    Solar in rural Washington is financed by the farms, packers and small businesses that use the power, not by solar companies, and the Rural Energy for America Program (REAP) is the federal tool that matters. USAspending records 156 REAP grants and no REAP guaranteed loans in Washington from FY2024 to FY2026, against just four solar generation businesses with payroll in the 2023 Census data. The rule effective 16 October 2026 changed the economics: a REAP grant now covers at most 25% of cost, a project must be built and running with twelve months of data before it applies, and grant plus guaranteed loan cannot exceed 75% of cost. The hub adds that ground for financing solar through Business and Industry (B&I) has narrowed. A Washington solar feasibility study therefore has to support the loan that builds the system, prove the energy load and payback, and treat the grant as a later, competitive reimbursement.

    Data current as of November 2026.

    What the October 2026 REAP rule means for a Washington solar project

    The current REAP terms date from a final rule with comment period printed at 91 FR 62600 on 1 October 2026 and in force from 16 October; it replaced the FY2025 to FY2027 funding notice that USDA withdrew in April 2026, so any Washington applicant without a signed financial assistance agreement had to start over. The terms below come from the rule text as recorded in this site's verified summary.

    TopicRule effective 16 October 2026What it means in Washington
    TimingProject period must end 12 to 24 months before the application (12 to 36 in the first window)Build first, with a loan or cash; apply for the grant later
    Data12 months of actual production or savings and 12 months of pre-installation dataKeep utility bills from before installation
    Award size$1,500 minimum; $500,000 maximum for renewable systems; $250,000 for efficiencyLarge packing-house arrays hit the cap
    Cost shareGrant at most 25% of project costThe owner or lender carries 75% or more
    Combined fundingGrant plus REAP guaranteed loan at most 75% of costCaps the loan when a grant is planned
    CroplandGround-mount solar or wind on Cropland (7 CFR 718.2) ineligible; no retrofits of such systemsOrchard and field sites need screening; rooftops and non-cropland are safer
    Foreign componentsSystems with any component from a foreign adversary under 15 CFR 791.4 ineligible, except those installed before publicationA country-of-origin list for every component
    SizingGround-mount systems need commensurate historical energy use; storage at most 120% of prior annual useLoad analysis from bills, not from the roof area
    EconomicsSimple payback must not exceed useful lifePayback is an eligibility test
    LocationsOne location per application; one application per fiscal year per highest-level ownerMulti-orchard operations choose one site a year
    ExclusionsEV chargers, retail energy dispensing, stand-alone storage, storage retrofits, distribution-only projectsKeep these out of the REAP budget
    InstallersLicensed in the state with at least three similar installations; procurement under 2 CFR 200.318 to 200.327Installer qualifications go in the file
    CompetitionOne competition for requests of $20,000 or less and one national competition; no state competitionsWashington applicants compete nationally

    No application window under the new rule had been announced in the Federal Register by 7 November 2026, so the next Washington filing date is unknown. The REAP guaranteed loan under 7 CFR 5001 is available for up-front costs, and under the fiscal 2026 notice (91 FR 11272) it carries an 80% guarantee, a 1.0% guarantee fee and 0.25% annual retention.

    Which program fits, and when a study is required

    For a REAP guaranteed loan, Part 5001's feasibility rule applies as it does to B&I: a guaranteed loan above $1,000,000 to a new business requires an independent study by a consultant the Agency accepts, on its scope (5001.306(a)(3)(i)); smaller loans are at its discretion. REAP grant applications carry their own technical and economic documentation. B&I has been a route for renewable systems, but the Washington hub states that "since an August 2025 USDA letter, wind and solar projects are ineligible for B&I"; that letter is not among the verified sources for this page, and the site's national renewable page cites a B&I provision for renewable systems, so confirm with the lender before planning a B&I solar loan. SBA 7(a) has financed two Washington solar generation businesses since FY2010. The hub also describes Washington's Commercial PACER program, under RCW 36.165 and adopted by King, Pierce, Snohomish, Spokane, Clark, Thurston and Whatcom counties, which finances energy, water and seismic improvements and can pay for solar where a county has adopted it. Community Facilities financing can serve a public or nonprofit facility's own solar.

    Screens: the hub reports that under the new REAP rule any gambling income, including lottery or pull-tab revenue, makes an applicant ineligible; that statement is not in this site's verified rule summary, so confirm it. For REAP and B&I guaranteed loans, owners above 20% must clear 5001.127(a).

