Cold Storage and Dairy Processing Feasibility: Washington USDA Feasibility Study Case Study

    Last updated 2026-11-08

    How to read this case study. The engagement summary reflects the published record. Client names, actual costs, loan terms and proprietary data are confidential, so the project budget, market sizing and financial projections below are a modeled example built from public data for this project type and location. They show the analysis a lender-grade study performs, not the client's figures.

    Data current as of November 2026.

    Engagement summary

    In 2024 we prepared a feasibility study for a combined cold storage and dairy processing project in Mount Vernon, Washington, financed through the USDA Business and Industry (B&I) guaranteed loan program with a Farm Credit System institution as lender. The loan sat in the $5 million to $25 million tier, and the study was prepared with throughput and absorption modeling.

    FieldPublished record
    ProgramUSDA Business and Industry (B&I) guaranteed loan
    AssetCold storage and dairy processing
    LocationMount Vernon, Washington (Skagit County)
    Loan size tier$5 million to $25 million
    Year2024
    Lender typeFarm Credit System institution
    OutcomePrepared with throughput and absorption modeling

    The engagement card describes what the throughput and absorption work measured: intake capacity in pounds per hour, utilization of the cold storage space, the minimum break-even occupancy (which it says was benchmarked at 85% or more for workable coverage), co-packing contract coverage as a share of stabilized revenue, and milk supply seasonality, with working capital sized from monthly ramp-up cash flows. This page builds a modeled version: a new company that processes members' and customers' milk into cultured products and cheese under co-packing agreements, with a 6,000-position freezer and cooler warehouse on the same site.

    The question the lender and USDA needed answered

    A plant built and owned by a newly formed company is a new business, so Part 5001 requires a feasibility study by an independent qualified consultant acceptable to the Agency for any B&I loan over $1,000,000, with the Agency setting the scope [1]. A combined project raised a harder question than whether the study was required. Two businesses share one loan: a dairy plant whose revenue depends on how much milk arrives and at what fee it is processed, and a cold storage warehouse whose revenue depends on how fast pallet positions fill. They ramp at different speeds, they carry different risks, and a lender has to know whether each pays its share of the debt or whether one is carrying the other.

    RuleRequirementEffect on this study
    7 CFR 5001.306(a)(3)(i)Independent study required for a loan over $1,000,000 to a new businessStudy mandatory
    7 CFR 5001.205(e)(2)Guarantee before completion: confirmed budget and timetable, overrun contingency, start-up working capital, fixed-price contract, equity firstBudget, schedule and start-up reserve sized in the study
    7 CFR 5001.202Quarterly cash flow through start-up for early-guarantee construction loans; seasonal borrowers; projections without history substantiatedMonthly throughput and quarterly absorption models
    7 CFR 5001.105(d)(2) and (3)10% equity if sales contracts cover debt service for the loan term; otherwise 25% for a new build with an early guaranteeContract terms tested against the equity rule
    7 CFR 5001.203Appraisal with as-is and prospective values; going concern deductedSpecial-purpose real estate discounted
    7 CFR 5001.3Rural area testSite screened on the eligibility map

    Project description (modeled)

    ComponentModeled scopeDriver
    Milk receiving and processingDesign capacity 300,000 lb of milk a day; receiving at about 25,000 lb an hour over 12 hoursPeak-month milk under contract
    Processing building22,000 sq ft of sanitary constructionProduct lines and code requirements
    ProductsCultured products and cheese made for customers under co-packing agreementsContracts with cooperatives and brands
    Cold storage40,000 sq ft: 26,000 sq ft freezer, 14,000 sq ft cooler; 6,000 pallet positionsPlant output plus regional shippers
    RefrigerationOne central ammonia system serving plant and warehouseShared capital and operating cost
    WastewaterOn-site pretreatment before discharge to the cityDischarge permit terms
    PhaseTiming (modeled)Milestone
    Design, permits, contractsMonths 1 to 10 before closingDischarge permit path, co-packing agreements, design-build price
    ClosingNote month 0Equity spent first; guarantee issued before completion
    ConstructionNote months 1 to 15Monthly draws with inspection
    Commissioning and trialsMonths 14 to 15Product trials, sanitation validation, hiring
    Operating year 1, interest-onlyMonths 16 to 27Anchor contracts start; warehouse leases up
    Full paymentsFrom month 28Within the 3-year limit of 5001.402

    Project cost and sources and uses

    Every line below is an assumption with a range, and the last column names the document a real study uses instead: a design-build price for the buildings, equipment quotes with performance terms, a refrigeration contractor's bid, an engineer's pretreatment design, and the utility's capacity letter.

