USDA Feasibility Study for Sawmills and Wood Products in Tennessee

    NAICS 321

    Tennessee has 6.1 wood product plants per 100,000 residents, nearly half again the national 4.1, and 47 percent of them sit in non-metro counties. The hub ties that base to East Tennessee's Appalachian hardwood forests and the Cherokee National Forest. The same data carry a warning: the state lost 26 plants between 2019 and 2023, and three of the seven seasoned Tennessee wood products loans in the SBA file were charged off. A sawmill feasibility study in Tennessee has to prove log supply, lumber markets and cash flow through price cycles before a lender will rest a USDA Business and Industry (B&I) guarantee on a mill.

    Sawmills and wood products in Tennessee: market evidence

    Tennessee: wood product manufacturing, supply and rural footprint

    MeasureTennesseeUnited States
    Establishments, 2019 → 2023461 → 435 (-5.6%)14,223 → 13,899
    Per 100,000 residents (2023)6.14.1
    Average employees per establishment38.031.1
    Average annual pay per employee$51,619$57,420
    Share of establishments in non-metro counties47.0% (190 in 35 counties)
    Share of state population in non-metro counties (2025)21.1%

    Non-metro counties with the most wood product manufacturing (2023): Fentress County (11); Hardeman County (11); Wayne County (10); Scott County (9); Sevier County (9); Greene County (8).

    Sources: U.S. Census Bureau, County Business Patterns 2019 and 2023 (state and county files; establishments with paid employees; employment and payroll suppressed in some cells); Vintage 2025 county population estimates; OMB metropolitan statistical area delineation, July 2023. Non-metro county is a proxy for USDA rural eligibility, not the eligibility test itself.

    What the numbers say. Wood products are a contracting industry in Tennessee: the plant count fell 5.6 percent from 2019 to 2023, more than double the national decline of 2.3 percent. The survivors are larger than average, 38.0 employees against 31.1, and pay $51,619, about 10 percent below the national figure; payroll per plant is $1,959,140 (computed from the pack). The table covers all wood product manufacturing, sawmills plus pallet, millwork, flooring and other plants, so a sawmill study should separate its own segment. A shrinking count can mean consolidation into fewer, larger mills or exit by marginal operators; either way, a reviewer will ask why a new or expanded mill will win logs and customers that others could not keep, and will test the projection against the low points of the lumber price cycle rather than the average.

    Rural footprint and B&I eligibility in Tennessee

    This is a rural industry. Census places 190 plants in 35 non-metro counties, 47.0 percent of the total it can locate, more than twice the 21.1 percent non-metro population share: 12.3 plants per 100,000 non-metro residents against 3.7 in metro counties (computed from the pack's county totals). Fentress and Hardeman lead with 11 each, followed by Wayne (10), Scott and Sevier (9 each) and Greene (8). Most mill sites will therefore pass the place test in 7 CFR 5001.3, which excludes only cities and towns above 50,000 at the 2020 Census and the urbanized areas contiguous and adjacent to them.

    The Tennessee hub lists the fifteen excluded cities, which include Knoxville, Johnson City and Kingsport near the East Tennessee hardwood region. Plants or concentration yards on the edge of those cities need a map check; a mill in a forested county away from them usually does not raise the question, though the study should still carry a dated USDA determination, since the rule bars approval subject to meeting the rural test later.

    Program fit for a Tennessee mill

    • B&I guarantee. The hub names it as the program that finances mills: land, buildings, saw lines, kilns and working capital for an eligible borrower, 85 percent guaranteed below $5 million.
    • REAP. The hub says REAP funds kilns and mill energy systems. Under the rule effective 16 October 2026, a renewable system such as a biomass boiler can receive a grant of at most 25 percent of cost and $500,000, and only after it has operated for 12 months; a REAP guaranteed loan can fund construction.
    • SBA 7(a) and 504 for mills. Twenty Tennessee wood products 7(a) loans and one 504 loan since FY2010.
    • Contract route for equity. A new business with sales contracts adequate for debt service and as long as the loan term needs 10 percent equity rather than 20 or 25 (5001.105(d)(2)).
    • Borrower screens. 5001.127 bars borrowers whose controlling or 20 percent owners have federal judgments, delinquent federal tax or debt, or debarments.

