USDA Data Center & Telecom Feasibility Study

    Last updated 2026-11-08

    Short answer

    A data center feasibility study is the independent report that tells a lender and USDA whether a facility will get the power it needs, on a date it can rely on, connect to enough fiber carriers, sign tenants at rents that cover an energy-heavy cost base, and cool its equipment at the efficiency the model assumes. For a USDA Business and Industry (B&I) guaranteed loan over $1,000,000 to a new business, an independent qualified consultant must prepare it; on smaller loans USDA or the lender may still require one [1]. B&I loans cap at $25M for single-borrower projects and carry an FY2026 guarantee of 85% on loans under $5M and 80% from $5M to $25M (91 FR 11272) [2][1].

    No Census industry code isolates data centers. The closest, NAICS 518210 (computing infrastructure providers, data processing, web hosting and related services), counted 18,544 establishments with paid employees in 2023 (+7.2% since 2019), paying $147,665 per employee; only 2.0% of those placed in a county were in non-metro counties [3][4]. Data centers used about 4.4% of U.S. electricity in 2023 and are expected to use 6.7% to 12% by 2028, according to the Department of Energy's report on Lawrence Berkeley National Laboratory's study [5]. Data current as of November 2026.

    QuestionAnswer
    Is a study required?Yes for a B&I loan over $1,000,000 to a new business; otherwise at USDA or lender discretion [1]
    Biggest eligibility trapProperty used primarily for commercial rental, with no control over tenants and services, is ineligible [1]
    What a reviewer reads firstThe signed utility load letter or interconnection agreement, then the tenant commitments
    U.S. industrial power price, January to August 20269.09 cents per kWh, +6.9% on a year earlier [6]
    SBA record for NAICS 5182101,371 7(a) and 504 loans, $624.1 million, FY2010 to FY2026 [7]
    Backup generator limitEmergency engines: 100 hours a year for maintenance and testing, 50 of them non-emergency, under EPA rules [8]

    Rural Data Centers: The Strategic Logic

    Rural markets are an increasingly central part of data center site selection. Low land costs, cooler climates supporting free-air cooling, direct access to renewable generation, and shorter interconnection queues can compound into a structural advantage over congested urban grids. This page covers facility types, rural advantages, power grid analysis, fiber connectivity, B&I program fit, and the five-component framework applied to rural technology infrastructure.

    The rural data center thesis rests on four structural advantages that urban and first-ring suburban markets cannot replicate. Land costs run far below urban comparables on a per-acre basis (this site has cited 80% to 95%), providing both construction economics and expansion optionality. Cooler climates support free-air cooling for substantial portions of the year, reducing the cooling load that is commonly put at 30% to 50% of operating expense in warm-climate siting. Direct access to utility-scale renewable generation meets tenant corporate sustainability commitments without complex virtual PPA structuring. And shorter interconnection queues at rural transmission nodes can shave years off power-availability timelines compared to congested urban grids. Each claim must be documented for the specific site, not asserted.

    The analytical work behind rural data center feasibility is substantially more technical than standard rural commercial asset classes. Signed utility load letters, interconnection queue documentation, fiber carrier route verification, ASHRAE climate zone analysis, and PUE projections grounded in comparable climate operating data all carry weight that generic rural market demand framing does not. The feasibility study must coordinate with electrical, mechanical, and civil engineering work, and the capital stack often integrates B&I senior debt with construction lender, tenant anchor commitments, and sponsor equity at scales that stretch USDA's standard program parameters. For the broader B&I framework, see the B&I page.

    As a feasibility study company organized around USDA lending, we scope data center engagements against the specific program the project routes through, whether B&I, Community Facilities, REAP, or another OneRD guarantee.

    What a data center feasibility study must prove

    Part 5001 defines a feasibility study as a report with an opinion or finding by independent qualified consultants on the economic, market, technical, financial and management feasibility of the project, under appendix A [1][9]. A business is new if it has operated less than a full year, or longer without reaching stable operations [1]; almost every data center financed at construction is a new business.

    #What the study must proveEvidence a reviewer expects
    1Power: the megawatts exist and arrive on scheduleSigned load letter or interconnection agreement, ramp schedule, substation and transmission scope, upgrade cost allocation
    2Power cost holds over the loan termTariff or power purchase agreement, demand charges, price history for the state [6]
    3Fiber: at least two diverse carriers reach the siteCarrier letters, route maps, laterals and build costs
    4Anchor tenants will sign at the modelled rentLeases, letters of intent or memoranda of understanding with named tenants; tenant credit
    5Absorption of the remaining capacityRegional supply and demand, competing facilities, pre-leasing
    6Cooling works at the assumed PUEClimate data, cooling design, comparable facility operating data
    7Water for cooling is available and permittedUtility or well capacity, water rights, discharge permits
    8Backup power is permitted and fuelledGenerator permits under emergency engine limits [8], fuel storage, testing plan
    9The borrower operates a business, not just a buildingServices, staffing and control over tenants and services [1]
    10Construction cost and schedule are realisticEngineer's estimate, fixed-price contract, contingency, equipment lead times
    11Jobs are counted honestlyStaffing plan by shift and position; construction jobs shown separately
    Financing routeFeasibility study ruleSource
    B&I loan over $1,000,000 to a new businessRequired, by an independent qualified consultant acceptable to the Agency; Agency sets scope5001.306(a)(3)(i)
    B&I loan of $1,000,000 or lessAgency may require one when the lender's analysis is not sufficient5001.306(a)(3)(ii)
    B&I loan of $600,000 or lessStreamlined application if the lender's analysis is sufficient5001.306(b)
    SBA 7(a) or 504SBA may require a feasibility study13 CFR 120.160(b)
    Guarantee issued before construction completionBudget and timetable confirmed by a qualified independent consultant5001.205(e)(2)

    Eligibility rules that decide a data center file

    Several Part 5001 provisions bear directly on data centers and telecom, and a study should address each before the market work is scoped [1].