    Line itemBasisModeled costAssumption rangeHow a real study sources it
    Land (about 7 acres, industrial zoning)allowance$1,050,000$700,000 to $1,500,000Appraisal; purchase contract
    Site work, paving, truck courts, utilitiesallowance$1,650,000$1,100,000 to $2,300,000Civil engineer estimate
    Wastewater pretreatment (equalization, dissolved air flotation)allowance$1,350,000$900,000 to $2,000,000Engineer design; city discharge permit terms
    Processing building, sanitary construction22,000 sq ft x $340$7,480,000$280 to $420 per sq ftDesign-build bid
    Milk receiving bays, silos and raw milk storageequipment$1,100,000$800,000 to $1,500,000Equipment quotes with performance terms
    Pasteurizer (HTST) and separatorequipment$1,250,000$900,000 to $1,700,000Equipment quotes with performance terms
    Cultured product and cheese vats, fermentation tanksequipment$1,600,000$1,200,000 to $2,200,000Equipment quotes with performance terms
    Filling and packaging linesequipment$1,400,000$1,000,000 to $2,000,000Equipment quotes with performance terms
    Clean-in-place (CIP) systemequipment$550,000$400,000 to $800,000Equipment quotes with performance terms
    Cold storage building (26,000 sq ft freezer, 14,000 sq ft cooler), insulated panel40,000 sq ft x $160$6,400,000$130 to $210 per sq ftDesign-build bid
    Central ammonia refrigeration (plant and warehouse)allowance$3,200,000$2,400,000 to $4,200,000Refrigeration contractor bid
    Pallet racking6,000 positions x $95$570,000$70 to $130 per positionRacking quote
    Dock doors, levelers, lift trucksallowance$550,000$400,000 to $800,000Vendor quotes
    Electrical service, switchgear and backup generatorallowance$850,000$600,000 to $1,300,000Utility letter; electrical bid
    Hard cost subtotal (excluding land)$27,950,000
    Architecture, process and refrigeration engineering6% of buildings, site and refrigeration$1,205,0005% to 8%Design contracts
    Permits, discharge permit, connection feesallowance$380,000$200,000 to $600,000City and state fee schedules
    Legal, appraisal, feasibility study, title, closingallowance$300,000$200,000 to $420,000Engagement letters
    Pre-commissioning, trials, hiring and trainingallowance$450,000$300,000 to $700,000Operator start-up budget
    Contingency7% of buildings, site and refrigeration; 5% of equipment$1,799,0005% to 10%Lender and engineer review
    B&I guarantee fee, issued before construction completion (3.5%)$22,000,000 x 80% x 3.5%$616,000Fixed by FY2026 notice91 FR 11272
    Interest during constructionaverage 48% drawn for 15 months at 7.25%$957,000Depends on draw scheduleLender draw schedule
    Working capital and start-up reserveallowance$1,500,000Sized from monthly ramp modelMonthly cash flow below
    Total project cost$36,207,000

    The modeled project costs $36,207,000. Process equipment is only $5,900,000 of that; the buildings, refrigeration and wastewater pretreatment ($1,350,000) are where a dairy plant's money goes, and pretreatment is the line most often missing from first budgets. Contingency of $1,799,000 reflects new construction with sanitary finishes and an ammonia system. The guarantee fee ($616,000) is the standard 3.0% plus 0.50% for a guarantee issued before construction completion; the reduced 1.0% fee is available only for loans that meet the Agency's reduced-fee criteria, which the model does not assume [2].

    SourcesAmountShareUsesAmount
    B&I guaranteed loan (80% guaranteed)$22,000,00060.8%Land, buildings, equipment, refrigeration$29,000,000
    Owner equity (dairy producers and operating partner)$14,207,00039.2%Design, permits, legal, start-up, contingency$4,134,000
    Guarantee fee and construction interest$1,573,000
    Working capital and start-up reserve$1,500,000
    Total sources$36,207,000100.0%Total uses$36,207,000

    The owners contribute $14,207,000 (39.2% of cost), well above the $9,051,750 minimum for a new business with an early guarantee. The working capital and start-up reserve of $1,500,000 is sized from the ramp model below, not chosen as a round number.

    Market analysis

    Washington cold storage supply

    MeasureWashingtonUnited States
    Establishments, 2019 → 202352 → 52 (+0.0%)1,350 → 1,367
    Per 100,000 residents (2023)0.70.4
    Average employees per establishment33.248.4
    Average annual pay per employee$62,389$56,901
    Share of establishments in non-metro counties16.7% (7 in 1 counties)
    Share of state population in non-metro counties (2025)10.2%

    Non-metro counties with the most refrigerated warehousing (2023): Grant County (7).

    Sources: U.S. Census Bureau, County Business Patterns 2019 and 2023 (state and county files; establishments with paid employees; employment and payroll suppressed in some cells); Vintage 2025 county population estimates; OMB metropolitan statistical area delineation, July 2023. Non-metro county is a proxy for USDA rural eligibility, not the eligibility test itself.

    Washington had 52 refrigerated warehouses with paid employees in both 2019 and 2023, 0.7 per 100,000 residents against 0.4 nationally, so the state has more public cold storage per head than the country but added none in four years. Its warehouses are smaller than the national average (33.2 employees against 48.4) and pay more ($62,389 against $56,901). Only 7 sit in non-metro counties, all in Grant County in the Columbia Basin. West of the Cascades, public cold storage is a metropolitan business, which is the gap a Skagit County warehouse would fill.

    Washington food processing supply

    MeasureWashingtonUnited States
    Establishments, 2019 → 2023760 → 828 (+8.9%)24,589 → 27,414
    Per 100,000 residents (2023)10.68.1
    Average employees per establishment37.842.0
    Average annual pay per employee$58,203$58,248
    Share of establishments in non-metro counties13.6% (114 in 14 counties)
    Share of state population in non-metro counties (2025)10.2%

    Non-metro counties with the most food manufacturing (excluding meat) (2023): Grant County (17); Adams County (11); Pacific County (10); Clallam County (9); Klickitat County (9); Lewis County (9).

    Sources: U.S. Census Bureau, County Business Patterns 2019 and 2023 (state and county files; establishments with paid employees; employment and payroll suppressed in some cells); Vintage 2025 county population estimates; OMB metropolitan statistical area delineation, July 2023. Non-metro county is a proxy for USDA rural eligibility, not the eligibility test itself.

    Food manufacturing outside the meat sector grew 8.9% in Washington from 2019 to 2023, to 828 plants, at 10.6 per 100,000 residents against 8.1 nationally. Plants average 37.8 employees and pay $58,203, almost exactly the national figure. Those two pay levels, $58,203 for processing and $62,389 for refrigerated warehousing, are the wage benchmarks the model uses.