    Solar and renewable generation in Washington: market evidence

    Washington: solar and other renewable power generation, supply and rural footprint

    MeasureWashingtonUnited States
    Establishments, 2019 → 20230 → 4 (n/a)405 → 942
    Per 100,000 residents (2023)0.10.3
    Average employees per establishment5.812.3
    Average annual pay per employee$210,478$138,631
    Share of state population in non-metro counties (2025)10.2%

    Sources: U.S. Census Bureau, County Business Patterns 2019 and 2023 (state and county files; establishments with paid employees; employment and payroll suppressed in some cells); Vintage 2025 county population estimates; OMB metropolitan statistical area delineation, July 2023. Non-metro county is a proxy for USDA rural eligibility, not the eligibility test itself.

    Four solar generation businesses with 23 employees in total is not a market in the sense a feasibility study usually measures; the $210,478 pay figure rests on so few workers that it means little. The count rose from none in 2019, while the national count more than doubled, from 405 to 942. The finding is that Washington solar is overwhelmingly behind-the-meter: a farm, packer, winery or store installs a system to cut its own power bill. The relevant evidence is that business's energy use and tariff, not a supply of competing generators.

    The REAP award count is the better market indicator: 156 Washington REAP grants in FY2024 to FY2026, according to USAspending, set against 14 B&I loans and 41 Community Facilities awards in the same period. Those counts may be incomplete, and they include efficiency as well as renewable projects.

    Regional comparison

    Neighbouring packs show the same pattern. Oregon reports 9 solar generation businesses in 2023 (3 in 2019) and no SBA loans; Idaho 5 (4 in 2019) and two SBA 7(a) loans; Montana none. Across the four states there are 18 solar generation employers, so a REAP solar study in any of them rests on the applicant's own load data and installer quotes rather than on regional comparables. The national SBA line is a caution for any stand-alone generation business: 12.9% of 31 seasoned solar 7(a) loans were charged off, on average 51 months after approval.

    Rural footprint and eligibility in Washington

    REAP grants and guaranteed loans serve agricultural producers anywhere and rural small businesses in rural areas; the guaranteed loan uses the 7 CFR 5001.3 test, which excludes cities above 50,000 at the 2020 Census and their contiguous urbanized areas and does not allow approval on future qualification. The Washington state page screens Wenatchee, Quincy, Moses Lake, Walla Walla, Mount Vernon and the lower Yakima Valley towns as eligible and places Yakima, Union Gap, Selah, Moxee and Naches inside the Yakima urbanized area. With 10.2% of Washington residents in non-metro counties and the hub estimating that only 28% to 31% live in B&I-eligible areas, a rural business near a metro edge should confirm the parcel before designing the system. For farms, the cropland exclusion is the bigger constraint: ground-mounted solar on cropland is now ineligible for REAP, so orchard and field operations will usually look to rooftops, packing-house roofs or non-cropland ground.

    Financing benchmarks: REAP and SBA

    Washington: SBA lending to solar and other renewable power generation

    Period7(a) loans7(a) dollars504 loans504 dollars
    FY2010 to FY20160$00$0
    FY2017 to FY20190$00$0
    FY2020 to FY20230$00$0
    FY2024 to FY20262$3.7 million0$0

    Average 7(a) loan, FY2020 to FY2026: $1.9 million. Washington had fewer than 30 seasoned 7(a) loans for solar and other renewable power generation; nationally, 12.9% of 31 FY2010 to FY2016 loans were charged off, on average 51 months after approval.

    Source: SBA 7(a) and 504 FOIA loan data, as of 30 Sep 2026 (project state; disbursed loans only; cancelled and undisbursed loans excluded).

    Two loans are not a benchmark. Across the country, the 138 SBA 7(a) loans to solar generation businesses in FY2020 to FY2026 averaged $478,591. For a farm or rural business adding solar, the financing is usually part of the owner's own credit, a REAP guaranteed loan, PACER where available, or equipment financing, and the feasibility question is whether the energy savings cover the debt.

