Washington stores more fruit than any other state, yet almost none of that storage shows up where lenders look for evidence. The hub describes a cold chain built around controlled-atmosphere apple and cherry rooms, packing houses and frozen potato products, and reports that Washington grew about 69% of the US apple crop in 2024. Census, however, counts just 52 refrigerated warehousing businesses with paid employees, unchanged since 2019, and SBA records only five Washington cold storage 7(a) loans since FY2010 and no 504 loans. The reason is classification: most fruit storage belongs to packers and growers reported under agricultural or wholesale codes, not to stand-alone warehouses. For a Business and Industry (B&I) guarantee, that gap is the finding. A study has to build its evidence from the crop, the packers and the shippers, because public warehouse data and lending history will not carry the file.
Data current as of November 2026.
When a cold storage loan needs a USDA feasibility study, and which program fits
Once a newly formed cold storage company asks for a B&I guarantee above $1,000,000, the study becomes a requirement: 7 CFR 5001.306(a)(3)(i) calls for an independent consultant that the Agency accepts, working to the Agency's scope. Refrigerated buildings almost always cost more than that. A packer adding rooms is an existing business, but USDA can still require a study (5001.306(a)(3)(ii)), and a loan above $1,000,000 that adds more than 50 jobs needs Department of Labor concurrence (5001.306(a)(1)).
B&I offers 85% below $5 million and 80% from $5 million to $25 million in fiscal 2026 (91 FR 11272), and a storage company with long-term storage or throughput contracts covering debt service for the loan term qualifies for the 10% equity test in 5001.105(d)(2), which grower-packer agreements often satisfy. SBA has played little part in Washington cold storage. REAP can reimburse up to 25% of refrigeration efficiency or rooftop solar after twelve months of measured savings under the rule effective 16 October 2026; ground-mount solar on cropland is ineligible, which matters on orchard land. The hub describes Washington's Commercial PACER program, enacted under RCW 36.165, as a source for energy, water and seismic improvements in adopting counties. The site's engagements page describes the Food Supply Chain Guaranteed Loan Program as discontinued in 2023, so it is not treated as available here. A private warehouse is outside the Community Facilities programs altogether.
Screens: owner tests under 5001.127(a); separation of the storage business from orchard production under 5001.105(b)(7), revised in December 2025; and the hub's caution that controlled environment agriculture and biodigester projects face a guarantee pause from 14 April to 31 December 2026, which can catch storage projects tied to greenhouse or digester operations.
Cold storage in Washington: market evidence
Washington: refrigerated warehousing, supply and rural footprint
| Measure | Washington | United States |
|---|---|---|
| Establishments, 2019 → 2023 | 52 → 52 (+0.0%) | 1,350 → 1,367 |
| Per 100,000 residents (2023) | 0.7 | 0.4 |
| Average employees per establishment | 33.2 | 48.4 |
| Average annual pay per employee | $62,389 | $56,901 |
| Share of establishments in non-metro counties | 16.7% (7 in 1 counties) | |
| Share of state population in non-metro counties (2025) | 10.2% |
Non-metro counties with the most refrigerated warehousing (2023): Grant County (7).
Sources: U.S. Census Bureau, County Business Patterns 2019 and 2023 (state and county files; establishments with paid employees; employment and payroll suppressed in some cells); Vintage 2025 county population estimates; OMB metropolitan statistical area delineation, July 2023. Non-metro county is a proxy for USDA rural eligibility, not the eligibility test itself.
Even this partial count is telling. Washington has 0.7 refrigerated warehouses per 100,000 residents, almost double the national 0.4, the count held steady while the national total rose 1.3%, and workers earn $62,389, 9.6% above the national average. Washington warehouses are smaller than the national norm, 33.2 employees against 48.4, with payroll near $2,070,827 per site. First-quarter payroll is 24.3% of the year, so stand-alone warehouses staff fairly evenly; packing-house storage, which follows harvest and sales seasons, will not.