    Regional comparison

    StateRefrigerated warehouses, 2023Per 100,000Employees eachAverage payNon-metro shareFood plants (excl. meat)Food plants per 100,000
    Washington520.6633.2$62,38916.7%82810.6
    Oregon250.5922.0$58,5930.0%62514.7
    Idaho130.6657.3$50,19657.1%23111.7
    California2110.5438.3$59,3450.0%3,8559.8
    United States1,3670.4148.4$56,90127,4148.1

    Washington and Idaho have the most refrigerated warehousing per resident in the region. Idaho's warehouses are large and mostly rural; Washington's are mid-sized and metropolitan; Oregon and California report none in non-metro counties. For a Skagit County project the regional table makes one point: a reviewer will not find rural public cold storage comparables west of the Cascades, so absorption has to be supported by named customers rather than by market vacancy statistics.

    Skagit County and the north Puget Sound region

    CountyOMB 2023Population, 2025Food plants (NAICS 311)Food employment (noise)Refrigerated warehousesWarehouse employees
    Skagit CountyMetro132,975311,175 (high)not shownn/a
    Whatcom CountyMetro236,392602,207 (low)4119
    Snohomish CountyMetro870,656661,734 (low)not shownn/a
    Island CountyNon-metro85,657847 (moderate)not shownn/a
    Grant CountyNon-metro105,727171,859 (low)7265
    Yakima CountyMetro259,185473,211 (low)6176
    Benton CountyMetro221,722201,354 (moderate)6160
    Franklin CountyMetro102,612163,192 (low)392

    Skagit County has 31 food plants with 1,175 employees (high noise) and no refrigerated warehouse large enough to appear in the county file. Whatcom County to the north has four refrigerated warehouses; Snohomish County to the south has none shown, despite 66 food plants. Cold storage in the region sits at the ports and in the Columbia Basin, and food processors in the Skagit and Whatcom valleys truck product to it. The county's population is 132,975, up 2.7% since 2020, but the market for this project is processors and dairies, not residents.

    Milk supply

    The engagement record cites Pacific Northwest Federal Milk Marketing Order 124 data: 6.76 billion pounds of milk pooled in 2025 across 17 regulated plants, monthly receipts from 480.3 million pounds in September to 692.5 million pounds in March, a March peak 44% above the September trough, and Class I utilization of 21.6%. These figures could not be confirmed from a primary source for this page, and they describe 2025, after the study was prepared, so they are shown as market context. The model uses the record's 1.44 peak-to-trough ratio to shape monthly milk deliveries, because seasonality is what sizes a dairy plant.

    MonthSeasonal factorYear 4 lb a dayYear 4 utilizationYear 5 lb a dayYear 5 utilizationFlag
    Jan1.05225,75075.2%231,00077.0%
    Feb1.04223,60074.5%228,80076.3%
    Mar1.18253,70084.6%259,60086.5%
    Apr1.15247,25082.4%253,00084.3%
    May1.12240,80080.3%246,40082.1%
    Jun1.02219,30073.1%224,40074.8%
    Jul0.93199,95066.6%204,60068.2%
    Aug0.86184,90061.6%189,20063.1%
    Sep0.82176,30058.8%180,40060.1%
    Oct0.88189,20063.1%193,60064.5%
    Nov0.93199,95066.6%204,60068.2%
    Dec1.02219,30073.1%224,40074.8%

    At the year-4 average of 215,000 lb a day, March deliveries reach 253,700 lb a day and September falls to 176,300. A plant sized for the average would turn milk away every spring; a plant sized for the peak runs well below capacity for half the year. The design capacity of 300,000 lb a day handles the modeled peak with room to spare, and the table shows the plant could take an average of up to 254,237 lb a day before March deliveries exceed it. That ceiling is the number a sponsor needs before signing more co-packing volume.

    Rural area test

    PlaceCensus base 2020Estimate 20255001.3 screen
    Everett, WA110,514113,567Over 50,000: excluded with its contiguous urbanized area
    Bellingham, WA91,47096,395Over 50,000: excluded with its contiguous urbanized area
    Marysville, WA70,71577,686Over 50,000: excluded with its contiguous urbanized area
    Mount Vernon, WA35,23035,193Under 50,000: passes on population; contiguity decides
    Anacortes, WA17,62918,080Under 50,000: passes on population; contiguity decides
    Sedro-Woolley, WA12,45013,308Under 50,000: passes on population; contiguity decides
    Burlington, WA9,16511,356Under 50,000: passes on population; contiguity decides

    Mount Vernon had 35,193 residents in the 2025 estimate and passes on population; Bellingham, Everett and Marysville are over 50,000. The site's Washington guide screens Mount Vernon as eligible and notes that some smaller towns near the larger cities, such as Arlington, are excluded by contiguity [11]. Skagit County is metropolitan in the OMB delineation, a county proxy that does not decide the B&I test; the study recorded the parcel's status from the USDA eligibility map with a date.

    Financing benchmarks

    Period7(a) loans7(a) dollars504 loans504 dollars
    FY2010 to FY20163$4.8 million0$0
    FY2017 to FY20190$00$0
    FY2020 to FY20232$5.6 million0$0
    FY2024 to FY20260$00$0

    Average 7(a) loan, FY2020 to FY2026: $2.8 million. Washington had fewer than 30 seasoned 7(a) loans for refrigerated warehousing; nationally, 5.3% of 38 FY2010 to FY2016 loans were charged off, on average 76 months after approval.

    Source: SBA 7(a) and 504 FOIA loan data, as of 30 Sep 2026 (project state; disbursed loans only; cancelled and undisbursed loans excluded).

    Period7(a) loans7(a) dollars504 loans504 dollars
    FY2010 to FY201690$40.0 million11$10.0 million
    FY2017 to FY201944$25.6 million5$8.7 million
    FY2020 to FY202342$12.5 million4$2.9 million
    FY2024 to FY202654$26.5 million2$2.3 million

    Average 7(a) loan, FY2020 to FY2026: $406,070. Average 504 loan: $870,333. Of the 90 7(a) loans approved in FY2010 to FY2016 for Washington food manufacturing (excluding meat), 2.2% were charged off (national: 7.4% of 3,150), on average 52 months after approval.