    TermREAP guaranteed loanWhat it means for a Washington system
    Guarantee80% (91 FR 11272)Lower than B&I's 85% under $5 million
    Fees1.0% upfront on the guaranteed share; 0.25% annual retention$3,200 at closing on a $400,000 loan
    Combined capGrant plus guaranteed loan at most 75% of project costAt least 25% of cost is owner money
    Term and rateUseful life, no balloon (5001.402); negotiated rate (5001.401)Match to panel and inverter life; inverters may need replacement within the term
    StudyIndependent study above $1,000,000 for a new business (5001.306(a)(3)(i))Most farm systems are smaller and discretionary
    Grant timingGrant only after 12 months of operating dataBridge the 25% with cash or a short loan

    Worked example (illustrative)

    Inputs. An illustrative $800,000.00 rooftop system at a rural Washington packing shed, financed two ways with a REAP guaranteed loan at an assumed 7.00% fixed over 20 years (illustrative; 5001.401 and 5001.402). Case A plans to apply for the maximum 25% grant, $200,000.00, after a year of operation, so grant plus loan is held to 75% of cost. Case B plans no grant and borrows 75% of cost. A 25-year useful life is assumed for the payback test. Retention is charged at 0.25% on the guaranteed part of the balance left after the first year's payments.

    Computed: funding split for an illustrative $800,000 system under the October 2026 REAP rule

    LineCase A: with a REAP grantCase B: without a grant
    Project cost (illustrative)$800,000.00$800,000.00
    REAP grant (at most 25% of cost and $500,000)$200,000.00$0.00
    REAP guaranteed loan$400,000.00$600,000.00
    Grant plus loan as a share of cost (cap 75%)75.0%75.0%
    Owner cash at closing$400,000.00$200,000.00
    Owner cash after the grant is paid$200,000.00$200,000.00
    Simple payback test: savings needed so payback is under a 25-year life$32,000.00 a year$32,000.00 a year

    Computed: REAP guaranteed loan terms for the two cases (Python, exact to the cent)

    LineCase A: grant planned, loan at the 75% combined capCase B: no grant, loan at 75% of cost
    Loan amount$400,000.00$600,000.00
    REAP guarantee (fiscal 2026 notice)80%80%
    Guaranteed amount$320,000.00$480,000.00
    Lender's unguaranteed share$80,000.00$120,000.00
    Upfront guarantee fee$3,200.00 (1.0%)$4,800.00 (1.0%)
    First annual retention fee$780.97 (0.25%)$1,171.45 (0.25%)
    Monthly principal and interest$3,101.20$4,651.79
    Annual debt service$37,214.35$55,821.52
    Annual savings or revenue for 1.25x$46,517.94$69,776.90
    Coverage if output falls 15%1.06x1.06x
    Coverage if the rate is 2 points higher1.08x1.08x

    Case A's owner must put $400,000.00 into the project at closing and wait at least a year to recover $200,000.00 through a competitive national grant; until then the grant is not cash. Case B needs $69,776.90 of annual energy savings or revenue for 1.25x coverage on the larger loan; Case A needs $46,517.94. Both comfortably exceed the $32,000.00 a year that a 25-year simple payback test requires, which shows that for a financed system the coverage test, not the payback test, sets the minimum savings. A system that cannot document savings of that size from twelve months of prior bills should be downsized.

    Evidence a Washington solar feasibility study must build

    1. Energy use: at least twelve months of utility bills before installation, load profile by month, and the tariff and net metering terms that apply.
    2. System design: size justified by historical use (and storage within 120% of prior annual use), production estimate, degradation and inverter replacement.
    3. Site screening: rooftop or ground; if ground, evidence that the land is not Cropland under 7 CFR 718.2.
    4. Components: country of origin for every component, to clear the foreign-adversary exclusion.
    5. Installer: proof the contractor holds a Washington licence and has finished three or more comparable systems, plus the procurement record the rule requires.
    6. Economics: simple payback against useful life, coverage of any loan at 1.25x, and a case without the grant.
    7. Ownership and site control: at least 12 months of ownership or lease before the project period, and the one-application-per-year rule across related owners.
    8. Interconnection: the utility's interconnection approval and any upgrade costs.

    Washington risks a solar study has to carry

    • Grant timing and competition. The grant comes after a year, from one national competition; underwrite without it.
    • Cropland and siting. Orchard and field ground-mounts are out; packing-house and shop roofs are the usual sites.
    • Tariffs. Savings depend on the serving utility's rates and net metering terms, which differ across Washington's utilities and can change.
    • B&I availability. The hub reports B&I is closed to wind and solar after an August 2025 USDA letter; confirm before relying on it.
    • Gambling income. The hub reports any gambling income bars REAP; a farm store with lottery sales should check first.
    • Funding notice. No REAP notice under the new rule had appeared as of 7 November 2026; timing of the next window is uncertain.

