USDA Feasibility Study for Sawmills and Wood Products in Mississippi

    NAICS 321

    Three in four Mississippi wood products plants that Census places by county, 129 of them, operate outside metro areas, and their workers earn $57,848 a year on average, slightly above the national figure; of the 18 project types on this site's Mississippi pages, only wood products and the eight utility-scale solar generators pay at or above the U.S. level. Behind them stand 19.2 million acres of forestland and, on the hub's figures, a $15.44 billion forestry economy. The job of a USDA sawmill feasibility study in Mississippi is to show that a particular mill can buy logs, sell lumber or other products through the cycle and service a Business and Industry (B&I) loan, in a sector where the plant count fell 10.6 percent in four years even as large new mills opened.

    Sawmills and wood products in Mississippi: market evidence

    Mississippi: wood product manufacturing, supply and rural footprint

    MeasureMississippiUnited States
    Establishments, 2019 → 2023235 → 210 (-10.6%)14,223 → 13,899
    Per 100,000 residents (2023)7.14.1
    Average employees per establishment41.431.1
    Average annual pay per employee$57,848$57,420
    Share of establishments in non-metro counties75.0% (129 in 28 counties)
    Share of state population in non-metro counties (2025)50.0%

    Non-metro counties with the most wood product manufacturing (2023): Chickasaw County (9); Jones County (8); Pontotoc County (8); Noxubee County (7); Amite County (6); Lee County (6).

    Sources: U.S. Census Bureau, County Business Patterns 2019 and 2023 (state and county files; establishments with paid employees; employment and payroll suppressed in some cells); Vintage 2025 county population estimates; OMB metropolitan statistical area delineation, July 2023. Non-metro county is a proxy for USDA rural eligibility, not the eligibility test itself.

    Consolidation in a timber state. Mississippi has 73 percent more wood products plants per resident than the nation, and they are a third larger (41.4 employees against 31.1). Yet 25 plants disappeared between 2019 and 2023, a 10.6 percent fall against 2.3 percent nationally. The hub's account of a nearly $200 million sawmill at Gloster with 131 direct jobs points to the pattern: fewer, bigger, more automated mills replacing small ones. That matters for a feasibility study in two ways. A new or expanding mill competes for logs with large, efficient buyers, so the study must show a timber supply and delivered log cost that leave margin; and the labour market is tight, with average payroll per plant of about $2.40 million (computed) and pay at the national level, so a pro forma cannot assume cheap rural labour. A reviewer will also test product price assumptions across the lumber cycle, not at a single year's price.

    Rural footprint and B&I eligibility in Mississippi

    At 75.0 percent, wood products has the highest non-metro share of any industry on the Mississippi pack list, against 50.0 percent of residents. The top non-metro counties are Chickasaw (9), Jones and Pontotoc (8 each), Noxubee (7), and Amite and Lee (6 each). Amite County is where the hub places the Gloster mill. Neighbouring states' packs, read as theirs, show the same concentration: Arkansas has 8.9 plants per 100,000, Alabama 6.8, Tennessee 6.1 and Louisiana 3.5.

    Most mill sites will pass 7 CFR 5001.3 easily, because the test excludes only cities and towns above 50,000 at the latest decennial census and the urbanized areas contiguous to them; on the hub's 2020 Census table those are Jackson, Gulfport and Southaven, plus their suburbs. A mill or pellet plant near the Jackson or Gulfport urbanized fringe still needs the map check, as does any industrial park site near Biloxi.

    The borrower and its significant owners must pass 5001.127: a federal court judgment left unpaid, federal tax or other federal debt in delinquency, or a suspension or debarment, whether it attaches to the company itself, to whoever controls it or to a holder of more than a fifth of it, makes the mill ineligible. Personal guarantees from owners of 20 percent or more follow 5001.204.

    Program fit for a Mississippi mill

    • B&I finances sawmills and wood products plants: buildings, saw lines, kilns, planers, log yards, rolling stock and working capital, with a ceiling of $25 million for any one borrower. The hub names B&I as the program that finances mills.
    • REAP, which the hub says funds kilns and mill energy systems, operates under the rule effective 16 October 2026: a renewable system such as a biomass-fired boiler can receive a grant covering no more than one quarter of its cost, with $500,000 the ceiling, and only after it has run for 12 months; grant plus REAP guaranteed loan cannot exceed 75 percent of cost. The REAP guaranteed loan can fund construction.
    • SBA 7(a) has made 21 Mississippi wood products loans since FY2010, and SBA 504 one, for $2.4 million, in FY2024 to FY2026.
    • Community Facilities does not fund private mills; the hub notes DRA co-funding in the Delta and ARC and Southeast Crescent coverage in parts of the state.