    Source: SBA 7(a) and 504 FOIA loan data, as of 30 Sep 2026 (project state; disbursed loans only; cancelled and undisbursed loans excluded).

    SBA has barely lent to Washington refrigerated warehouses (five 7(a) loans since FY2010), so there is no local loss history for the asset; nationally, 5.3% of seasoned refrigerated warehouse 7(a) loans were charged off. Washington food manufacturers have a low seasoned loss rate (2.2% against 7.4% nationally). USAspending lists 14 B&I loans and 156 REAP grants in Washington for FY2024 to FY2026 (counts may be incomplete). The site's Washington guide also records a 2023 REAP energy grant of $979,000 to a Skagit County seed company [11], evidence that Rural Development finances agricultural businesses in the county.

    Financial feasibility

    Throughput and absorption assumptions

    Throughput and absorption assumption (modeled)ValueEvidence a real study uses
    Plant design capacity300,000 lb of milk a day (about 25,000 lb an hour over a 12-hour receiving window)Equipment ratings; process engineer
    Average milk processed, years 1 to 5165,000, 190,000, 205,000, 215,000, 220,000 lb a daySigned co-packing agreements and letters of intent
    Operating days350 a yearPlant schedule
    Co-packing fee$10.75 per cwt of milk processed, +2.5% a yearContract terms; competing co-packer quotes
    Cold storage positions6,000 (26,000 sq ft freezer, 14,000 sq ft cooler)Racking layout
    Cold storage occupancy, years 1 to 540%, 60%, 75%, 85%, 88%Anchor storage agreements; regional vacancy survey
    Storage rate$23.00 per position per month, +3% a yearRate sheets of regional warehouses
    Handling$19.00 per pallet in and out; 7 turns a yearCustomer inventory data
    Accessorial charges6% of storage and handlingRate sheets (blast freezing, labelling, cross-dock)
    Plant labour26 FTE plus 0.09 per 1,000 lb a day, at $58,203 plus 28% benefitsWashington food manufacturing pay, CBP 2023 (pack)
    Warehouse labour6 FTE plus 1.2 per 1,000 occupied positions, at $62,389 plus 28%Washington refrigerated warehousing pay, CBP 2023 (pack)
    Plant utilities and wastewater$1.35 per cwtUtility tariffs; discharge permit surcharges
    Warehouse power1,000,000 kWh fixed plus 420,000 kWh at full occupancy, at 9.5 centsRefrigeration load calculation; utility tariff
    Insurance, property tax, management and administration$1,235,000 in year 1, +2.5% a yearQuotes; assessor; staffing plan

    Electricity is modeled at 9.5 cents per kWh, against a U.S. industrial average of 9.09 cents for January to August 2026 [10]. A real study uses the serving utility's tariff, including demand charges, because refrigeration runs around the clock.

    Cold storage absorption

    QuarterOccupancyPositions occupiedCold storage revenue
    Year 1 Q125%1,500$162,578
    Year 1 Q236%2,160$234,112
    Year 1 Q345%2,700$292,640
    Year 1 Q454%3,240$351,167
    Year 2 Q157%3,420$381,797
    Year 2 Q260%3,600$401,892
    Year 2 Q362%3,720$415,288
    Year 2 Q461%3,660$408,590

    The warehouse opens with the plant's own customers' finished goods and fills with regional shippers over two years. The quarterly path matters because Part 5001 asks for quarterly cash flow through start-up on a construction loan with an early guarantee [1].

    Debt terms

    Term (model)ValueRule or basis
    Loan amount$22,000,000$5 million to $25 million tier; B&I cap $25 million (5001.406(c))
    Guarantee80%: $17,600,000 guaranteed, $4,400,000 unguaranteedFY2026 notice
    Guarantee fee3.0% plus 0.50% for a guarantee issued before construction completion: $616,000FY2026 notice; 5001.454
    Annual retention fee0.55% of guaranteed principal outstanding: $95,375 in year 2FY2026 notice; 5001.455
    Rate7.25% fixed (illustrative assumption)Negotiated (5001.401)
    Interest-only15 months of construction and the first 12 operating months; first full payment in month 28Within 3 years of the note (5001.402)
    Amortization25 years; monthly payment $159,018Blended useful life of buildings, refrigeration and equipment (5001.402)

    Five-year pro forma

    Operating yearYear 1Year 2Year 3Year 4Year 5
    Milk processed, lb per day (average)165,000190,000205,000215,000220,000
    Plant utilization of 300,000 lb a day55.0%63.3%68.3%71.7%73.3%
    Co-packing fee per cwt$10.75$11.02$11.29$11.58$11.87
    Processing revenue$6,208,125$7,327,469$8,103,602$8,711,372$9,136,811
    Cold storage occupancy40.0%60.0%75.0%85.0%88.0%
    Storage revenue$662,400$1,023,408$1,317,638$1,538,123$1,640,181
    Handling revenue$319,200$493,164$634,949$741,197$790,377
    Accessorial revenue$58,896$90,994$117,155$136,759$145,834
    Total revenue$7,248,621$8,935,035$10,173,344$11,127,451$11,713,204
    Plant labour$3,043,332$3,291,231$3,479,179$3,638,364$3,766,329
    Plant utilities and wastewater$779,625$920,194$1,017,662$1,093,986$1,147,413
    Cleaning chemicals, lab, supplies$317,625$374,894$414,603$445,698$467,465
    Plant maintenance$118,000$147,500$177,000$177,000$177,000
    Warehouse labour$709,136$844,734$956,465$1,042,295$1,087,392
    Warehouse refrigeration power$110,960$121,913$131,249$138,827$143,619
    Warehouse supplies, repairs, lift truck costs$139,200$152,520$163,898$173,164$179,083
    Insurance, property tax, management and administration$1,235,000$1,265,875$1,297,522$1,329,960$1,363,209
    Replacement reserve (1.5% of revenue)$108,729$134,026$152,600$166,912$175,698
    Net operating income$687,014$1,682,148$2,383,167$2,921,244$3,205,996
    Debt service (year 1 interest-only)$1,595,000$1,908,210$1,908,210$1,908,210$1,908,210
    Retention fee (0.55% of guaranteed balance)$96,800$95,375$93,843$92,197$90,427
    DSCR0.43x0.88x1.25x1.53x1.68x
    DSCR after retention fee0.41x0.84x1.19x1.46x1.60x