    RuleWhat it saysWhat it means for a data center
    5001.115(g)Properties used primarily for commercial rental when the borrower has no control over tenants and services are ineligible, except industrial-site infrastructure developmentA powered shell or wholesale hall net-leased to one tenant looks like rental property; a colocation operator providing power, cooling, security and interconnection runs a business
    5001.105(b)(12)Constructing or equipping facilities for lease to private businesses in commercial or industrial operations is an eligible project typeLeasing is not fatal; tenant control and services decide which rule governs
    5001.105(b)(10)Broadband and telecommunication systems are eligible when not eligible for, or not funded by, the Rural Utilities Service program, subject to public notice and reporting rules in 7 CFR 1738Fiber and telecom builds go to RUS programs first
    5001.115(k) and (l)Community antenna television and radio facilities are ineligible; telephone systems are ineligible unless not eligible for the Agency's telecommunications programCarrier-type businesses usually belong in RUS programs
    5001.121Up to 10% of project funds may go to broadband infrastructure, subject to 7 CFR part 1980, subpart MA fiber lateral to the site can be part of a B&I project
    5001.126(d)(4)The project must primarily create new or save existing jobs for rural U.S. residents; collateral must be fixed assets in the United StatesLean staffing must still be documented honestly
    5001.118(b)Over $1 million and more than 50 new jobs: job transfer and overcapacity testsRarely binding at operation; construction jobs do not count as direct employment
    5001.406(c)$25 million maximum per borrowerHyperscale campuses exceed it many times over

    B&I applies only in rural areas: outside cities or towns over 50,000 under the latest decennial census and their contiguous urbanized areas, decided before approval [1]. Data centers favour sites near metro substations and fiber routes, which is exactly where the rural boundary falls, so a dated, address-level eligibility determination belongs in the study.

    Program fit: B&I, ReConnect, REAP and SBA

    RouteFit for a data center or telecom projectKey termsStudy trigger
    USDA B&I guaranteed loanEdge, enterprise and multi-tenant facilities operated by the borrower in a rural area; equipment and working capital [1]Up to $25 million; FY2026 guarantee 85% under $5 million, 80% above; 3.0% fee [2]Over $1 million to a new business
    ReConnect (7 CFR 1740)Broadband service to rural areas where at least 90% of households lack sufficient access; loans, grants and combinations [10]Its own rural test: outside places over 20,000 and urbanized areas next to cities over 50,000 [10]Program application rules
    REAPSolar or efficiency at an operating rural small businessGrants after completion with 12 months of data; at most 25% of cost [11]Technical report
    Community FacilitiesNot for commercial telecom or broadband; such projects are inherently commercial unless they meet the CF conditions [1]Public bodies and nonprofitsn/a
    SBA 504 and 7(a)Owner-occupied facilities and equipment; 7(a) up to $5 million504 equity 10% to 20% [12]SBA may require one

    National market evidence: what public data exists

    Public statistics on data centers are thin. There is no Census code for data centers alone, no federal register of facilities and no public series of rents or vacancy. Three public sources help, and the study fills the rest with primary evidence: utility letters, carrier letters, tenant commitments and competitor inventories.

    Electricity use by data centers

    Measure (Lawrence Berkeley National Laboratory, released by DOE)Value
    Data center electricity use, 201458 TWh [5]
    Data center electricity use, 2023176 TWh, about 4.4% of U.S. electricity [5]
    Estimated use, 2028325 to 580 TWh, about 6.7% to 12% of U.S. electricity [5]

    Demand growth of that size is the market argument for new capacity, and it is also the reason utilities now ration large loads. A study cannot rely on national growth; it has to show this site's power and this facility's tenants.

    NAICS 518210: computing infrastructure, data processing and web hosting

    MeasureUnited States
    Establishments with paid employees, 2019 (NAICS 2017 code 518210)17,297
    Establishments with paid employees, 2023 (NAICS 2022 code 518210)18,544
    Change, 2019 to 2023+1,247 (+7.2%)
    Establishments per 100,000 residents, 20235.5
    Paid employees, 2023 (mid-March)629,527
    Annual payroll, 2023$92.96 billion
    Average employees per establishment33.9
    Average annual pay per employee$147,665
    Establishments the county file places in a county15,854 (85.5% of the national total)
    Of those, in non-metro counties314 (2.0%) in 66 counties
    Share of U.S. population living in non-metro counties, 202513.6%
    Rural concentration index0.15

    The code covers cloud and hosting providers, colocation operators and data processing services, so it is a broad proxy. Two numbers still matter for a rural study. The industry is urban: a rural concentration index of 0.15 and 5,348 employees (0.9%) in non-metro counties [3][4]. And rural jobs pay differently: $63,709 per employee in non-metro counties against $153,068 in metro counties, so a rural facility's payroll model should use local technician and security wages, not the industry average.

    Top states by NAICS 518210 establishments, 2023

    RankState20192023ChangeEmployees 2023Avg payNon-metro shareIndustrial power price Jan-Aug 2026 (cents/kWh)
    1California2,5282,698+6.7%123,859$211,3980.2%21.11
    2Texas1,2651,412+11.6%56,290$123,6230.0%6.77
    3Florida1,0571,266+19.8%30,385$122,3550.3%9.20
    4New York1,0171,013-0.4%39,730$247,1720.3%10.33
    5Pennsylvania808937+16.0%19,443$112,8365.1%10.82
    6Virginia629641+1.9%33,404$144,9700.0%10.07
    7Ohio544633+16.4%14,692$112,3651.4%10.23
    8Illinois641627-2.2%21,934$120,1390.0%10.42
    9New Jersey555595+7.2%18,632$140,3090.0%15.31
    10Georgia547567+3.7%26,230$120,3960.7%8.67
    11Colorado570554-2.8%17,689$135,3252.2%9.64
    12Massachusetts508510+0.4%27,905$166,8460.0%19.94

    The twelve states hold 61.8% of establishments [3]. Industrial power prices in the same states run from 6.77 cents in Texas to 21.11 in California [6]; the state, and then the utility, sets the largest operating cost.

    Non-metro counties with the most NAICS 518210 establishments

    Non-metro countyStateEstablishments, 2023
    Laurel CountyKentucky17
    Sheridan CountyWyoming15
    Sussex CountyDelaware14
    Monroe CountyPennsylvania14
    Madison CountyKentucky13
    Franklin CountyKentucky9
    Eagle CountyColorado8
    Merrimack CountyNew Hampshire8
    Harrison CountyKentucky6
    Kennebec CountyMaine6
    Douglas CountyNevada6
    Montour CountyPennsylvania6

    These rural clusters are mostly back-office processing and hosting firms, not hyperscale campuses, but they show where rural technical labor already exists [3]. The site's state guides also report large campuses in or near rural counties, repeated as stated there and not USDA-financed: Amazon Web Services at New Carlisle, Indiana ($11 billion across 16 data shells, with a state data center sales-tax exemption and a ten-year 50% property tax abatement); Meta's Hyperion campus in Richland Parish, Louisiana (more than $50 billion, expanded to 5 GW in July 2026); and Amazon in Madison County and Compass in Meridian, Mississippi ($10 billion each) [13].