    Financing benchmarks: USDA B&I next to SBA

    Tennessee: SBA lending to wood product manufacturing

    Period7(a) loans7(a) dollars504 loans504 dollars
    FY2010 to FY20167$5.6 million0$0
    FY2017 to FY20192$355,0000$0
    FY2020 to FY20237$3.7 million1$334,000
    FY2024 to FY20264$3.6 million0$0

    Average 7(a) loan, FY2020 to FY2026: $663,955. Average 504 loan: $334,000. Tennessee had fewer than 30 seasoned 7(a) loans for wood product manufacturing; nationally, 7.1% of 1,015 FY2010 to FY2016 loans were charged off, on average 65 months after approval.

    Source: SBA 7(a) and 504 FOIA loan data, as of 30 Sep 2026 (project state; disbursed loans only; cancelled and undisbursed loans excluded).

    B&I termFY2026 ruleFor a Tennessee mill
    Guarantee85% under $5 million; 80% from $5 millionA new mill with kilns may cross $5 million
    Fees3.0% upfront; 0.55% a year (reduced 1.0% and 0.50% with an 80% guarantee)Budget both in sources and uses
    TermUseful life, 40 years at most, no balloonSaw lines and mobile equipment have short lives; amortize accordingly
    CollateralAppraisal under 5001.203; going-concern value deducted before discountingUsed mill equipment can have thin resale value
    EquityExisting 10%; new business 20% balance-sheet or 25% of cost; 10% with long debt-covering sales contractsSupply agreements with flooring or pallet buyers can help
    StudyRequired for a new business borrowing over $1 millionA new mill almost always crosses it

    B&I terms summarised from 91 FR 11272 and 7 CFR 5001.105(d), 5001.203, 5001.306(a)(3) and 5001.402.

    The loss record. The Tennessee SBA file for wood products is small, 11 7(a) loans in FY2020 to FY2026 averaging $663,955, and its seasoned layer is troubling. The pack's loan file shows 3 of the 7 FY2010 to FY2016 Tennessee loans charged off, 42.9% by count and 24.9% of dollars, on average about 89 months after approval; the pack itself reports only that Tennessee had fewer than 30 seasoned loans. Seven loans cannot set a rate, but alongside a national loss rate of 7.1 percent and a shrinking plant count they tell a lender to stress price cycles hard. For context on USDA's own volume, USAspending lists 13 Tennessee B&I guaranteed loans, all industries combined, in FY2024 to FY2026.

    Worked example (illustrative)

    Inputs: a $665,000 B&I loan, the Tennessee average wood products 7(a) loan rounded, at an illustrative 7.75% fixed rate over 15 years, matching a mix of building and saw-line equipment, for a newly formed company upgrading an existing hardwood mill.

    Input or resultValueBasis
    Loan amount$665,000.00Tennessee FY2020 to FY2026 average wood products 7(a) loan ($663,955), rounded
    Interest rate (illustrative, fixed)7.75%Negotiated between lender and borrower (7 CFR 5001.401)
    Term15 years, monthly payments, fully amortizingUseful life, 40 years at most, no balloon (5001.402)
    FY2026 B&I guarantee85%91 FR 11272
    Guaranteed amount$565,250.00Loan x guarantee percentage
    Unguaranteed amount (lender's own risk)$99,750.00Loan minus guaranteed amount
    Upfront guarantee fee (3.00%)$16,957.50Guaranteed amount x fee rate (5001.454)
    Upfront fee if the guarantee issues before construction is complete (+0.50%)$19,783.7591 FR 11272
    First annual retention fee (0.55%)$2,994.66Guaranteed share of the balance after 12 payments x rate (5001.455)
    Monthly payment$6,259.48Level amortization
    Annual debt service$75,113.8112 x monthly payment
    NOI needed for 1.25x coverage$93,892.26Annual debt service x 1.25
    Coverage on that NOI if the rate were 2 points higher1.11xDebt service at 9.75%: $84,537.14
    New business, 25% of project cost route: equity / total cost$221,666.67 / $886,666.675001.105(d)(4)
    New business, 20% balance-sheet equity route (this loan the only debt)$166,250.005001.105(d)(4), debt-to-equity 4:1
    Existing business, 10% of project cost: equity / total cost$73,888.89 / $738,888.895001.105(d)(1)