    The combined project reaches 1.25x coverage in year 3 and 1.53x at stabilization in year 4, when revenue is $11,127,451 and NOI $2,921,244. The first two years are the problem. Year-1 NOI of $687,014 covers interest only 0.43x, and in year 2 NOI of $1,682,148 covers full payments 0.88x. The cumulative shortfall over the two years is $1,134,047 ($907,986 in year 1 and $226,062 in year 2), which is why the start-up reserve is $1,500,000. The study's recommendation was to extend interest-only to the three-year limit in Part 5001, which here allows about eight more months, or to hold the reserve at closing; the model shows the reserve.

    Break-even and contract coverage

    Break-even (year 4 prices; other driver at base case)For 1.00xFor 1.25xBase case
    Milk processed, lb a day175,317 (58.4% of capacity)194,004 (64.7%)215,000 (71.7%)
    Cold storage occupancy36.4%59.3%85.0%
    Segment test (year 4 prices)Cold storageDairy processing
    Share of capital (direct cost plus allocated site and electrical)35.2%64.8%
    Allocated debt service$671,810$1,236,400
    Segment NOI at base case$557,322$2,363,923
    Segment DSCR at base case0.83x1.91x
    Break-even for 1.00x90.5% occupancy170,833 lb a day (56.9% of capacity)
    Level for 1.25x98.5% occupancy182,941 lb a day (61.0%)

    The segment test is the central finding. Taken together, the project breaks even at 175,317 lb of milk a day or, holding milk at base, at 36.4% warehouse occupancy, so the warehouse looks easy. Taken on its own, with 35.2% of the capital and $671,810 of the debt service, the warehouse covers its share only 0.83x at 85% occupancy and needs 90.5% occupancy to break even. That is consistent with the engagement card's statement that break-even occupancy was benchmarked at 85% or more. The dairy plant covers its share 1.91x. In other words, the warehouse is justified as infrastructure for the plant's customers, not as a stand-alone public warehouse, and the study had to say so plainly.

    Revenue under contract, year 4 (modeled)RevenueShare under signed agreementsContracted revenue
    Co-packing (processing fees)$8,711,37280%$6,969,098
    Cold storage (anchor storage agreements)$2,416,07845%$1,087,235
    Total$11,127,45172.4%$8,056,333
    Operating costs, year 4$8,206,206
    Contracted revenue as a share of operating costs98.2%
    Contracted revenue as a share of operating costs plus debt service79.7%

    At stabilization 72.4% of revenue is under signed agreements. Contracted revenue alone covers 98.2% of operating costs and 79.7% of operating costs plus debt service, so the remaining coverage depends on uncontracted storage and processing. The lender's covenant package follows from that: minimum contracted volume, notice periods long enough to replace a customer, and reporting on contract renewals.

    Sensitivity and stress tests

    Milk processed (lb a day) \ cold storage occupancy85%75%65%55%
    220,0001.60x1.49x1.38x1.27x
    200,0001.33x1.22x1.11x1.00x
    180,0001.06x0.95x0.84x0.73x
    160,0000.80x0.69x0.58x0.47x
    140,0000.53x0.42x0.31x0.20x
    Scenario (year 4)NOIDebt serviceDSCR
    Base case, year 4$2,921,244$1,908,2101.53x
    Co-packing fee 10% lower$2,063,174$1,908,2101.08x
    Storage and handling rates 10% lower$2,683,261$1,908,2101.41x
    Warehouse power price 40% higher$2,865,713$1,908,2101.50x
    Labour cost 10% higher$2,453,178$1,908,2101.29x
    Rate 8.25% (+1 point)$2,921,244$2,081,5081.40x
    Rate 9.25% (+2 points)$2,921,244$2,260,8481.29x
    Construction overrun of 10% ($2,008,000) added to the loan$2,921,244$2,082,3781.40x
    Largest co-packing customer (35% of volume) leaves$1,000,236$1,908,2100.52x

    The project's weak points are concentration and fee. If the largest co-packing customer, modeled at 35% of volume, leaves, coverage falls to 0.52x. A 10% lower co-packing fee gives 1.08x. Higher labour costs (10%) give 1.29x. Energy and storage rates matter less than a reader of cold storage studies might expect: a 40% rise in warehouse power prices only moves coverage to 1.50x, because the warehouse is a minority of the revenue. A one-point rate rise gives 1.40x, two points 1.29x, and a 10% overrun of $2,008,000 financed with more debt gives 1.40x.

    Equity test

    New-business testRequiredModeledResult
    5001.105(d)(3): construction, guarantee before completion: 25% of project cost$9,051,750$14,207,000Pass
    5001.105(d)(3) alternative: 25% balance-sheet equity (debt to equity at most 3 to 1)25% of assets39.2%Pass
    5001.105(d)(2): 10% if sales contracts cover debt service for at least the loan term$3,620,700Co-packing contracts run 5 years in the model, shorter than the 25-year loanNot available
    5001.205(e)(2): equity injected before any guaranteed loan fundsTiming testFirst draws are equityStructured

    The 10% equity route for new businesses with sales contracts applies only when the contracts are adequate for debt service and run at least as long as the loan [1]. Co-packing agreements of five years do not meet that test for a 25-year loan, so the 25% rule for a new build with an early guarantee applies.