    Four Rural Data Center Categories

    Rural data center development spans four facility categories with distinct capital intensity, tenant structures, and USDA program fit. B&I accommodates edge and mid-sized enterprise facilities most naturally; hyperscale typically exceeds B&I's scale parameters; telecommunications infrastructure layers with ReConnect.

    Edge data centers. Small-footprint data centers (typically 1 to 5 MW) positioned near end-user populations to reduce latency for specific workloads: streaming, gaming, autonomous systems, and regional content delivery. Edge deployments are a growing rural data center category, driven by 5G rollout and content provider network expansion into secondary markets. Capital intensity is lower than hyperscale but site selection criteria are similarly rigorous on power, fiber, and climate.

    Enterprise and colocation facilities. Mid-sized facilities (typically 5 to 25 MW) serving enterprise customers, regional cloud providers, and multi-tenant colocation demand. Rural colocation development often anchors around regional industry clusters (healthcare systems, financial services back-office, agricultural technology) where customer concentration creates local demand. Tenant quality and lease economics drive feasibility; single-tenant enterprise facilities are structurally different from multi-tenant colocation, and under 5001.115(g) the difference can decide eligibility [1].

    Hyperscale campuses. Large-scale (100 MW plus) facilities serving cloud providers and major content platforms. Hyperscale projects increasingly target rural markets for land cost, power availability, and climate advantages. Feasibility work for hyperscale projects is typically driven by the hyperscaler tenant's own site selection criteria rather than open-market demand analysis. USDA B&I financing is uncommon at hyperscale scale but can support certain infrastructure and power components, within the $25 million borrower cap [1].

    Telecommunications infrastructure. Fiber networks, wireless tower infrastructure, rural broadband distribution, and supporting tech infrastructure. USDA operates the ReConnect program specifically for rural broadband, and B&I can finance broadband and telecommunication systems that are not eligible for, or not funded by, the Rural Utilities Service program [10][1]. Technology infrastructure feasibility differs from data center feasibility in several dimensions: utility-like economics, regulatory framework, and often subscriber-driven demand rather than enterprise tenant lease demand.

    Power Grid Analysis: The Single Most Important Analytical Dimension

    Power capacity and interconnection economics drive data center site selection more than any other factor. Six analytical dimensions anchor the power grid analysis that feasibility work must resolve.

    Analytical dimensionTreatment
    Megawatt availabilityThe primary site selection criterion. Feasibility work documents the specific power allocation the utility has committed in writing: the megawatt amount, the ramp schedule, and the interconnection timeline. Informal utility discussions do not substitute for formal load letters or interconnection agreements. Projects depending on undocumented power commitments face severe capital stack risk if capacity is reallocated.
    Transmission voltageData center projects typically require 138 kV or 345 kV transmission interconnection rather than distribution-level service. Transmission interconnection involves ISO or regional transmission operator queues, often multi-year timelines, and specific engineering studies (System Impact Study, Facility Study). Feasibility work documents queue position, study status, and expected completion dates.
    Substation capacity and upgradesMost rural substations lack capacity for data center scale loads without upgrades. Feasibility work quantifies the substation upgrade scope, cost allocation (utility vs. customer-funded), and timeline. Upgrades can add 18 to 36 months to the schedule and $20M to $100M plus to project cost depending on scope.
    Utility capacity and rate structureRural utility rate structures differ substantially from urban. Large industrial customer rates, demand charges, and Power Purchase Agreement availability all drive long-term operating economics. Feasibility work models expected utility costs over a 15 to 20-year horizon given the specific rate structure available at the site.
    Renewable PPA structuringCorporate sustainability commitments increasingly require renewable energy matching for data center loads. PPA structures (virtual PPA, physical PPA, utility green tariff) vary by market and tenant requirement. Feasibility work addresses how the data center's power profile integrates with available renewable PPA structures, and the cost delta vs. standard grid rates.
    Redundancy and resilienceTier III and Tier IV data center classifications require redundant power paths (N+1 or 2N configurations) to ensure uptime commitments to tenants. Rural siting can complicate redundancy by limiting the number of independent transmission paths available. Feasibility work documents the specific redundancy configuration achievable at the site and its implications for uptime SLA commitments.

    States with the lowest industrial power prices

    RankStateIndustrial price Jan-Aug 2026 (cents/kWh)Same period 2025ChangeNAICS 518210 establishments, 2023
    1New Mexico5.196.02-13.8%77
    2Louisiana6.586.33+3.9%130
    3Texas6.776.31+7.3%1,412
    4Tennessee6.846.75+1.3%248
    5Oklahoma6.896.10+13.0%161
    6Arkansas6.966.71+3.7%129
    7Montana6.997.10-1.5%58
    8Washington7.176.95+3.2%476
    9Kentucky7.496.84+9.5%441
    10Mississippi7.657.26+5.4%74
    11Iowa7.667.27+5.4%126
    12South Carolina7.867.27+8.1%186
    United States9.098.50+6.9%18,544

    Industrial prices rose in 47 of 51 jurisdictions (the 50 states and the District of Columbia) between the first eight months of 2025 and 2026, with the largest increases in the District of Columbia (+44.9%); Ohio (+26.3%); Maryland (+22.3%) [6]. The lowest-priced states were New Mexico (5.19); Louisiana (6.58); Texas (6.77) cents per kWh; the highest Hawaii (37.83); Alaska (23.90); Rhode Island (21.57) [6]. A model built on last year's tariff can be wrong by double digits within a year.

    What one megawatt of IT load costs to power

    PUE (assumed)kWh per year per 1 MW of IT load at full useAnnual power cost at 6.00 centsAt 9.09 cents (U.S. industrial, Jan-Aug 2026)At 12.00 centsAt 16.00 cents
    1.210,512,000$630,720$955,541$1,261,440$1,681,920
    1.412,264,000$735,840$1,114,798$1,471,680$1,962,240
    1.614,016,000$840,960$1,274,054$1,681,920$2,242,560

    At a PUE of 1.4, one megawatt of IT load running all year draws 12,264,000 kWh, about $1,114,798 at the U.S. industrial average, and every cent per kWh adds $122,640 a year [6]. Whether leases pass power through to tenants at cost decides whether that risk sits with the borrower, so the study reads the lease forms before it builds the model.