    Computed in Python from the inputs shown; guarantee, fee and retention rates from 91 FR 11272; equity tests from 7 CFR 5001.105(d). Illustrative, not a quote or a commitment.

    Per-MBF test. At an illustrative output of 8,000 thousand board feet (MBF) a year, the 1.25x NOI of $93,892.26 equals $11.74 per MBF after logs, labour, energy, maintenance and selling costs. Lumber prices can move by far more than that within a year, so the study has to show coverage at the low end of the price range, not the midpoint. The 0.25x cushion is $18,778.45; with the first-year retention fee of $2,994.66, the target becomes $97,635.58.

    Contract-backed equity. If the mill holds purchase agreements that cover debt service and run as long as the loan, 5001.105(d)(2) cuts the new-business equity to $73,888.89 on a $738,888.89 project, $147,777.78 less than the 25 percent route.

    Rate stress. At a rate two points higher, 9.75%, debt service would be $84,537.14 and coverage on the same NOI 1.11x.

    How the numbers scale

    B&I loanFY2026 guaranteeGuaranteed amountUpfront fee (3.0%)Annual debt serviceNOI for 1.25xStudy rule for a new business (5001.306(a)(3))New-business equity at 25% of cost
    $665,00085%$565,250.00$16,957.50$75,113.81$93,892.26Agency may require$221,666.67
    $2,000,00085%$1,700,000.00$51,000.00$225,906.18$282,382.73Required, independent consultant$666,666.67
    $5,500,00080%$4,400,000.00$132,000.00$621,242.00$776,552.50Required, independent consultant$1,833,333.33

    Computed in Python at the same illustrative rate and term; guarantee tiers and fees from 91 FR 11272; study rule from 7 CFR 5001.306(a)(3). A new mill with dry kilns or a biomass system typically sits in the second or third row, where the independent study is required and, above $5,000,000, the guarantee drops to 80 percent.

    What a lender-grade sawmill feasibility study in Tennessee must prove

    1. Log supply: the timber basket within haul distance, ownership mix, any national forest sales, supply agreements and historic delivered-log prices.
    2. Markets by product and grade: flooring, furniture, pallet, crosstie and export buyers, with letters of intent or contracts and price history across a full cycle.
    3. Recovery and throughput: board feet per log, grade yield, shifts and downtime, benchmarked to comparable mills.
    4. By-product revenue and costs: sawdust, chips, bark and slabs, and whether a biomass boiler or kiln uses them.
    5. Labour: headcount and wages against the state's $51,619 average and the 38-employee norm, including safety and training costs.
    6. Capital costs and equipment life: saw line, edgers, kilns, yard equipment and buildings, with lives matching the term.
    7. Working capital: log inventory and lumber in drying, which can tie up months of revenue.
    8. Energy and REAP timing: if a kiln or boiler project plans a REAP grant, the study must show the project works without it, since the grant comes after 12 months of operation.
    9. Eligibility: a 5001.3 map determination and owner screens under 5001.127.

    Risks and mitigants in Tennessee

    Price cycles are the defining risk, and the pack's loan file shows what they do to small mills. Log supply is the second: a mill depends on landowners and timber buyers within a haul radius, and weather or competing mills can cut deliveries. Industry contraction is the third, with 26 fewer Tennessee wood plants in 2023 than in 2019. Mitigants include long-term purchase agreements, diversified products, a by-product strategy, conservative recovery rates and reserves sized for a weak price year.