    Collateral

    Collateral (modeled)ValueDiscount or treatmentLendable value
    Land, as is$1,050,000Included in real estate below
    Real estate at completion (special-purpose food plant and cold storage), prospective$21,500,00075% (assumption)$16,125,000
    Process equipment, orderly liquidation value$2,065,00035% of cost already applied$2,065,000
    Discounted collateral$18,190,000
    Loan$22,000,000
    Discounted coverage0.83x

    A dairy plant with a freezer warehouse is special-purpose real estate, so the appraisal's prospective value carries a heavier discount than a general warehouse would, and process equipment is valued at orderly liquidation, not cost. In the model discounted collateral covers the loan 0.83x. The shortfall is the price of a specialised asset; the guarantee, the equity and the contracts carry the lender through it, and the study shows each so the credit memo can.

    Technical and environmental feasibility

    The engagement card states that the technical work tested compliance with 7 CFR part 58, subpart B, the general specifications for dairy plants approved for USDA inspection and grading service, which cover floors, drains, refrigeration and related construction. In a modeled study, the technical section reviews the plant layout against those specifications and the state's dairy licensing, the separation of raw and finished product areas, clean-in-place design, the ammonia system's design and its process safety documentation, and the wastewater pretreatment design against the city's discharge limits. For the warehouse it reviews floor heave protection under the freezer, door and dock design, racking layout and the backup power that protects stored product.

    Environmental review is a separate Agency requirement from the five feasibility components. For this project its likely questions are the discharge permit, stormwater, ammonia storage, truck traffic, and, in a river valley, floodplain status of the parcel. Each one has a schedule effect that belongs in the timetable the early guarantee requires.

    Management and governance feasibility

    A new company has no operating record, so management feasibility rests on the people and the agreements. The study reviewed the plant manager's and quality manager's experience with licensed dairy plants, the warehouse manager's experience with food-grade cold storage, the co-packing agreements (volume commitments, fee escalation, term, termination and who owns the product), and the owners' governance: who decides on new contracts, capital calls and distributions. The engagement card notes that key personnel and foreign-adversary screening were part of the management section.

    Part 5001 adds ownership tests. Owners of 20% or more give guarantees in proportion to their ownership for the life of the loan, and the borrower and its controlling owners must be free of federal judgments, delinquent federal debt and debarment [1]. Where dairy producers own the company, the study shows each owner's share and guarantee capacity, because the guarantee requirement falls on every owner at 20% or more.

    Economic and community impact (modeled)

    Effect (modeled)AmountBasis
    Permanent jobs, year 4 (FTE)57Staffing model above
    Wages, year 4 (before benefits)$3,656,765FTE x Washington pay benchmarks, +2.5% a year
    Milk processed a year, year 475,250,000 lbThroughput model
    Cold storage positions available to regional shippers6,000Racking layout
    Construction spending (land and hard costs)$29,000,000Budget
    Skagit County food manufacturing today31 plants, 1,175 employees (high noise)CBP 2023

    The modeled project employs about 57 people by year 4, with wages of about $3,656,765 at Washington processing and warehousing pay levels. Its larger effect is on the dairies and processors around it: processing capacity and cold storage that do not exist in the county today, which shortens haul distances for milk and finished goods. A real study measures that from the customers' own shipping data.

    Risks and mitigants

    RiskEffect in the modelMitigant
    Loss of the largest co-packing customerCoverage 0.52xContract notice periods; diversified customer base; volume covenants
    Co-packing fee pressure1.08x at -10% feeFee escalation clauses; cost pass-through for utilities
    Slow rampShortfall of $1,134,047 over years 1 and 2Start-up reserve of $1,500,000; extended interest-only
    Warehouse lease-upSegment break-even at 90.5% occupancyAnchor storage agreements; warehouse treated as plant infrastructure
    Spring milk peakMarch deliveries 253,700 lb a day in year 4Capacity of 300,000 lb a day; volume ceiling of 254,237 lb average
    Labour1.29x with labour 10% higherStaffing plan at local wages; automation in packaging
    Energy cost1.50x with warehouse power 40% higherUtility tariff review; REAP efficiency grant after 12 months of data [15]
    Construction overrun1.40x if 10% is debt-financedDesign-build contract; contingency; equity for overruns
    Food safety and licensingLost productionDesign review against part 58 specifications; trials before first contract volume
    CollateralDiscounted coverage 0.83xEquity; owner guarantees; contracts

    What the five Part 5001 components showed

    Part 5001 organises an acceptable study into economic, market, technical, financial and management feasibility [3]. The engagement card lists environmental as a fifth heading; this page treats environmental review as the separate Agency requirement it is.

    ComponentWhat the modeled study foundWhat a reviewer checks
    EconomicNo public cold storage in the county file for Skagit County; local processors and dairies ship out of the countyCustomer shipping data; haul distances
    MarketMilk supply seasonal (peak 1.44 times trough); co-packing demand under contract for 72.4% of stabilized revenueMilk supply agreements; co-packing contracts; warehouse anchor agreements
    TechnicalCapacity of 300,000 lb a day covers the spring peak; part 58 design review; pretreatment pricedEngineering, permits, equipment terms
    Financial1.53x stabilized; years 1 and 2 below 1.00x and funded by reserve; warehouse alone 0.83xMonthly and quarterly cash flow; segment tests; stress
    ManagementExperienced plant, quality and warehouse managers; clear owner governanceRésumés with plant results; agreements; guarantees

    Combined processing and cold storage studies are sent back for recurring reasons:

    1. One blended pro forma that hides a segment that does not pay its share of the debt.
    2. Throughput modeled on annual averages, ignoring the spring milk peak.
    3. Warehouse absorption from market vacancy data when no rural comparables exist.
    4. Co-packing revenue without signed agreements, or agreements shorter than the reviewer assumed.
    5. No wastewater pretreatment in the budget.
    6. Year-1 and year-2 shortfalls left unfunded.
    7. A fee assumption of 1.0% when the loan does not meet the reduced-fee criteria.