    Backup generation has its own limit. Under EPA's rules for stationary compression ignition engines, an emergency engine may run without limit in emergencies, but only 100 hours a year for maintenance and readiness testing, of which up to 50 may be non-emergency use; outside those limits it must meet non-emergency engine requirements [8]. A design that counts on generators for routine peak shaving or demand response needs a different permit and cost.

    Fiber Connectivity & ReConnect Integration

    Fiber carrier diversity and route resilience distinguish viable data center sites from ineligible ones. Four elements structure the fiber connectivity analysis, including USDA's ReConnect program as a potential funding source for the broadband infrastructure component.

    Long-haul fiber carriers. Data center demand for low-latency connectivity requires multiple long-haul fiber carriers at the site. Feasibility work documents which tier-1 carriers (Lumen, AT&T, Verizon, Cogent, Zayo, others) have fiber reaching the site, the specific routes, and the redundancy available. Single-carrier sites face substantial tenant concerns about path diversity. Most rural sites require new fiber builds to achieve the three-to-five carrier standard tenants expect.

    USDA ReConnect program integration. USDA's ReConnect program provides grants, loans, and loan/grant combinations for rural broadband infrastructure [10]. Its purpose is broadband service: an eligible service area is one where at least 90% of households lack sufficient access, defined by the funding notice and never below 10 Mbps down and 1 Mbps up, and its rural test excludes places over 20,000 [10]. A data center's own fiber is not a ReConnect project; a carrier serving unserved households near the site may be one. Feasibility work addresses how ReConnect funding integrates with commercial data center fiber infrastructure, where applicable to the specific project structure, and B&I itself can fund broadband infrastructure up to 10% of project funds [1].

    Middle-mile and last-mile coordination. Edge data centers and enterprise colocation facilities often require integration with middle-mile regional networks and last-mile local access. Rural markets frequently have underdeveloped middle-mile infrastructure, creating both a feasibility challenge and a strategic opportunity. Projects that can anchor middle-mile network investment often secure infrastructure advantages competitors cannot replicate. The site's ReConnect broadband feasibility guide covers the broadband side.

    Interconnection economics and meet-me rooms. Data center revenue increasingly derives from interconnection fees (cross-connects, meet-me room access, cloud on-ramps) rather than raw space and power. Rural data center feasibility addresses whether sufficient carrier presence and tenant density can support interconnection revenue, or whether the project is structurally a power-and-space play without the interconnection premium that drives urban colocation economics.

    B&I Program Fit for Tech Infrastructure

    B&I can finance edge data centers, regional colocation facilities, and rural telecommunications infrastructure under standard program rules where the project is eligible. Four structural elements anchor B&I's fit for data center and tech infrastructure projects.

    Tech infrastructure as rural business activity. A borrower must be engaged in a business, which can include providing services or other activities that will provide employment or improve the economic climate in rural communities [1]. Data center and telecommunications infrastructure qualifies for B&I financing as rural business development where the project meets standard B&I eligibility criteria: a rural location under the 5001.3 test, a borrower that operates the business, the job requirement, and demonstrated feasibility.

    Job creation documentation. Data centers carry a specific job creation challenge: operational staffing is lean (the site has cited 15 to 30 FTE for a 25 MW facility) despite large capital investment. B&I feasibility work documents direct employment realistically rather than overstating, and addresses the indirect job impact through construction, supplier ecosystem, and regional economic development. The rule requires that the project primarily create or save jobs for rural U.S. residents [1]; direct job count alone does not carry rural multifamily or rural hospitality projects, and the same analytical honesty applies here.

    Regional connectivity and economic purpose. B&I's purpose is to improve, develop or finance business, industry and employment and improve the economic climate in rural communities [1]. Feasibility work documents the regional technology infrastructure gap the project addresses, the tenant demand (existing or projected) the project serves, and the economic development impact beyond the direct operational footprint.

    Loan size and guarantee coverage. B&I loans cap at $25M for single-borrower projects and carry an FY2026 guarantee of 85% on loans under $5M and 80% from $5M to $25M (91 FR 11272) [2]. Large data center projects frequently exceed B&I's single-borrower cap, requiring either phased structuring, multi-entity borrowing, or alternative senior debt with B&I supporting specific components. Affiliates that depend on each other must generally be co-borrowers [1], which limits splitting one project across entities. Feasibility work addresses the capital stack structure that matches project scale to B&I's program parameters.

    Financing evidence: SBA lending to NAICS 518210 and seasoned losses

    SBA records are the only public loan-level history for the industry [7]. From FY2020 to FY2026 lenders made 513 7(a) loans averaging $557,961 and 22 504 loans averaging $779,182, most to hosting and processing firms; the states with the most were California (61); Texas (61); Florida (42); New York (31); Illinois (23).

    Approval years7(a) loans7(a) dollarsAverage 7(a)504 loans504 dollarsAverage 504Jobs reported (both)
    FY2010 to FY2016541$170.5 million$315,24450$36.9 million$737,8207,318
    FY2017 to FY2019226$99.4 million$439,73319$13.9 million$732,6842,938
    FY2020 to FY2023249$152.0 million$610,57117$12.3 million$725,2942,451
    FY2024 to FY2026264$134.2 million$508,3395$4.8 million$962,4002,757
    FY2010 to FY20261,280$556.2 million$434,50191$68.0 million$746,74715,464
    ProgramApproval yearsCohort ageLoansCharged offCharge-off rate (count)Charged-off dollars / approved dollarsAverage months to charge-off
    7(a)FY2010 to FY2016seasoned (10 to 16 years)541193.5%1.8%68
    7(a)FY2017 to FY2019maturing (7 to 9 years)226219.3%5.0%63
    7(a)FY2020 to FY2023young (3 to 6 years)24972.8%1.6%47
    7(a)FY2024 to FY2026new (under 3 years)26410.4%0.3%29
    504FY2010 to FY2016seasoned (10 to 16 years)5000.0%0.0%n/a
    504FY2017 to FY2019maturing (7 to 9 years)1900.0%0.0%n/a
    504FY2020 to FY2023young (3 to 6 years)1700.0%0.0%n/a
    504FY2024 to FY2026new (under 3 years)500.0%0.0%n/a

    Of 541 7(a) loans approved in FY2010 to FY2016, 19 were charged off (3.5%, 1.8% of dollars), on average 68 months after approval; the FY2017 to FY2019 cohort has already lost 9.3% of 226 [7]. These are small loans to small firms, far from a B&I data center, so they set a floor on risk, not a benchmark for a powered facility.