Computed: Washington refrigerated warehouses by number of employees, 2023 (Census CBP state file, NAICS 493120)
| Employees at the site | Refrigerated warehouses | Share of sized sites |
|---|---|---|
| 1 to 4 | 8 | 16.0% |
| 5 to 9 | 4 | 8.0% |
| 10 to 19 | 10 | 20.0% |
| 20 to 49 | 17 | 34.0% |
| 50 to 99 | 11 | 22.0% |
Computed: where Washington's county-placed refrigerated warehouses are, 2023 (Census CBP county file; Vintage 2025 population; OMB July 2023 status)
| County | OMB 2023 status | Refrigerated warehouses, 2023 | Residents, 2025 | Refrigerated warehouses per 100k residents |
|---|---|---|---|---|
| King County | Metropolitan | 11 | 2,344,939 | 0.5 |
| Grant County | Nonmetropolitan | 7 | 105,727 | 6.6 |
| Benton County | Metropolitan | 6 | 221,722 | 2.7 |
| Yakima County | Metropolitan | 6 | 259,185 | 2.3 |
| Pierce County | Metropolitan | 5 | 946,288 | 0.5 |
| Whatcom County | Metropolitan | 4 | 236,392 | 1.7 |
| Franklin County | Metropolitan | 3 | 102,612 | 2.9 |
Forty-two of the 52 warehouses are placed by county. King and Pierce hold 16, serving the ports and metro distribution; Grant County holds 7, the only non-metro concentration; and Benton, Yakima, Franklin and Whatcom hold 19 between them, all metropolitan under OMB but all agricultural counties. Ten warehouses are not placed. None of this captures the controlled-atmosphere rooms inside packing houses in the Wenatchee, Yakima and Columbia Basin districts.
Regional comparison: Washington against its neighbours
Computed from the Oregon, Idaho and Montana cold storage packs (their figures, same Census and SBA sources)
| State | Refrigerated warehouses 2019 → 2023 | Per 100k residents | Average employees | Average pay | Share in nonmetropolitan counties | SBA 7(a) / 504 loans, fiscal 2010 to 2026 |
|---|---|---|---|---|---|---|
| Washington | 52 → 52 | 0.7 | 33.2 | $62,389 | 16.7% (Grant County) | 5 / 0 |
| Oregon | 24 → 25 | 0.6 | 22.0 | $58,593 | 0.0% | 0 / 0 |
| Idaho | 13 → 13 | 0.7 | 57.3 | $50,196 | 57.1% (Cassia County) | 0 / 2 |
| Montana | 0 → 0 | 0.0 | n/a | n/a | n/a | 0 / 0 |
Washington has twice Oregon's number of refrigerated warehouses for less than twice the population, Idaho's are fewer but larger and mostly rural (Cassia County), and Montana reports none with payroll. SBA lending is nearly absent across all four states: five Washington 7(a) loans, two Idaho 504 loans, and nothing in Oregon or Montana. A Washington cold storage sponsor therefore cannot point to a regional lending record; the study's own evidence carries the credit case.
Rural footprint and B&I eligibility in Washington
Only Grant County appears among non-metro counties, with 7 warehouses, 6.6 per 100,000 residents. The fruit districts lie largely in metropolitan counties under OMB (Chelan, Yakima, Benton, Franklin, Walla Walla), which is why the non-metro share, 16.7%, says little about eligibility. Under 7 CFR 5001.3, eligibility turns on the parcel: outside cities above 50,000 at the 2020 Census and their contiguous urbanized areas, with no approval granted on later qualification. The Washington state page screens Wenatchee, Quincy, Moses Lake, Zillah, Sunnyside, Grandview, Granger, Toppenish and Wapato as eligible, and places Yakima, Union Gap, Selah, Moxee and Naches in the Yakima urbanized area; Pasco, Kennewick and Richland exceed 50,000. Many packing-house sites in the lower Yakima Valley and the Columbia Basin can therefore qualify, while storage on the edge of the Tri-Cities or Yakima will not.
Financing benchmarks: USDA B&I next to SBA
Washington: SBA lending to refrigerated warehousing
| Period | 7(a) loans | 7(a) dollars | 504 loans | 504 dollars |
|---|---|---|---|---|
| FY2010 to FY2016 | 3 | $4.8 million | 0 | $0 |
| FY2017 to FY2019 | 0 | $0 | 0 | $0 |
| FY2020 to FY2023 | 2 | $5.6 million | 0 | $0 |
| FY2024 to FY2026 | 0 | $0 | 0 | $0 |
Average 7(a) loan, FY2020 to FY2026: $2.8 million. Washington had fewer than 30 seasoned 7(a) loans for refrigerated warehousing; nationally, 5.3% of 38 FY2010 to FY2016 loans were charged off, on average 76 months after approval.
Source: SBA 7(a) and 504 FOIA loan data, as of 30 Sep 2026 (project state; disbursed loans only; cancelled and undisbursed loans excluded).