    Financing benchmarks: USDA B&I next to SBA

    Mississippi: SBA lending to wood product manufacturing

    Period7(a) loans7(a) dollars504 loans504 dollars
    FY2010 to FY201610$2.4 million0$0
    FY2017 to FY20195$6.2 million0$0
    FY2020 to FY20234$3.6 million0$0
    FY2024 to FY20262$1.7 million1$2.4 million

    Average 7(a) loan, FY2020 to FY2026: $886,467. Average 504 loan: $2.4 million. Mississippi had fewer than 30 seasoned 7(a) loans for wood product manufacturing; nationally, 7.1% of 1,015 FY2010 to FY2016 loans were charged off, on average 65 months after approval.

    Source: SBA 7(a) and 504 FOIA loan data, as of 30 Sep 2026 (project state; disbursed loans only; cancelled and undisbursed loans excluded).

    B&I termFiscal 2026 ruleSource
    Guarantee85% if the loan is less than $5 million; 80% between $5 million and $25 million91 FR 11272
    Upfront fee3.0% of the guaranteed amount; reduced-fee loans 1.0%91 FR 11272
    Retention fee0.55% annually of the guaranteed outstanding balance91 FR 11272
    Termeach asset's useful life, up to 40 years; saw lines and rolling stock shorter than buildings7 CFR 5001.402
    Equity10% existing mill; 10% new mill with qualifying offtake contracts; otherwise 20% or 25%7 CFR 5001.105(d)
    Collateralappraisal; going-concern value deducted before discounts7 CFR 5001.203
    Studyrequired for a new business above $1 million7 CFR 5001.306(a)(3)(i)

    B&I terms summarised from the FY2026 notice and 7 CFR Part 5001.

    What the lending record implies. SBA's role in Mississippi wood products has been modest, 21 loans in 17 years, and recent loans averaged $886,467, equipment-scale money. Mill construction and modernisation run to millions and sit naturally in B&I. With too few seasoned state loans to report, the national benchmark applies: 7.1 percent of 1,015 wood products loans charged off, on average 65 months after approval, one of the higher industrial loss rates, which reflects the lumber price cycle. A lender will want the study to show coverage through a price trough, not at the top of the cycle.

    Worked example (illustrative)

    Loan A is $770,000, the national FY2020 to FY2026 average wood products 7(a) loan ($766,800) rounded, because Mississippi had only six such loans; it finances equipment over 12 years at an illustrative 7.50 percent. Loan B is an illustrative $4,500,000 modernisation of an existing mill, kept below the $5 million tier line, at 7.25 percent over 20 years.

    Input or resultLoan A: equipment, national averageLoan B: mill modernisation
    Loan amount$770,000.00$4,500,000.00
    Program and fee scheduleB&I, fiscal 2026 noticeB&I, fiscal 2026 notice
    Guarantee percentage85%85%
    Guaranteed amount$654,500.00$3,825,000.00
    Upfront guarantee fee$19,635.00$114,750.00
    Upfront fee if the guarantee is issued before construction is complete (+0.50%)$22,907.50$133,875.00
    First annual retention fee (guaranteed share of the balance after 12 payments)$3,407.38$20,551.48
    Interest rate (illustrative, fixed)7.50%7.25%
    Amortization, years (no balloon)1220
    Monthly payment$8,125.24$35,566.92
    Annual debt service$97,502.91$426,803.03
    Quarterly debt service$24,375.73$106,700.76
    NOI needed for 1.25x coverage$121,878.64$533,503.79
    Coverage on that 1.25x NOI if the rate were 2 points higher1.13x1.08x
    Equity, existing business, 10% of project cost (5001.105(d)(1))$85,555.56$500,000.00
    Equity, new business with qualifying sales contracts, 10% of project cost (5001.105(d)(2))$85,555.56$500,000.00
    Equity, new business, 25% of project cost (5001.105(d)(4))$256,666.67$1,500,000.00
    Total project cost on that basis$1,026,666.67$6,000,000.00

    Computed in Python from the inputs shown; guarantee and fee rates from 91 FR 11272; equity routes from 7 CFR 5001.105(d), assuming the guaranteed loan is the only debt.