    Hiring a USDA solar feasibility study consultant in Washington

    A REAP guaranteed loan above $1,000,000 to a new business requires an independent study scoped by the Agency; smaller REAP loans and grant applications need technical and economic documentation that lenders and reviewers test closely under the new rule. The USDA feasibility study consultant for a solar project should be independent of the installer, the equipment supplier and the lender.

    The site's cost page prices REAP work in two bands: studies for projects with a REAP loan under $600,000 at $4,900 to $8,500 over four to five weeks, and studies supporting a REAP guaranteed loan over $600,000 at $7,500 to $11,500 over five to seven weeks, the latter including full financial projections, coverage analysis and interconnection and utility rate modelling. Every engagement includes the five Part 5001 components where they apply, sensitivity analysis, the PDF and Word report with the Excel model, two scheduled calls, a revision round and the written acceptance guarantee; engineering, environmental work, appraisal and grant application drafting are excluded. Owners with an interconnection or construction deadline can shorten delivery to three or four weeks for 20% to 35% more.

    Gather twelve months or more of utility bills, the installer's design and quote, component origin information, site ownership or lease documents, the interconnection application, financial statements and the lender's terms. The national renewable energy feasibility guide and the site's REAP feasibility page cover the program in depth. To scope a Washington system, request a proposal on the contact page; a senior analyst replies within one business day.

    Washington REAP precedents (earlier rules; program evidence, not the firm's work)

    The hub's precedent table lists a 2023 REAP award of $979,000 to Sakata Seed America in Skagit County for an energy upgrade, and its text reports REAP-funded energy upgrades at Borton & Sons, the Borton Fruit plant in Zillah, Royal Dairy and Leonetti Cellar in Walla Walla. All were made under the rules in force before 16 October 2026, when grants could fund projects before construction; the same projects would now be built first and reimbursed later, for at most 25% of cost. The site's Pennsylvania REAP solar case study is an out-of-state analysis of commercial rooftop solar.

    Last updated 2026-11-08

    David Miller, CPA

    USDA Feasibility, Inc.

    Frequently Asked Questions

    Does a Washington solar project need a feasibility study for REAP?

    Only a large one triggers the formal rule: a REAP guaranteed loan of more than $1,000,000 to a new business needs an independent study under 7 CFR 5001.306(a)(3)(i). Most farm and small-business systems are smaller, but the rule effective 16 October 2026 still demands twelve months of pre-installation and production data, a simple payback within useful life and a load analysis for ground-mounted systems, so lenders and reviewers expect a documented technical and financial case either way.

    What does a solar feasibility study consultant charge in Washington?

    The site's cost page lists REAP studies for projects with a loan under $600,000 at $4,900 to $8,500 and studies supporting a REAP guaranteed loan over $600,000 at $7,500 to $11,500, each fixed in a written proposal. The larger band includes interconnection and utility rate modelling. Engineering, environmental work and drafting the grant application are not included.

    How long does a REAP solar study take?

    Four to five weeks for the smaller REAP band and five to seven weeks for studies backing a REAP guaranteed loan over $600,000, per the site's cost page, with a three-to-four-week rush at a 20% to 35% premium. Under the new rule, the grant application cannot be filed until twelve months after the project period ends, so the study for the construction loan comes well before any grant filing.

    Who can prepare a solar feasibility study for USDA?

    For a guaranteed loan, an independent consultant the Agency accepts as qualified, with no financial interest in the installer, the equipment or the loan. Installers' production estimates and quotes are inputs the consultant tests. The preparer must reconcile the design with historical energy use, model savings under the utility's tariff, test payback and coverage, and document component origin and installer qualifications.

    How long is a solar feasibility study valid?

    Part 5001 sets no expiry for studies, but tariffs, equipment prices and the REAP notice change often. Data older than roughly eighteen months tends to draw questions from USDA, by the cost page's account. Under the new rule, the grant application uses actual production data from the first twelve months, so the pre-construction study is mainly for the loan and should be updated if pricing or tariffs move before closing.