    Process, documents and why studies come back

    Mill applications reach the Rural Development state office serving Tennessee, in Nashville per the hub, through the lender. The sponsor supplies timber supply data and agreements, customer contracts or letters, equipment quotes and layout, the building and kiln budget, environmental and permit information, management résumés, owners' financial statements and, for an existing mill, three years of production and financial records. Mill studies come back when log costs are taken from one good year, when grade recovery is optimistic, when working capital for drying inventory is missing, or when a REAP grant is counted as construction funding.

    Program example: a Tennessee REAP grant for a biomass boiler

    The hub's precedent file lists a $250,000 REAP grant in 2022 to New River Hardwoods Inc. for a biomass boiler. It is a REAP grant made under the earlier rules, not a B&I loan, and is reported on the hub, not as an engagement of this firm. Under the rule effective 16 October 2026, a grant of that size would require a project costing at least $1,000,000, because the grant may cover no more than 25 percent of cost, and the boiler would have to operate for 12 months before the application.

    Hiring a USDA sawmill feasibility study consultant in Tennessee

    For a new business borrowing more than $1,000,000 under B&I, 7 CFR 5001.306(a)(3)(i) requires a feasibility study by an independent, qualified consultant acceptable to the Agency, scoped by the Agency. The $665,000 example falls below that, so the Agency may require a study but need not, and given the loss record above, many lenders will. A new mill with kilns, or an expansion with a biomass system, normally exceeds the threshold.

    The site's cost page prices standard B&I engagements at $6,900 to $12,500 over six to seven weeks and complex ones, with limited comparables or several sites, at $10,500 to $14,500 over seven to nine weeks; REAP studies with a guaranteed loan over $600,000 run $7,500 to $11,500 over five to seven weeks. A rush in three to four weeks adds 20 to 35 percent. Every engagement includes the five Part 5001 components, market and supply analysis, comparable operator benchmarks, the projection and Excel model with sensitivity tables, a management assessment, one revision round and the written acceptance guarantee. Timber cruises, engineering and appraisals are separate.

    A sawmill feasibility study consultant should explain before you engage how log supply and lumber prices will be tested across a cycle. The homepage describes the work of a USDA feasibility study consultant with lenders and the Agency, and the national sawmill feasibility study for USDA financing page covers mills across states. Send the site, products, capacity, project cost and lender status through the contact page; the response comes within one business day.

    Last updated 2026-11-08

    David Miller, CPA

    USDA Feasibility, Inc.

    Frequently Asked Questions

    Does a Tennessee sawmill need a feasibility study for a B&I loan?

    If the borrower is a new business and the loan exceeds $1,000,000, yes (5001.306(a)(3)(i)). Tennessee wood products 7(a) loans averaged $663,955 in FY2020 to FY2026, below the line, but new mills with kilns usually borrow more. For smaller loans the Agency may still require a study, and the weak seasoned loan record gives lenders reason to ask.

    What does a sawmill feasibility study consultant cost in Tennessee?

    The site's cost page gives $6,900 to $12,500 for a standard B&I study and $10,500 to $14,500 for complex work, both as fixed fees; REAP studies with a guaranteed loan above $600,000 run $7,500 to $11,500. A mill adding kilns and a biomass boiler, with REAP and B&I together, is usually complex. USDA's upfront fee on the $665,000 example is $16,957.50.

    How long does a sawmill study take?

    Per the cost page, six to seven weeks for standard B&I work and seven to nine for complex, with a three to four-week rush at a premium. Log supply and buyer interviews take the most time. Having timber data, customer letters and equipment quotes ready at kick-off keeps the schedule.

    Who can prepare a USDA sawmill feasibility study?