Five loans in seventeen years is too few to benchmark anything except their size: the two recent loans averaged $2.8 million, about twice the US FY2020 to FY2026 average of $1,424,256, and national 504 cold storage loans averaged $3,038,875. Nationally, 2 of 38 seasoned cold storage 7(a) loans (5.3%) were charged off about 76 months after approval. For B&I, the message is that a Washington cold storage project will usually be large, will often cross into the 80% tier, and will be judged on contracts rather than on any industry track record.
| Term | B&I rule | What it means for Washington cold storage |
|---|---|---|
| Guarantee | 85% under $5 million; 80% from $5 million to $25 million (91 FR 11272) | CA room additions may stay at 85%; new warehouses often fall to 80% |
| Fees | 3.0% upfront on the guaranteed share, 3.5% if the guarantee issues before construction is complete; 0.55% a year | $156,000 at closing on a $6.5 million loan |
| Term | Useful life up to 40 years, no balloon (5001.402) | Insulated buildings last; refrigeration plant needs a shorter blended term |
| Equity with contracts | 10% when storage or throughput contracts cover debt service for the loan term (5001.105(d)(2)) | Grower and packer agreements can qualify |
| Equity, other new owners | 20% balance sheet equity (4:1) or 25% of cost; 25% if issued before completion (5001.105(d)(3) and (4)) | Speculative public warehousing |
| Construction | Fixed-price contract, equity first, contingency and start-up working capital (5001.205(e)(2)) | Refrigeration commissioning delays are common |
| Collateral | Appraisal over $250,000; specialised buildings discounted (5001.203) | CA rooms have few alternative uses |
Worked example (illustrative)
Inputs. Washington's two recent loans are too few to average, so Loan A uses the US FY2020 to FY2026 cold storage 7(a) average of $1,424,256, rounded to $1,420,000. Loan B is an illustrative $6,500,000 controlled-atmosphere fruit storage build in the 80% tier. Both assume 7.50% fixed over 20 years on monthly payments, an illustration consistent with 5001.401 and 5001.402. Capacities of 4,000 and 16,000 pallet positions are assumptions (fruit storage is often sized in bins instead). The retention line applies 0.55% to the guaranteed share of principal remaining after a year of payments; the equity lines assume this loan is the only debt.
Computed: B&I terms on two Washington cold storage loans (Python, exact to the cent)
| Line | Loan A: US 7(a) average | Loan B: illustrative fruit storage build |
|---|---|---|
| Loan amount | $1,420,000.00 | $6,500,000.00 |
| Guarantee (fiscal 2026 notice) | 85% | 80% |
| Guaranteed amount | $1,207,000.00 | $5,200,000.00 |
| Lender's unguaranteed share | $213,000.00 | $1,300,000.00 |
| Upfront guarantee fee | $36,210.00 (3.0%) | $156,000.00 (3.0%) |
| Balance after 12 payments | $1,388,146.74 | $6,354,192.84 |
| First annual retention fee | $6,489.59 (0.55%) | $27,958.45 (0.55%) |
| Monthly principal and interest | $11,439.42 | $52,363.56 |
| Annual debt service | $137,273.08 | $628,362.69 |
| NOI for 1.00x (break-even) | $137,273.08 | $628,362.69 |
| NOI for 1.25x | $171,591.35 | $785,453.36 |
| Coverage if NOI falls 15% | 1.06x | 1.06x |
| Coverage if the rate is 2 points higher | 1.08x | 1.08x |
| NOI per pallet position per year for 1.25x (illustrative capacity) | $42.90 (4,000 positions) | $49.09 (16,000 positions) |
| Upfront fee if the guarantee issues before construction is complete (+0.50%) | $42,245.00 | $182,000.00 |
| New business, 5001.105(d)(4): 25% of project cost | $473,333.33 on $1,893,333.33 | $2,166,666.67 on $8,666,666.67 |
| New business, 5001.105(d)(4): 20% balance sheet equity (4:1) | $355,000.00 | $1,625,000.00 |
| Existing business, 5001.105(d)(1): 10% of project cost | $157,777.78 on $1,577,777.78 | $722,222.22 on $7,222,222.22 |
| SBA 7(a) on the same loan: guaranteed / fee ceiling | $1,065,000.00 / $37,437.50 | not compared |
Loan B needs $785,453.36 of NOI for 1.25x, $49.09 per pallet position a year at 16,000 positions; Loan A needs $42.90 per position at 4,000. In fruit storage the revenue behind those figures comes from storage and handling charges per bin or per box, set by contract with growers or by the packer's own throughput, so the study must show the contracted volume. If Loan B's guarantee issues before construction is complete, the upfront fee rises to $182,000.00.