    USDA activity, all states

    USAspending counts awards by program, not industry: 643 B&I guaranteed loan awards from 1 October 2023 to 30 September 2026, shown for the ten states with the most [14].

    StateB&I guaranteed loan awardsREAP grantsREAP guaranteed loansCommunity Facilities awards
    Missouri74309432
    Texas72134340
    Oklahoma37103047
    California3593551
    North Carolina331021287
    Louisiana2872022
    New York281861393
    Florida2467121
    Illinois21459637
    Ohio21268075
    All 51 states with data6436,722751,717

    Financing structure: terms, equity and collateral

    FY2026 loan typeGuarantee feeAnnual retention feeGuaranteeExtra fee if guarantee issued before construction completion
    B&I under $5 million3.0%0.55%85%0.50%
    B&I $5 million to $25 million3.0%0.55%80%0.50%
    B&I reduced fee1.0%0.50%80%0.50%
    B&I Alaska high-cost isolated area not on road system1.0%0.50%90%0.50%
    Community Facilities guaranteed1.25%0.50%80%0.50%
    REAP guaranteed1.0%0.25%80%0.50%

    The guarantee fee is loan times guaranteed percentage times rate; the retention fee is charged yearly on the guaranteed share of principal outstanding [1][2]. Terms follow the useful life of the collateral up to 40 years, fully amortising [1]; IT and cooling equipment has a much shorter life than the building, so a data center loan blends terms and the study's replacement schedule must fund equipment refreshes.

    Borrower situation at closingMinimum capital or equity (any one test)Rule
    Existing business10% balance-sheet equity (or debt to equity no more than 9 to 1); or 10% of total eligible project costs invested; or owner capital of at least 10% of net fixed assets plus depreciation5001.105(d)(1)
    New business with sales contracts covering debt service for at least the loan term10% balance-sheet equity (or 9 to 1); or 10% of project cost5001.105(d)(2)
    New business, construction, guarantee requested before completion25% balance-sheet equity (or 3 to 1); or 25% of project cost5001.105(d)(3)
    All other new businesses20% balance-sheet equity (or 4 to 1); or 25% of project cost5001.105(d)(4)
    Higher-risk loansAgency may raise the requirement (industry status, concentration, collateral, guarantees, cash flow, contracts, credit rating, strength of the feasibility study, management)5001.105(d)(5)

    Equity must be cash or earning assets, injected before guaranteed funds when the guarantee is issued during construction, and the construction rules require a fixed-price contract, contingency and a budget confirmed by an independent consultant [1]. Real estate over $250,000 needs a USPAP appraisal with as-is and prospective values, with going concern value deducted [1]. A data center appraises on its leases and power; without signed tenants, the prospective value and the collateral coverage both fall.

    Worked examples (illustrative)

    Two illustrative loans at an assumed 7.50% fixed rate over 20 years: Example A, a $4,500,000 edge or enterprise facility with about 1.5 MW of IT load in the 85% tier, and Example B, a $20,000,000 colocation facility with about 8 MW in the 80% tier. Neither is a quote or a past project.

    Example A: $4,500,000 edge facility, 85% guarantee

    ItemIllustrative valueBasis
    Loan amount$4,500,000Illustrative edge or enterprise facility, about 1.5 MW of IT load
    Rate and term7.50% fixed, 20 years, monthly paymentsAssumption within 5001.401 and 5001.402
    FY2026 guarantee85%: $3,825,000 guaranteed, $675,000 notB&I under $5 million: 85%
    Guarantee fee$114,750 (3.00%); $133,875 if the guarantee is issued before construction is completeLoan x guarantee % x fee rate; 5001.454
    Monthly payment / annual debt service$36,252 / $435,020Level amortisation, no balloon
    Retention fee, year 1 / year 10$20,566 / $14,2780.55% x guaranteed principal outstanding; 5001.455
    NOI for 1.00x / 1.25x$435,020 / $543,775Debt service x coverage
    NOI for 1.25x with the retention fee$569,482(Debt service + year-1 retention fee) x 1.25
    New business: 25% of project cost testCost $6,000,000; equity $1,500,0005001.105(d)(3) and (4)
    New business: 20% balance-sheet testAssets $5,625,000; equity $1,125,0005001.105(d)(4)
    Existing business: 10% of project cost testCost $5,000,000; equity $500,0005001.105(d)(1)

    Example B: $20,000,000 colocation facility, 80% guarantee

    ItemIllustrative valueBasis
    Loan amount$20,000,000Illustrative multi-tenant colocation facility, about 8 MW of IT load
    Rate and term7.50% fixed, 20 years, monthly paymentsAssumption within 5001.401 and 5001.402
    FY2026 guarantee80%: $16,000,000 guaranteed, $4,000,000 notB&I $5 million to $25 million: 80%
    Guarantee fee$480,000 (3.00%); $560,000 if the guarantee is issued before construction is completeLoan x guarantee % x fee rate; 5001.454
    Monthly payment / annual debt service$161,119 / $1,933,424Level amortisation, no balloon
    Retention fee, year 1 / year 10$86,026 / $59,7230.55% x guaranteed principal outstanding; 5001.455
    NOI for 1.00x / 1.25x$1,933,424 / $2,416,780Debt service x coverage
    NOI for 1.25x with the retention fee$2,524,312(Debt service + year-1 retention fee) x 1.25
    New business: 25% of project cost testCost $26,666,667; equity $6,666,6675001.105(d)(3) and (4)
    New business: 20% balance-sheet testAssets $25,000,000; equity $5,000,0005001.105(d)(4)
    Existing business: 10% of project cost testCost $22,222,222; equity $2,222,2225001.105(d)(1)

    Example A needs about $543,775 of net operating income for 1.25 times coverage; Example B about $2,416,780. As new businesses above $1,000,000 both need an independent study, and Example B's sponsor would put in about $6,666,667 under the 25% of project cost test [1].