    Per-MBF and per-job tests. At an illustrative output of 30 million board feet a year, Loan B's 1.25x NOI of $533,503.79 equals $17.78 per thousand board feet (MBF) after log costs, labour, energy and maintenance; at 15 million board feet it doubles to $35.57. Loan A needs $4.06 per MBF at 30 million board feet. Spread across a plant of the state's average size, 41.4 employees, Loan B's target equals about $12,887 per job. The study must show the delivered log cost and product price spread that produce those margins in a weak year.

    Cycle test. If lumber prices fall far enough to cut NOI by 20 percent, coverage drops to 1.00x; a two-point rate rise alone cuts it to 1.08x. Quarterly debt service of $106,700.76 on Loan B means a mill needs working capital to carry log inventory through wet-weather months when logging slows.

    What a lender-grade sawmill feasibility study in Mississippi must prove

    1. Timber supply: volume of available sawtimber within haul distance, ownership, competing mills' demand and delivered log price trends.
    2. Products and markets: product mix, buyers, distribution and price history across at least one full cycle.
    3. Technology and recovery: saw line design, recovery rates, kiln and planer capacity, confirmed by equipment suppliers or engineers.
    4. Residuals: sales of chips, sawdust and bark to pulp, pellet or energy buyers, with contracts where possible.
    5. Labour: staffing, wages against the $57,848 state average and training; the study shows recruitment in counties where other mills compete.
    6. Energy: kiln fuel and power costs, and any REAP-eligible system, sized to the rule's commensurate-use test.
    7. Capital costs and schedule with vendor quotes, construction contract and contingency; a construction-period guarantee adds the 5001.205(e)(2) requirements.
    8. Air, water and stormwater permits obtained by the sponsor's environmental advisers, with their conditions carried into the cost and schedule.
    9. Rural-area status of the parcel under 5001.3.

    Risks and mitigants in Mississippi

    Price cycles are the defining risk; mitigants are conservative price decks, residual income and a debt structure that survives a trough. Log supply competition from large new mills is addressed with supply agreements and a wood-basket analysis. Weather affects logging and log inventory; the study models wet seasons. Fire and equipment breakdown risk call for insurance and spare-parts budgets.

    Lender file, sponsor inputs and frequent review comments

    Applications reach Rural Development in Jackson, the state office listed on the hub, through the lender. The sponsor provides timber supply studies or procurement plans, offtake and residual agreements, equipment quotes and layouts, permits, historical financials for an existing mill and owners' statements. Studies return with comments when prices come from a single strong year, log supply ignores competing mills, or residual income is assumed without buyers.

    Program example

    The hub's precedent file lists no sawmill financed by USDA in Mississippi. It does describe the nearly $200 million CLAW Forestry sawmill at Gloster in Amite County, with 131 direct jobs, now operating as Gloster Forest Products, as an example of recent private investment; the inputs do not say USDA financed it, and this page does not present it as a program example.

    Hiring a USDA sawmill feasibility study consultant in Mississippi

    The rule is clear for start-ups: a new business seeking a B&I guarantee above $1,000,000 must provide a feasibility study by an independent consultant whom the Agency accepts, with scope the Agency sets (7 CFR 5001.306(a)(3)(i)). A new mill company borrowing at Loan B's scale would be covered; an existing mill modernising, as in the example, is at the Agency's discretion, and lenders typically still ask given the lumber cycle.

    Mill studies with timber supply analysis and construction usually land in the higher, complex tier on the cost page (up to $14,500, seven to nine weeks), while an equipment expansion for an established mill can fit the standard band starting at $6,900. The deliverable covers supply and market analysis, technical and management review, cycle-tested projections, the Excel model and the acceptance guarantee; forestry inventory, engineering and environmental permitting are separate professional work.

    A sawmill feasibility study consultant should begin with your wood basket and your buyers. The homepage outlines what to ask a USDA feasibility study consultant before signing. Through the contact page, send the mill location, products, capacity, budget and lender; the reply is a written scope with a fixed fee.

    Last updated 2026-11-08

    David Miller, CPA

    USDA Feasibility, Inc.

    Frequently Asked Questions

    Does a Mississippi sawmill project need a feasibility study for B&I?

    A new mill company borrowing more than $1,000,000 must have one under 7 CFR 5001.306(a)(3)(i). Most mill projects exceed that size; Mississippi's SBA wood products loans averaged $886,467 even for equipment. An established mill modernising is at USDA's discretion, but with a national seasoned loss rate of 7.1 percent in this sector, lenders usually require one.