    Program terms that applied

    FY2026 B&I termValueSource
    Guarantee, loans of $5 million to $25 million80%91 FR 11272 [2]
    Guarantee fee3.0% of the guaranteed portion91 FR 11272 [2]
    Extra fee, guarantee issued before construction completion0.50%91 FR 11272 [2]
    Reduced-fee option1.0% fee, 0.50% retention, 80% guarantee, for loans meeting the Agency's criteria91 FR 11272 [2]
    Annual retention fee0.55% of guaranteed principal outstanding at 31 December91 FR 11272 [2]; 5001.455 [1]
    Maximum loan$25 million per borrower5001.406(c) [1]
    TermUseful life, up to 40 years; no balloon; first full payment within 3 years5001.402 [1]
    Equity, new business10% with qualifying long-term sales contracts; 25% for construction with an early guarantee; otherwise 20% balance-sheet or 25% of cost5001.105(d) [1]
    Feasibility studyRequired over $1,000,000 for a new business5001.306(a)(3)(i) [1]
    Rural areaOutside cities over 50,000 and their contiguous urbanized areas5001.3 [1]

    The FY2026 notice took effect on 1 October 2025. A study prepared in 2024 worked under that year's notice, so the percentages and fees shown here are current terms for a new application, not the engagement's.

    Lessons for sponsors of similar projects

    1. Test each business on its own. A combined project can hide a segment that does not carry its debt; show the segment test before the lender builds one.
    2. Size the plant to the peak month. Spring milk sets capacity; the average sets revenue.
    3. Put the warehouse's purpose in writing. If it exists to serve the plant's customers, say so and support it with their storage agreements.
    4. Fund the ramp. Two years below 1.00x is normal for a new processing plant; an unfunded shortfall is not.
    5. Watch customer concentration. One customer at 35% of volume is the largest single risk in this model.
    6. Price pretreatment early. Wastewater is a permit condition and a large line item.
    7. Use the standard fee unless you qualify for the reduced one. A 1.0% fee assumption understates cost when the loan does not meet the criteria.

    If you are planning processing or cold storage capacity with a B&I guarantee, a USDA feasibility study consultant can build the throughput, absorption and segment tests your lender will ask for. Standard B&I studies take six to seven weeks and complex ones seven to nine, with fees on the cost page [12]. Request a proposal for a fifteen-minute scoping call and a written, fixed-fee proposal [13].

    David Miller, CPA

    USDA Feasibility, Inc.

    Frequently Asked Questions

    Does a combined dairy plant and cold storage project need a feasibility study for B&I?

    Yes if the borrower is a new business and the loan is over $1,000,000: Part 5001 requires a study by an independent qualified consultant acceptable to the Agency, with scope set by the Agency [1]. A company formed to build and run the facility is a new business. Even for an existing company, a lender usually asks for one on a project of this size, because the two activities ramp at different speeds and the cash flow has no history to rely on.

    What is throughput and absorption modeling?

    Throughput modeling follows the milk: how much arrives each day and month, how much the plant can receive and process, and what fee it earns per hundredweight. Absorption modeling follows the warehouse: how fast pallet positions fill, at what rates, and what handling revenue they produce. In the model the plant processes 215,000 lb a day by year 4 with a March peak of 253,700 lb, and the warehouse fills from 25% in its first quarter to 85% by year 4.

    What occupancy does a cold storage warehouse need to break even?

    It depends on whether it is tested alone. In the model the combined project would break even with the warehouse only 36.4% full, because the dairy plant earns most of the income. Tested on its own share of capital and debt service, the warehouse needs 90.5% occupancy to break even and covers its share only 0.83x at 85%. The engagement card says break-even occupancy was benchmarked at 85% or more, which is consistent with a stand-alone test.

    Which guarantee fee applies: 1% or 3%?

    Under the FY2026 notice, a B&I loan of $5 million to $25 million carries an 80% guarantee with a 3.0% fee on the guaranteed portion and a 0.55% annual retention fee; an extra 0.50% applies if the guarantee is issued before construction is complete [2]. A reduced fee of 1.0% with a 0.50% retention fee exists for loans that meet the Agency's criteria. A pro forma should use 3.0% unless the loan is shown to qualify. On the modeled $22,000,000 loan the fee is $616,000.

    Can co-packing contracts reduce the equity requirement?

    They can, under one condition. Part 5001 lets a new business close with 10% equity if it has sales contracts adequate to service the debt and their term is at least as long as the loan [1]. Co-packing agreements usually run a few years, not the life of a 25-year loan, so most new plants with an early guarantee fall under the 25% rule. In the model the minimum is $9,051,750; the owners contribute $14,207,000.

    How does milk seasonality affect the feasibility study?

    It sets plant capacity and cash flow. The engagement record cites Order 124 receipts with a March peak 44% above the September trough. Applied to the model, a plant averaging 215,000 lb a day must handle about 253,700 lb a day in March and sees about 176,300 in September. Capacity of 300,000 lb a day covers the peak; the plant could take an average of up to 254,237 lb a day before March deliveries exceed it.

    Is Mount Vernon eligible for USDA B&I?

    Mount Vernon passes on population, with about 35,193 residents in the 2025 estimate, and the site's Washington guide screens it as eligible [11]. The B&I test in Part 5001 excludes cities over 50,000 and the urbanized areas contiguous to them [1]; Bellingham, Everett and Marysville are over the line, and some smaller towns near them are excluded by contiguity. Skagit County's metropolitan status is not the test. The study recorded the parcel's status from the USDA eligibility map with a date.

    Why does the model show coverage below 1.00x in the first two years?