    Can the same study support a REAP loan, PACER and a bank loan?

    Yes, if it is built to the USDA standard: load analysis, production, payback, coverage and stress cases. That also answers what SBA can require under 13 CFR 120.160(b) and what a PACER program or bank will want to see. In Washington, where the hub describes Commercial PACER in several counties and USAspending shows 156 REAP grants but no REAP loans in FY2024 to FY2026, sponsors often compare these routes.

    Can a Washington orchard install ground-mounted solar with REAP?

    Not on Cropland. Since 16 October 2026, any ground-mounted solar or wind array sitting on land classed as Cropland under 7 CFR 718.2 is outside REAP, and so is a retrofit of one. Orchards and field operations should look at packing-house, shop or cold-storage roofs, or ground that is not Cropland, and document the land status. A ground array on non-cropland still has to be sized to the farm's past electricity use.

    Can B&I finance solar in Washington?

    The Washington hub says no, stating that since an August 2025 USDA letter wind and solar projects are ineligible for B&I. That letter is not among the sources verified for this page, and the site's national renewable page cites a B&I provision for renewable systems, so the position should be confirmed with the lender and USDA. REAP guaranteed loans, PACER where adopted, and conventional or equipment financing remain available routes.

    Does gambling income affect REAP eligibility in Washington?

    The hub reports that under the new REAP rule any gambling income, including lottery or pull-tab revenue, makes an applicant ineligible, and that Washington Lottery retailers earn a 5% commission. That provision is not in this site's verified summary of the rule, so confirm it before applying. A farm store, winery tasting room or fuel stop selling lottery tickets should settle the question first.

    Sources

    1. USDA RBCS, Rural Energy for America Program final rule with comment period, 91 FR 62600 (1 Oct 2026), effective 16 Oct 2026: https://www.govinfo.gov/content/pkg/FR-2026-10-01/html/2026-20178.htm
    2. USDA RBCS, Notice of Rescission of Funding Opportunity for REAP, 91 FR 20090 (15 Apr 2026): https://www.govinfo.gov/content/pkg/FR-2026-04-15/html/2026-07332.htm
    3. 91 FR 11272, OneRD FY2026 guarantee fee, retention fee and guarantee percentage notice (REAP 80%, 1.0%, 0.25%): https://www.govinfo.gov/content/pkg/FR-2026-03-09/html/2026-04581.htm
    4. 7 CFR Part 5001, CFR 2026 edition (govinfo): https://www.govinfo.gov/content/pkg/CFR-2026-title7-vol15/xml/CFR-2026-title7-vol15-part5001.xml
    5. U.S. Census Bureau, County Business Patterns 2019 and 2023 (NAICS 221114, 221117, 221118): https://www2.census.gov/programs-surveys/cbp/datasets/
    6. U.S. Census Bureau, Vintage 2025 population estimates: https://www2.census.gov/programs-surveys/popest/datasets/2020-2025/
    7. Office of Management and Budget, metropolitan and micropolitan delineation, July 2023: https://www2.census.gov/programs-surveys/metro-micro/geographies/reference-files/2023/delineation-files/list1_2023.xlsx
    8. U.S. Small Business Administration, 7(a) and 504 FOIA loan data, as of 30 Sep 2026: https://data.sba.gov/dataset/7-a-504-foia
    9. USAspending.gov, prime award data by assistance listing 10.868, 10.768 and 10.766, FY2024 to FY2026 (counts may be incomplete): https://www.usaspending.gov/
    10. 13 CFR Part 120, SBA business loan programs (CFR 2026 edition): https://www.ecfr.gov/current/title-13/chapter-I/part-120
    11. Oregon, Idaho and Montana solar packs (Census CBP and SBA FOIA), used for regional comparison.
    12. USDA Feasibility Study Consultants, Washington state page (REAP precedents, PACER, B&I solar statement, gambling statement, eligibility screens): https://usda-feasibility-study.com/washington
    13. USDA Feasibility Study Consultants, cost page and contact page: https://usda-feasibility-study.com/usda-feasibility-study-cost ; https://usda-feasibility-study.com/contact

    Data current as of November 2026.

    Ready to Start Your USDA Project?

    Get your free consultation today and take the first step toward securing USDA funding for your rural development project.

    Our USDA feasibility study consultants scope every engagement against the five Part 5001 components in a free consultation.