    What does a sawmill feasibility study consultant cost in Mississippi?

    Most new-mill studies sit in the site's complex range, $10,500 to $14,500, because timber supply, residual markets and construction all need analysis; a straightforward equipment project for an existing Mississippi mill can fit the standard range from $6,900. Whatever the tier, the written proposal fixes the fee before work begins. USDA's upfront fee on the $4,500,000 example is $114,750.00.

    How long does a mill feasibility study take?

    The cost page allows seven to nine weeks for complex B&I work and six to seven for standard work, with a faster schedule at a premium. Wood-basket data and buyer confirmations take the longest in a Mississippi mill study, along with quotes for the saw line and kilns; a sponsor with a recent timber supply study, equipment proposals and signed residual contracts saves several weeks.

    Who can prepare a sawmill study for USDA?

    Rule 5001.306(a)(3)(i) asks for an independent consultant whom the Agency considers qualified. That excludes anyone paid on the timber supply, the equipment sale, the land or the loan. Foresters, cruisers and saw line suppliers provide inputs, and their reports can be appended, but the feasibility conclusion must be the consultant's own. Rural Development decides acceptability for each application.

    How long is a sawmill feasibility study valid?

    No expiry is stated in Part 5001. In practice, the cost page says, USDA looks for data not much older than 18 months, and the real estate appraisal has to be inside one year (5001.203). Lumber prices can move sharply within a year, so update the price deck before the lender files if the market has moved.

    Can a single mill study satisfy SBA and USDA lenders?

    Yes. Address it to both lenders and model both loans; an SBA lender can make a study a condition (13 CFR 120.160(b)). The one Mississippi wood products 504 loan, $2.4 million in FY2024 to FY2026, shows SBA real estate financing is possible, but B&I's $25 million ceiling and useful-life terms fit larger mill projects.

    Can REAP pay for a kiln or biomass boiler at a Mississippi mill?

    Possibly, under the rule effective 16 October 2026: a renewable system can receive up to one quarter of its cost, never more than $500,000, and the system must have run for 12 months before the application, so the grant reimburses rather than funds construction. Grant plus a REAP guaranteed loan cannot exceed 75 percent of cost. The hub notes REAP funds kilns and mill energy systems.

    How does competition from large new mills affect a smaller project?

    The Census data show 25 fewer Mississippi wood products plants in 2023 than in 2019, while the hub reports a nearly $200 million mill at Gloster. Large mills raise local log demand and prices. A smaller mill's study must map competing buyers in its wood basket, show a delivered log cost it can sustain and identify products or markets the large mills do not serve.

    Sources

    1. U.S. Census Bureau, County Business Patterns 2019 and 2023, state and county files: https://www2.census.gov/programs-surveys/cbp/datasets/
    2. U.S. Census Bureau, Vintage 2025 population estimates: https://www2.census.gov/programs-surveys/popest/datasets/2020-2025/
    3. Office of Management and Budget, metropolitan and micropolitan delineation, July 2023: https://www2.census.gov/programs-surveys/metro-micro/geographies/reference-files/2023/delineation-files/list1_2023.xlsx
    4. U.S. Small Business Administration, 7(a) and 504 FOIA loan data, as of 30 Sep 2026: https://data.sba.gov/dataset/7-a-504-foia
    5. 7 CFR Part 5001, CFR 2026 edition (govinfo): https://www.govinfo.gov/content/pkg/CFR-2026-title7-vol15/xml/CFR-2026-title7-vol15-part5001.xml
    6. 91 FR 11272, OneRD FY2026 fee and guarantee notice (govinfo): https://www.govinfo.gov/content/pkg/FR-2026-03-09/html/2026-04581.htm
    7. 13 CFR Part 120, SBA business loan programs: https://www.ecfr.gov/current/title-13/chapter-I/part-120
    8. REAP final rule, 91 FR 62600 (1 Oct 2026): https://www.govinfo.gov/content/pkg/FR-2026-10-01/html/2026-20178.htm
    9. Alabama, Louisiana, Tennessee and Arkansas wood products packs (same Census source, each state's own figures)
    10. MDAC and MSU forestry figures, the Gloster mill and 2020 Census city counts, as cited on the Mississippi hub
    11. Site pages: /usda-feasibility-study-cost, /contact

    Data current as of November 2026.

    Ready to Start Your USDA Project?

    Get your free consultation today and take the first step toward securing USDA funding for your rural development project.

    Our USDA feasibility study consultants scope every engagement against the five Part 5001 components in a free consultation.