    Because new plants ramp up. Milk volume and warehouse occupancy start low while labour and fixed costs start near full. In the model NOI covers interest 0.43x in year 1 and full payments 0.88x in year 2, a combined shortfall of $1,134,047. Part 5001 asks for working capital through start-up when the guarantee is issued before completion [1], so the study sized a $1,500,000 reserve from the monthly ramp and showed the lender how it is used.

    Can a Farm Credit institution make a USDA B&I guaranteed loan?

    The engagement record shows that this loan's lender was a Farm Credit System institution. Part 5001 sets the rules any approved lender must follow for B&I: credit evaluation, appraisal, collateral, equity and the feasibility study [1]. A sponsor should confirm with the lender that it is approved for OneRD guaranteed loans and how it handles the unguaranteed portion, because that affects pricing and covenants as much as the guarantee itself.

    What does a study like this cost and how long does it take?

    The site's cost page lists $6,900 to $12,500 for standard B&I studies and $10,500 to $14,500 for complex engagements, such as loans over $10 million, multi-use projects or markets with limited comparable data [12]. A combined processing and cold storage study in this loan range usually falls in the complex band. Standard studies take six to seven weeks and complex ones seven to nine, and every engagement includes all five Part 5001 components and an Excel workbook [12][13].

    Sources

    [1] 7 CFR part 5001, OneRD Guaranteed Loans (CFR 2026 edition, title 7 vol. 15, revised 1 Jan 2026), govinfo; sections 5001.3, 5001.105, 5001.127, 5001.202, 5001.203, 5001.204, 5001.205, 5001.306, 5001.401, 5001.402, 5001.406, 5001.454, 5001.455. https://www.govinfo.gov/content/pkg/CFR-2026-title7-vol15/xml/CFR-2026-title7-vol15-part5001.xml (accessed 11 Nov 2026)

    [2] USDA, OneRD Annual Notice of Guarantee Fee Rates, Periodic Retention Fee Rates, Loan Guarantee Percentage and Fee for Issuance of the Loan Note Guarantee Prior to Construction Completion for Fiscal Year 2026, 91 FR 11272 (9 Mar 2026). https://www.govinfo.gov/content/pkg/FR-2026-03-09/html/2026-04581.htm (accessed 6 Nov 2026)

    [3] OneRD Guaranteed Loan Regulation, 85 FR 42494 (14 Jul 2020), appendix A to subpart D of part 5001, Elements of an Acceptable Feasibility Study, pp. 42556-42557. https://www.govinfo.gov/content/pkg/FR-2020-07-14/pdf/2020-13991.pdf (accessed 7 Nov 2026)

    [4] U.S. Census Bureau, County Business Patterns 2019 and 2023, state and county files. https://www2.census.gov/programs-surveys/cbp/datasets/2023/cbp23st.zip ; https://www2.census.gov/programs-surveys/cbp/datasets/2023/cbp23co.zip ; https://www2.census.gov/programs-surveys/cbp/datasets/2019/cbp19st.zip (accessed 7 Nov 2026)

    [5] U.S. Census Bureau, Vintage 2025 county population estimates (co-est2025-alldata). https://www2.census.gov/programs-surveys/popest/datasets/2020-2025/counties/totals/co-est2025-alldata.csv (accessed 7 Nov 2026)

    [6] U.S. Census Bureau, Vintage 2025 city and town population estimates (sub-est2025). https://www2.census.gov/programs-surveys/popest/datasets/2020-2025/cities/totals/sub-est2025.csv (accessed 8 Nov 2026)

    [7] OMB metropolitan and micropolitan statistical area delineation file, July 2023 (list1_2023). https://www2.census.gov/programs-surveys/metro-micro/geographies/reference-files/2023/delineation-files/list1_2023.xlsx (accessed 7 Nov 2026)

    [8] U.S. Small Business Administration, 7(a) and 504 FOIA loan data, as of 30 Sep 2026. https://data.sba.gov/dataset/7-a-504-foia (accessed 7 Nov 2026)

    [9] USAspending.gov, award counts by place of performance for Assistance Listings 10.768 (B&I), 10.766 (Community Facilities) and 10.868 (REAP), FY2024 to FY2026. https://api.usaspending.gov/api/v2/search/spending_by_award_count/ (accessed 7 Nov 2026)

    [10] U.S. Energy Information Administration, Electric Power Monthly, table 5.6.B, Average Price of Electricity to Ultimate Customers by End-Use Sector, by State, year to date through August 2026. https://www.eia.gov/electricity/monthly/epm_table_grapher.php?t=epmt_5_6_b (accessed 11 Nov 2026)

    [11] usda-feasibility-study.com, Washington USDA feasibility study guide (site page; eligibility screen and precedent file attributed there to USDA Rural Development charts and releases). https://usda-feasibility-study.com/washington (read 7 Nov 2026)

    [12] usda-feasibility-study.com, USDA Feasibility Study Cost & Timeline (site page). https://usda-feasibility-study.com/usda-feasibility-study-cost (read 7 Nov 2026)

    [13] usda-feasibility-study.com, Contact & Request a Proposal (site page). https://usda-feasibility-study.com/contact (read 7 Nov 2026)

    [14] usda-feasibility-study.com, Selected Engagements (site page). https://usda-feasibility-study.com/engagements (read 7 Nov 2026)

    [15] USDA RBCS, Rural Energy for America Program (REAP), final rule with comment period, 91 FR 62600 (1 Oct 2026), effective 16 Oct 2026. https://www.govinfo.gov/content/pkg/FR-2026-10-01/html/2026-20178.htm (accessed 7 Nov 2026)

    Ready to Start Your USDA Project?

    Get your free consultation today and take the first step toward securing USDA funding for your rural development project.

    Our USDA feasibility study consultants scope every engagement against the five Part 5001 components in a free consultation.