    Income per leased kilowatt the debt requires

    Share of IT capacity leased (assumed)Example A leased kWExample A NOI per leased kW per month for 1.25xExample B leased kWExample B NOI per leased kW per month for 1.25x
    50%750$604,000$50
    70%1,050$435,600$36
    90%1,350$347,200$28

    At 70% of capacity leased, Example A must earn about $43 of net operating income per leased kW each month and Example B about $36, after power, staff, maintenance and reserves. The study compares those figures with the rents and power terms in signed tenant documents.

    Stress test, including power price

    ScenarioExample A NOIExample A coverageExample B NOIExample B coverage
    Base case at 1.25x$543,7751.25x$2,416,7801.25x
    NOI down 10%$489,3981.12x$2,175,1021.12x
    NOI down 20% (break-even)$435,0201.00x$1,933,4241.00x
    NOI down 30%$380,6430.88x$1,691,7460.88x
    Power 1 cent per kWh higher, not passed through (70% load, PUE 1.4)$415,0030.95x$1,729,9960.89x
    Power 2 cents per kWh higher, not passed through (70% load, PUE 1.4)$286,2310.66x$1,043,2120.54x
    Variable rate 2 points higher, re-amortised$543,7751.08x$2,416,7801.08x

    At 70% load and a PUE of 1.4, Example A draws about 12,877,200 kWh a year and Example B about 68,678,400; each cent of unrecovered power cost removes $128,772 and $686,784 from income. A two-cent rise not passed through to tenants takes Example A to 0.66x and Example B to 0.54x [6]. The lease pass-through clause is therefore a credit term, and the study should show coverage with and without it.

    Priority points a data center can document

    B&I priority factor (5001.318, maximum 100 points)PointsWhat the study can document
    Project in an unincorporated area or a city under 25,0005Site address
    Distressed community (EIG index); persistent-poverty rural county; unemployment at least 125% of the state rate; tribal land5 eachCounty data
    Rate at or below Prime + 1.5%; guaranteed loan under 60% of project cost; veteran-owned5 eachRate quote, sources and uses
    Industry not already present in the community5Local employers by NAICS
    20% or more of sales in international markets5Tenant contracts abroad
    Locally owned and managed5Ownership chart
    Natural resource value-added product5Rarely applies
    At least five jobs created or saved at an average wage above 150% of the federal minimum wage5Staffing plan and wages
    Healthcare benefits offered to all employees, at least 50% of the premium paid5Benefits plan
    State Director or Administrator discretionary pointsUp to 10 eachStatewide distribution, emergencies, strategic plans, special initiatives; loans over $10 million

    The Five Components, Applied to Data Centers

    The 7 CFR Part 5001 five-component framework applies to B&I-financed data center and telecommunications infrastructure projects. Technical component demands coordination with electrical, mechanical, and civil engineering work substantially beyond standard rural commercial asset classes.

    ComponentApplied to a data center
    Economic feasibilityRegional economic base, technology sector presence, broadband infrastructure baseline, utility capacity trajectory, and state/local economic development incentive environment. Census ACS, utility capacity filings, state technology sector economic data, and local economic development organization research.
    Market feasibilityTenant demand quantification (enterprise, colocation, edge, hyperscale by category), regional competitive inventory, projected market absorption, lease rate benchmarking, and interconnection ecosystem depth. Edge facilities reference content delivery network and 5G deployment; colocation references regional enterprise tenant presence.
    Technical feasibilityPower interconnection engineering, substation capacity, transmission routing, fiber carrier diversity, cooling infrastructure (free-cooling hours, chiller capacity, redundancy), Tier classification (III vs IV), and ASHRAE climate integration. Reconciliation with electrical, mechanical, and civil engineering work.
    Financial feasibilityMulti-year projection with revenue by product (space, power, interconnection), operating expense structure (power is the dominant line item; cooling and staffing follow), debt service coverage, and sensitivity to PUE, power cost, and tenant absorption. Capital structure including construction lender, permanent debt, and sponsor equity documented.
    Management feasibilitySponsor and operator experience in data center development and operations, tenant relationships and leasing pipeline, construction management capacity for technical facility construction, and ongoing operations staffing plan. Tenant anchor commitments (LOIs, MOUs, or signed leases) substantially strengthen the feasibility case.

    Data center risks and how the study tests them

    RiskRule or regulatorHow the study tests it
    Power not delivered on scheduleUtility and transmission operator processesSigned load letter, queue position, study status, upgrade schedule
    Power priceState utility commission tariffs [6]Tariff model; pass-through terms; price shock
    Tenant does not sign or leavesNone; market riskSigned leases, tenant credit, re-leasing time
    Rental-property ineligibility5001.115(g) [1]Services, staffing and control over tenants
    Generator permits and limits40 CFR 60.4211 emergency engine limits [8]; state air permitsPermit path and operating hours
    Technology obsolescenceUseful life sets loan term [1]Equipment refresh reserve
    Construction overrun5001.205(e)(2) for early guarantees [1]Fixed-price contract, contingency, lead times
    WaterState water law and discharge permitsCapacity letter, cooling design, drought case

    Where Data Center Studies Fail Review

    Nine patterns in rural data center feasibility studies that trigger USDA reviewer challenges. Undocumented power commitments and overstated tenant demand dominate this list.

    1. Power allocation documented through utility letters of support rather than signed load letters or interconnection agreements.
    2. Fiber carrier diversity claims without verification of actual fiber presence and owner-operated routes.
    3. Cooling efficiency (PUE) projections benchmarked against marketing materials rather than comparable climate zone operating data.
    4. Hyperscale tenant demand assumed without LOI, MOU, or site selection criteria confirmation from a named tenant.
    5. Construction cost estimates below rural data center construction benchmarks, understating capital stack requirements.
    6. Interconnection revenue projections applied to rural sites without carrier ecosystem depth to support cross-connect volume.
    7. ReConnect program integration assumed without addressing actual program eligibility and funding cycle timing.
    8. Job creation documentation overstated, inflating direct employment counts beyond realistic data center staffing ratios.
    9. A single-tenant powered shell presented as an operating business, without addressing 5001.115(g) [1].