Computed: stress test for the two cold storage loans
| Scenario | Loan A | Loan B |
|---|---|---|
| Base case: NOI at 1.25x | $171,591.35 / 1.25x | $785,453.36 / 1.25x |
| NOI down 10% | $154,432.22 / 1.13x | $706,908.03 / 1.13x |
| NOI down 20% | $137,273.08 / 1.00x | $628,362.69 / 1.00x |
| NOI down 30% | $120,113.95 / 0.88x | $549,817.35 / 0.88x |
| Rate 1 point higher, re-amortised | 1.16x (debt service $147,877.08) | 1.16x (debt service $676,902.12) |
| Rate 2 points higher, re-amortised | 1.08x (debt service $158,835.15) | 1.08x (debt service $727,062.33) |
| Rate 3 points higher, re-amortised | 1.01x (debt service $170,123.93) | 1.01x (debt service $778,736.31) |
A short crop that cuts storage volume 20% takes either loan to break-even, which is why lenders favour multi-year storage contracts with minimum volumes or take-or-pay terms.
Evidence a Washington cold storage study must build
- Crop and volume: acreage, yields and historical volumes for the fruit or potatoes the facility will hold, by grower, with the hub's statewide crop context as background only.
- Storage contracts: signed or draft agreements with growers, packers or shippers, with volumes, rates, terms and minimums.
- Existing capacity: an inventory of CA and regular cold rooms in the district, from packers and operators, since Census misses most of it.
- Throughput model: receiving, storage duration and out-shipment by month, linked to harvest and marketing seasons.
- Energy: refrigeration load, utility rates and any efficiency measures, with REAP or PACER counted only once approved.
- Labour: staffing by season at Washington wages, benchmarked against $62,389.
- Capital costs: building, insulation, refrigeration plant, CA equipment and site work, with quotes and contingency.
- Coverage and stress: 1.25x at stabilisation, with short-crop, price and rate stresses as above.
Washington risks a cold storage study has to carry
- Crop risk. Frost, heat or a light crop year cut storage volume directly; contracts with minimums are the mitigant.
- Energy cost. Refrigeration load is the largest operating cost after labour; rate changes flow straight to coverage.
- Single-purpose buildings. CA rooms appraise below cost, so collateral is thin and equity matters more.
- Program status. The Food Supply Chain program is described on the site as discontinued in 2023, and the hub reports a guarantee pause for controlled environment agriculture and biodigester projects through 31 December 2026.
- Harvest-season filing. Projects aiming to close before the next crop should know that, by the hub's account, B&I intake closes on 20 November 2026 until a new portal opens.
Hiring a USDA cold storage feasibility study consultant in Washington
A new storage company borrowing more than $1,000,000 under B&I must provide an independent study scoped by USDA; a packer expanding rooms falls under the Agency's and lender's discretion, which they tend to exercise when storage revenue depends on third-party growers. Engage a USDA feasibility study consultant that has no interest in the orchard, the packing company, the refrigeration contract or the loan.
Washington cold storage is a classic complex engagement under the site's cost page: limited comparable data and USDA-flagged market questions point to the $10,500 to $14,500 band over seven to nine weeks, while a straightforward room addition with contracts in hand may fit the standard $6,900 to $12,500 band over six to seven weeks. Either way the engagement covers the five Part 5001 components, a five to ten year model with volume, rate and energy sensitivities, district supply analysis, benchmarks, a management review, the PDF and Word report with an Excel model, two scheduled calls, a revision round and the acceptance guarantee. Engineering, refrigeration design, environmental work, appraisals and lender packaging are separate. A three-to-four-week schedule, if analysts are free, adds 20% to 35%.
Assemble crop and volume history, storage agreements, the facility design and refrigeration quotes, utility terms, financial statements for any operating company, owner résumés and the lender's term sheet. The national cold storage feasibility guide covers method and national data. For a Washington project, ask for a proposal on the contact page; a senior analyst replies within one business day.
Program evidence, honestly labelled
The site's engagements page lists a cold storage and dairy processing study in Washington in the $5 million to $25 million band, prepared with throughput and absorption modelling, as the site presents it. No USDA-financed cold storage project in Washington is named in the inputs. Beyond Washington, the national cold storage guide on this site describes a California project, Origo Cold Storage in Madera County, where a $35 million USDA-guaranteed loan sat alongside $17 million of C-PACE money to build 254,000 square feet of temperature-controlled space; the guarantee came from the Food Supply Chain program, since discontinued, so it illustrates layered financing rather than a B&I precedent. The Arkansas cold storage case study is an out-of-state analysis.
Last updated 2026-11-08