    The author must be an independent, qualified consultant the Agency finds acceptable. A sawmill equipment dealer, a timber buyer or a lumber broker can supply information but not the conclusions, because each profits if the mill is built. USDA publishes no list; the Rural Development state office serving Tennessee accepts or rejects the preparer for each application.

    How long is a sawmill feasibility study valid?

    Part 5001 does not fix a validity period. The cost page describes data generally inside 18 months as USDA's working standard, and appraisals may be no more than a year old (5001.203). Lumber and log prices can move sharply within months, so update price assumptions if the study is more than a few months old at filing.

    Can one study support SBA and B&I mill loans?

    Yes, if both lenders are named and both structures modelled. On the $665,000 example, B&I guarantees $565,250.00 and 7(a) $498,750.00, with a B&I fee of $16,957.50 against a 7(a) guaranty-fee ceiling of $14,962.50. Equipment-heavy mills often need different terms for real estate and machinery, and the study should show coverage under each lender's structure.

    Can REAP pay for a dry kiln or biomass boiler at a Tennessee mill?

    REAP can support renewable systems and efficiency improvements, and the hub says it funds kilns and mill energy systems. Under the rule effective 16 October 2026, the grant is at most 25 percent of cost and $500,000 for renewable systems, and the project must operate for 12 months first. The REAP guaranteed loan can fund the build, which is what a lender will underwrite.

    Why have Tennessee wood products loans performed poorly?

    The pack's loan file shows 3 of 7 seasoned Tennessee loans charged off, about 89 months after approval on average, against 7.1 percent nationally. Seven loans are too few to explain, but late failures fit an industry exposed to price cycles and log supply. A study should test coverage at low lumber prices and high log costs, not the averages.

    Is a mill in Fentress, Hardeman or Wayne County eligible for B&I?

    Very likely. All three are non-metro counties in the pack, with 11, 11 and 10 wood plants, and none contains a city over 50,000 on the hub's 2020 list. Eligibility is still decided parcel by parcel under 5001.3, so the study should attach a dated USDA map determination for the mill site and any separate log yard.

    Sources

    1. U.S. Census Bureau, County Business Patterns 2019 and 2023, state and county files: https://www2.census.gov/programs-surveys/cbp/datasets/
    2. U.S. Census Bureau, Vintage 2025 population estimates (state, county and incorporated places): https://www2.census.gov/programs-surveys/popest/datasets/2020-2025/
    3. Office of Management and Budget, metropolitan and micropolitan delineation, July 2023: https://www2.census.gov/programs-surveys/metro-micro/geographies/reference-files/2023/delineation-files/list1_2023.xlsx
    4. U.S. Small Business Administration, 7(a) and 504 FOIA loan data, as of 30 Sep 2026: https://data.sba.gov/dataset/7-a-504-foia
    5. 7 CFR Part 5001, CFR 2026 edition (govinfo): https://www.govinfo.gov/content/pkg/CFR-2026-title7-vol15/xml/CFR-2026-title7-vol15-part5001.xml
    6. 91 FR 11272, OneRD FY2026 guarantee fee, retention fee and guarantee percentage notice (govinfo): https://www.govinfo.gov/content/pkg/FR-2026-03-09/html/2026-04581.htm
    7. 13 CFR Part 120, SBA business loan programs: https://www.ecfr.gov/current/title-13/chapter-I/part-120
    8. REAP final rule, 91 FR 62600 (1 Oct 2026): https://www.govinfo.gov/content/pkg/FR-2026-10-01/html/2026-20178.htm
    9. USAspending.gov prime award data by assistance listing 10.768, FY2024 to FY2026: https://www.usaspending.gov
    10. Hardwood region context, the 2020 city list and the New River Hardwoods REAP grant, as cited on the Tennessee hub
    11. Site pages: /usda-feasibility-study-cost and /contact

    Data current as of November 2026.

    Ready to Start Your USDA Project?

    Get your free consultation today and take the first step toward securing USDA funding for your rural development project.

    Our USDA feasibility study consultants scope every engagement against the five Part 5001 components in a free consultation.