    Process, timeline and documents

    The B&I path runs from eligibility and the rental-property question with the State Office, to lender engagement, study and appraisal, the lender's credit analysis, application, conditional commitment, closing and the loan note guarantee. The borrower must take no action that could harm the environment or limit alternatives until USDA's environmental review is complete [1]. On this site's schedule the data request goes out within 48 hours of signing, market work runs in weeks 2 to 4, the model and draft in weeks 4 to 6 and delivery in weeks 6 to 8, with revisions at no added cost until USDA or the lender accepts the report; complex engagements take longer [15][16]. Bring the load letter, interconnection documents, carrier letters, tenant documents, engineering estimates and cooling design, generator plans, and the sponsor's operating record.

    Data center feasibility by state

    The site has no state-level data center pages. Its state guides cover each State Office, the rural boundaries and state incentives; the tables above link the guides for the states with the most NAICS 518210 establishments and the lowest industrial power prices. The guides for Indiana, Louisiana, Mississippi and Georgia discuss data center and power projects in their states [13].

    Hiring a data center feasibility study consultant

    An independent qualified consultant acceptable to the Agency is required for a B&I loan over $1,000,000 to a new business, with scope set by the Agency [1]. The consultant should be independent of the developer, the equipment vendors, the utility and the anchor tenant. A USDA feasibility study consultant on this site scopes each engagement against the program the project uses and works with the project's power, fiber and engineering consultants rather than replacing them.

    The engagement includes all five Part 5001 components, a five to ten year projection with sensitivity analysis, market area and demand analysis, a competitive supply inventory, comparable operator benchmarks, a management assessment, PDF and Word reports with an Excel workbook, kickoff and midpoint calls, one round of revisions and a written acceptance guarantee; engineering, environmental assessments, legal work and appraisals are separate [15]. Fees on the cost page: $10,500 to $14,500 for complex B&I studies (7 to 9 weeks) and $9,500 to $18,000 for cross-program OneRD engagements (7 to 10 weeks), quoted as a firm fixed fee; a rush runs 3 to 4 weeks at a 20% to 35% premium [15]. A senior analyst responds within one business day [16].

    Fifteen-minute scoping call, written proposal, firm fixed fee before you sign: request a proposal for your data center feasibility study.

    David Miller, CPA

    USDA Feasibility, Inc.

    Frequently Asked Questions

    Can USDA finance a data center project?

    Yes, through B&I, for projects in a rural area run by a borrower that operates the business. B&I lends up to $25 million per borrower, with an FY2026 guarantee of 85% under $5 million and 80% above [1][2]. A building leased to tenants the borrower does not control can be ineligible as commercial rental [1]. Broadband components may fit ReConnect [10]. Edge and mid-sized enterprise facilities fit B&I's parameters more naturally than hyperscale.

    What is the typical fee for a USDA data center feasibility study?

    The site's cost page lists $10,500 to $14,500 for complex B&I studies, such as loans over $10 million or an unusual asset class, and $9,500 to $18,000 for cross-program OneRD engagements, each quoted as a firm fixed fee in a written proposal [15]. Data centers usually price in those tiers because of power, fiber and engineering coordination. Timelines run 7 to 10 weeks; a rush is 3 to 4 weeks at a 20% to 35% premium.

    How do you document power capacity for data center feasibility?

    Signed utility documentation. Load letters confirming megawatt allocation, interconnection queue position confirmation from the ISO or regional transmission operator, System Impact Study and Facility Study results where available, and the specific substation and transmission path documentation. Informal utility discussions or letters of support without specific capacity commitment do not support data center feasibility conclusions. The tariff or power contract then sets the cost line, stressed against state price changes [6].

    What climate zones work best for rural data centers?

    Cooler climates (ASHRAE climate zones 5, 6, 7, and parts of zone 4 north) support the most hours of free-air cooling annually and produce the most favorable PUE economics. Upper Midwest, Pacific Northwest, Northern New England, interior Mountain West, and Northern Great Plains all work. Warmer climates can still support data centers but require more active cooling and typically produce less favorable PUE. Power price often outweighs climate: the cheapest industrial power in 2026 was in New Mexico, Louisiana and Texas [6].

    How does USDA ReConnect integrate with B&I for telecommunications projects?

    ReConnect is a separate Rural Utilities Service program of loans, grants and combinations for broadband service in rural areas where at least 90% of households lack sufficient access, with its own rural test excluding places over 20,000 [10]. B&I finances broadband and telecom systems only when they are not eligible for, or not funded by, RUS programs, and lets up to 10% of project funds go to broadband infrastructure [1]. Layered applications need separate eligibility analysis.

    Can small-town data centers work, or does it require metro proximity?

    Edge data centers work in smaller rural markets where specific demand drivers exist: proximity to major population centers within latency thresholds (typically 50 to 100 mile radius from metro), regional industry cluster demand, or content delivery network deployment. Standalone rural markets without latency proximity or specific tenant demand face harder feasibility challenges. The strongest rural projects combine land and power cost advantages with access to metro demand, while staying outside the metro's urbanized area for B&I [1].

    Do I need a feasibility study for a USDA data center loan?

    Yes for a B&I loan over $1,000,000 to a new business, which describes almost every data center financed at construction [1]. Below that, the Agency may still require one when the lender's analysis is not sufficient, and SBA lenders may also require a study [12]. Because power, tenants and eligibility are all uncertain before construction, lenders on these projects rarely proceed without one.

    Is a data center leased to a single tenant eligible for B&I?

    It depends on control and services. Properties used primarily for commercial rental where the borrower has no control over tenants and services are ineligible, while facilities for lease to private businesses in commercial or industrial operations are an eligible project type [1]. A colocation operator providing power, cooling, security and interconnection is running a business; a powered shell on a triple-net lease looks like rental property. Ask the State Office before scoping the study.

    Who can prepare a data center feasibility study?

    An independent qualified consultant acceptable to the Agency, with scope set by the Agency [1]. The author should be independent of the developer, vendors, utility and tenants. Electrical, mechanical and civil engineering, interconnection studies and appraisals come from specialists; the study reconciles them into the market, financial and management opinion that appendix A requires, with the consultant's qualifications [9].

    How long is a data center feasibility study valid?

    Part 5001 sets no expiry for studies; appraisals may be no more than a year old [1], and this site works to an 18-month data recency standard [15]. Data center inputs move fast: a revised interconnection date, a new tariff or a tenant change can alter coverage in months. Update the study whenever the power schedule, power price, anchor lease or construction budget changes materially.

    Can one study serve SBA and USDA lenders?

    Usually yes, if built to the Part 5001 standard, because SBA may require a feasibility study and reviews the same evidence [12]. But SBA 7(a) stops at $5 million and 504 suits owner-occupied facilities, so most data center financing that needs a guarantee looks to B&I. The study can model both where the facility is small enough.

