content/pkg/FR-2026-03-09/html/2026-04581.htm
    10. 13 CFR Part 120, SBA business loan programs (CFR 2026 edition): https://www.ecfr.gov/current/title-13/chapter-I/part-120
    11. USAspending.gov, prime award data by assistance listing 10.768, 10.766 and 10.868, FY2024 to FY2026 (counts may be incomplete): https://www.usaspending.gov/
    12. USDA Feasibility Study Consultants, Minnesota state page (state office, eligibility screens, sectors and precedents as the site reports them): https://usda-feasibility-study.com/minnesota
    13. USDA Rural Development Minnesota awards chart and releases; USDA Food Supply Chain awards list (2022 to 2024), as compiled on the site's Minnesota page: https://usda-feasibility-study.com/minnesota
    14. USDA Feasibility Study Consultants, national renewable energy page (REAP rule summary and state award ranking as the site reports them): https://usda-feasibility-study.com/renewable-energy-feasibility-study-usda
    15. USDA Feasibility Study Consultants, cost and timeline page (fee bands, phases, inclusions, exclusions, rush terms): https://usda-feasibility-study.com/usda-feasibility-study-cost
    16. USDA Feasibility Study Consultants, contact page (response time): https://usda-feasibility-study.com/contact

    Data current as of November 2026.

    Ready to Start Your USDA Project?

    Get your free consultation today and take the first step toward securing USDA funding for your rural development project.

    Our USDA feasibility study consultants scope every engagement against the five Part 5001 components in a free consultation.