    Can backup generators be used to cut power bills?

    Only within limits. EPA's rules let an emergency stationary diesel engine run without limit in emergencies, but only 100 hours a year for maintenance and readiness testing, of which up to 50 may be non-emergency use [8]. Running generators for routine peak shaving makes them non-emergency engines with stricter requirements. The study should model the operating hours the permit allows, not the hours that would save the most money.

    How many jobs does a data center need to show for B&I?

    No minimum, but the project must primarily create or save jobs for rural U.S. residents [1]. Operating staff are few relative to cost, so the study should count technicians, security and facility staff by shift, show construction jobs separately, and avoid inflated totals. Five jobs above 150% of the federal minimum wage earns a priority point, and healthcare benefits earn another [1].

    Sources

    [1] 7 CFR part 5001, OneRD Guaranteed Loans (CFR 2026 edition, title 7 vol. 15, revised 1 Jan 2026), govinfo. https://www.govinfo.gov/content/pkg/CFR-2026-title7-vol15/xml/CFR-2026-title7-vol15-part5001.xml (accessed 11 Nov 2026)

    [2] USDA, OneRD Annual Notice of Guarantee Fee Rates, Periodic Retention Fee Rates, Loan Guarantee Percentage and Fee for Issuance of the Loan Note Guarantee Prior to Construction Completion for Fiscal Year 2026, 91 FR 11272 (9 Mar 2026). https://www.govinfo.gov/content/pkg/FR-2026-03-09/html/2026-04581.htm (accessed 6 Nov 2026)

    [3] U.S. Census Bureau, County Business Patterns 2019 and 2023, state and county files. https://www2.census.gov/programs-surveys/cbp/datasets/2023/cbp23st.zip ; https://www2.census.gov/programs-surveys/cbp/datasets/2023/cbp23co.zip ; https://www2.census.gov/programs-surveys/cbp/datasets/2019/cbp19st.zip (accessed 11 Nov 2026)

    [4] OMB metropolitan and micropolitan statistical area delineation file, July 2023 (list1_2023). https://www2.census.gov/programs-surveys/metro-micro/geographies/reference-files/2023/delineation-files/list1_2023.xlsx (accessed 7 Nov 2026)

    [5] U.S. Department of Energy, DOE Releases New Report Evaluating Increase in Electricity Demand from Data Centers (20 Dec 2024), on Lawrence Berkeley National Laboratory's 2024 Report on U.S. Data Center Energy Use. https://www.energy.gov/articles/doe-releases-new-report-evaluating-increase-electricity-demand-data-centers (accessed 11 Nov 2026)

    [6] U.S. Energy Information Administration, Electric Power Monthly, table 5.6.B, Average Price of Electricity to Ultimate Customers by End-Use Sector, by State, year to date through August 2026 and 2025. https://www.eia.gov/electricity/monthly/epm_table_grapher.php?t=epmt_5_6_b (accessed 11 Nov 2026)

    [7] U.S. Small Business Administration, 7(a) and 504 FOIA loan data, as of 30 Sep 2026: FOIA_7a_FY2010_FY2019, FOIA_7a_FY2020_Present, FOIA_504_FY2010_Present. https://data.sba.gov/sites/default/files/uploaded_resources/FOIA_7a_FY2020_Present_asof_260930.csv (and companion files) (accessed 11 Nov 2026)

    [8] 40 CFR 60.4211, Compliance requirements for stationary compression ignition internal combustion engines (CFR 2025 edition). https://www.govinfo.gov/content/pkg/CFR-2025-title40-vol8/xml/CFR-2025-title40-vol8-sec60-4211.xml (accessed 11 Nov 2026)

    [9] OneRD Guaranteed Loan Regulation, 85 FR 42494 (14 Jul 2020), appendix A to subpart D of part 5001, Feasibility Study Components, pp. 42556-42557 (published as images). https://www.govinfo.gov/content/pkg/FR-2020-07-14/html/2020-13991.htm (accessed 11 Nov 2026)

    [10] 7 CFR part 1740, Rural eConnectivity Program (CFR 2025 edition). https://www.govinfo.gov/content/pkg/CFR-2025-title7-vol11/xml/CFR-2025-title7-vol11-part1740.xml (accessed 11 Nov 2026)

    [11] USDA RBCS, Unleashing American Energy and Economic Prosperity; Rural Energy for America Program (REAP), final rule with comment period, 91 FR 62600 (1 Oct 2026), effective 16 Oct 2026. https://www.govinfo.gov/content/pkg/FR-2026-10-01/html/2026-20178.htm (accessed 7 Nov 2026)

    [12] 13 CFR part 120, Business Loans (CFR 2026 edition), govinfo; sections 120.150, 120.151, 120.160, 120.210, 120.220, 120.801, 120.900 to 120.971. https://www.govinfo.gov/content/pkg/CFR-2026-title13-vol1/xml/CFR-2026-title13-vol1-sec120-160.xml ; https://www.govinfo.gov/content/pkg/CFR-2026-title13-vol1/xml/CFR-2026-title13-vol1-sec120-151.xml (120.151 accessed 11 Nov 2026; others accessed 6 Nov 2026)

    [13] usda-feasibility-study.com, state USDA guides (site pages, as captured 7 to 10 Nov 2026), for precedents attributed there to USDA Rural Development releases and lender announcements. https://usda-feasibility-study.com/states

    [14] USAspending.gov, award counts by place of performance for Assistance Listings 10.768 (B&I), 10.766 (Community Facilities) and 10.868 (REAP), 1 Oct 2023 to 30 Sep 2026, API v2 spending_by_award_count. https://api.usaspending.gov/api/v2/search/spending_by_award_count/ (accessed 7 Nov 2026)

    [15] usda-feasibility-study.com, USDA Feasibility Study Cost & Timeline (site page, as captured 7 Nov 2026). https://usda-feasibility-study.com/usda-feasibility-study-cost

    [16] usda-feasibility-study.com, Contact & Request a Proposal (site page, as captured 7 Nov 2026). https://usda-feasibility-study.com/contact

    Ready to Start Your USDA Project?

    Get your free consultation today and take the first step toward securing USDA funding for your rural development project.

    Our USDA feasibility study consultants scope every engagement against the five Part 5001 components in a free consultation.